HomeMy WebLinkAbout _ 4.11(a)--Accept Bid Schedule No. 5234, South Bonnyview I-5 Bechelli Project GI �" Y C� F
� � �- ' � ° � � i � CITY OF REDDING
��
REPORT TO THE CITY COUNCIL
MEETING DATE: June 16,2026 FROM: Michael Webb, Assistant City
ITEM NO. 4.11(a) Manager/Public Works
Director
***APPROVED BY***
�� � 3,�� �.nu„
����
� � � �
�
�� s � ,,��
� 5� � �� �� �� �,��,�
� � � =µ
1" irel'We, .. v: aty Vf� a�et Rubliu\ c*rA�.;�Uectetcrr f���?02G �}F������'�1'�3(JX �,�ti"�'��.��23a3�TG"I �,. �f������.7
mwebb@cityofredding.org wtarbox@cityofredding.gov
SUBJECT: 4.11(a)--Accept Bid Sched�ule No. 5234, South Bonnyview I-5 Bechelli Project
Recommendation
Accept Bid Negotiation No. 5234, South Bonnyview I-5 Bechelli Project, awarded to J.F. Shea
Construction, Inc., as satisfactorily complete, with a final cost of$5,032,522.63.
Fiscal Impact
Citywide Traffic Impact Fee (TIF) ($4,000,000) and California Department of Transportation
(CalTrans) State Highway Operation Protection Program (SHOPP) Minor A ($1,250,000) budget
in the amount of $5,250,000 was approved for this project for Fiscal Year 2021-22. The total
project cost, including surveying, design, bidding, construction, �ield engineering, inspection,
and contract administration, is $5,032,522.63
AZteNnative Action
The City Council (Council) may choose to not accept the project as satisfactorily complete, and
advise staff on how to proceed.
Background
J.F. Shea Construction, Inc. has completed all items of work on the South Bonnyview I-5
Bechelli Project as o�April 25, 2025, which was within the contract time frame. The project
warranty period expires one y�ar from the completion date of April 25, 2025, and the Public
Works Department subsequently filed a notice of completion with the County.
At its meeting of December 2, 2021, the Council awarded a construction eontract to J.F. Shea
Construction, Inc. of Redding, for $3,403,836 and approved a $340,000 construction
eontingeney fund. Also authorized was $610,000 for eontract administration and construerion
inspection fees and $830,000 for project development costs, and the City Manager was
authorized to approve additional increases in either the construction management or eonstruction
Report to Redding City Council June 2,2026
Re: 4.11(a)--Accept Bia'Schedule No. 5234,South Bonnyview 1-5 Bechelli Project Page 2
contingency amounts up to a total of $50,000, for a total authorized amount of $5,233,836.
Project development costs include engineering, environmental, and consultant services. Due to
the project extending longer than anticipated for design changes during construction and claims
resolution, additional staff time was needed to colnplete the project. Project contingency funds in
the amount of$74,000 were transferred to contract administration and construction inspection to
cover sta�f time costs reducing the contingency fund to $266,000. During construction, there
were nine change orders in the amount of$114,735.57, leaving a balance of$151,264.43 in the
contingency fund. The final project cost was $5,032,522.63.
Cost Summary
Awarded Amounts Actual Cost
Project Development Costs $830,000 $830,000
Construction Contract
+
3 743 836
Contin enc
$
, ,
Construction Contract + �
: 3 518 571.57
.��� :: � �°' _ $
, �
Contract Chan e Orders
Contract Administration & �61�0,000 $683,951.06
Ins ection
Additional City Manager �50,000 $0
Authorit
Total $5,233,836 $5,032,522.63
The project involved improvements to the Southbound South Bonnyview Off Ramp consisting of
widening and lengthening the ramp, constructing a 1000-foot auxiliary lane prior to the ramp and
traffic signal modifications for the additional lane configuration created at the intersection.
Additionally, the project also included improvements to the Northbound South Bonnyview Off
Ramp which was widened consisting of new retaining walls, additional asphalt pavement and
striping.
Environmental Review
This action is not a project as defined by the California Environmental Quality Act, and no
action is required. On December 2, 2021, the Council determined that the South Bonnyview I-5
Bechelli Project was categorically exempt from review under the California Environmental
Quality Act Guidelines,pursuant to Section 15301(c)—Existing Facilities.
Council Pr�iority/City Manager Goals
• This agenda item is a routine operational item.
c: Nick Visconti, Construction Manager
Attachments
Previous Staff Report- December 7, 2021, Award JFShea
�,
,�� .��` CITY OF REDDING
: � _ :�'
REPORT TO THE CITY COUNCIL
MEETING DATE: December 7, 2021 FROM: Chuck Aukland,Public
ITEM NO. 4.11(c) Works Director
***APPROVED BY***
�
,� �._ s.N,.��
��� ���
G�kl�nd,H'�ibli�W'�a�s 27qr��t � 1/:?412421 � : �� �,,,ci�y�t�,�x ����•�c�Gir „a� ��s��wiG��t�w���k�r itt���zt�zt
caulzland@ci.redding.ca.us btippin@cityofredding.org
SUBJECT: 4.11(c)--Award Bid Schedule No. 5234 (Job Order No. 2644) South Bonnyview
I-5 Bechelli Project
Recommendation
Authorize the following actions relative to Bid Schedule No. 5234 (Job No. 2644) South
Bonnyview I-5 Bechelli Project:
(1) Award to JF Shea Construction in the amount of$3,403,836;
(2) Approve an additional $610,000 to cover the cost of administration and inspection fees;
and$830,000 for project development costs;
(3) Approve $340,000 to provide construction contingency funding;
(4) Authorize the City Manager to approve additional increases in either the construction
management or construction contingency amounts up to a total of$50,000; and
(5) Find that the Project is categorically exempt from the California Environmental Quality
Act per Section 15302(c)—Replacement or Reconstruction.
Fiscal Impact
The South Bonnyview Interstate-5 (I-5) Bechelli Project (Project) is being funded by the
Citywide Traffic Impact Fee (TIF) and California Department of Transportation (Caltrans) State
Highway Operation Protection Program (SIHOPP) Minor A. Caltrans funding contribution for
construction cost is $1.25 million. There is $5,250,000 budgeted for the total project.
Cost Summa
Item Estimated
Pro'ect Develo ment Costs $830,000
Construction Contract+ Contin enc $3,743,836
Contract Administration, Ins ection, Testin $610,000
Additional Cit Mana er Authorit $50,000
Total Pro'ect Costs $5,233,836
Pro'ect Bud et $5,250,000
Report to Redding City Council December 2,2021
Re: 4.11(c)--Award BS No. 5234 South Bonnyview 1-5 Bechelli Project Page 2
Project cost components are estimates and some shifting of the project development,
construction management, and construction contingency funds may be necessary to balance the
project within the approved budget.
Alter�native Action
The City Council (Council) could choose not to award the bid for the South Bonnyview I-5
Bechelli Project and provide staff with alternate direction. If the project is not awarded, the
proposed project improvements will not be constructed which are required for regional
development and I-5 operations. In addition, the City of Redding and Caltrans would lose $1.25
million in project funding.
Background/Analysis
Attached is a tabulation of bids received and opened on November 23, 2021, for the South
Bonnyview I-5 Bechelli Project. The low bid in the amount of$3,403,836 was received from JF
Shea Construction of Redding, California. The engineer's estimate was $3,750,169. Total project
development costs for this project are estimated to be $830,000. Project development costs
include engineering, surveying, right-of-way, environmental, consultant services, and permit
fees.
At its regular meeting on October 3, 2017, the Council approved the Project St�udy Report (PSR)
for the South Bonnyview/I-5 Interchange Improvements Project. The PSR identified long term
planned improvements to the interchange needed in anticipation of future traffic growth from
new development over a 40-year time frame. Among other significant improvements ultimately
leading to a divergent diamond interchange, the PSR identified I-5 off ramp improvements
including but not limited to:
� Southbound Off Ramp
o Widen and lengthen ramp
o Traffic signal modifications
o Construct 1000-foot minimum auxiliary lane prior to ramp
� Northbound Off Ramp
o Widen ramp to existing freeway gore point
These improvements will increase off ramp capacity in the short term due to proposed land
development in the area as well as address existing ramp deficiencies. The majority of the
proposed ramp improvements are located on facilities owned and operated by Caltrans, and its
approval is required. Caltrans is interested in partnering on the project to facilitate other
operational and safety deficiency corrections beyond the capacity improvements required by
development as indicated in the PSR. As such, the City and Caltrans have agreed to partner
together to complete the project(s). Caltrans will provide a funding contribution, project
oversight, and approvals through the Cooperative Agreement approved by the Council on
November 17, 2020. GHD Inc. will provide supplemental staff to provide construetion
management and inspection services for this project as approved by the Council on November 2,
2021.
Report to Redding City Council December 2,2021
Re: 4.11(c)--Award BS No. 5234 South Bonnyview 1-5 Bechelli Project Page 3
Additional improvements associated with the ultimate interchange design are currently
underway. The Bechelli Lane/South Bonnyview Road Roundabout Project is currently
advertising for construction bids, and staff will return to the Council for award in January 2022.
Both projects should be complete prior to occupancy of the new Costco Warehouse in the Fall of
2022. Staff continues to seek additional grant funding sources to complete the ultimate divergent
diamond interchange and the roundabout proposed for the Churn Creek intersection on the east
side of the interchange.
Staff has determined that the project qualifies as Categorically Exempt from environmental
review under California Environmental Quality Act Guidelines Section 15302. The project area
does not have significant values for wildlife habitat or other environmental resources, and the
project has no potential to have a significant effect on the environment.
Council Priority/City Manager Goals
• Public Safety — "Work to improve all aspects of public safety to help people feel secure
and safe where they live, work, and play in the City of Redding."
• Government of the 21st Century — `Be relevant and proactive to the opportunities and
challenges of today's residents and workforce. Anticipate the future to make better
decisions today."
• Economic Development — "Facilitate and become a catalyst for economic development
in Redding to create jobs, retain current businesses and attract new ones, and encourage
investment in the community."
Attachments
Bid Tabulation
Location map
Notice of Exemption
10-3-17 Staff Report (available online)
ll-17-20 Caltrans COOP staff rpt(available online)
11-2-21 Staff Report (available online)