Loading...
HomeMy WebLinkAbout _ 4.11(a)--Retention Reduction Bid Neg. 5451 RDD Airport Runway 16-34, Taxiway and MAGVAR Improvements GI �" Y C� F � � �- ' � ° � � i � CITY OF REDDING �� REPORT TO THE CITY COUNCIL MEETING DATE: December 16, 2025 FROM: Michael Webb, Public Works ITEM NO. 4.11(a) Director ***APPROVED BY*** ie ael � iiEali� oaks L)arector t2:�'S1242� t�s�a a �, t�t � 12,�11(202� mwebb@cityofredding.org sbade@cityofredding.org SUBJECT: 4.ll(a)--Approve a Partial Retention Reduction Release for Bid Negotiation No. 5451 Redding Regional Airport Runway 16-34 and Taxiway Connectors Rehabilitation and MAGVAR Im rovements Pro�ect Recommendation Authorize staff to reduce the retention by five percent, thereby releasing $1,208,464.75 to Redding Airport Constructors, the contractor, for Bid Negotiation No. 5451 (Job No. 9944-33) Redding Airport Runway 16-34 and Taxiway Connectors Rehabilitation and MAGVAR Improvements Project. Fiscal Impact There is no fiscal impact to the Redding Regional Airport Runway 16-34 and Taxiway Connectors Rehabilitation and MAGVAR Improvements Project (Project) as release of these retention funds will be used to pay subcontractors for work that was already completed. Retention is withheld from progress payments on all Public Works construction projects for numerous reasons, most often to reserve for any claims that may arise from underpayment to the subcontractors and materials suppliers. The release of these retention funds will satisfy this condition. There have been no claims from subcontractors or materials suppliers on this project with sufficient funds remaining to complete the project. Alternative Actzon The City Council (Council) may choose not to reduce the retention to Redding Airport Constructors (Contractor), and provide staff with alternate direction. Without this release, the City of Redding (City) would continue to withhold five percent r�tention on previous and forthcoming project progress payments until project completion which is currently unknown due to weather conditions being unfavorable to perform final runway striping and final grading. This would cause Redding Airport Constructors (Contraetor) and its subeontractors, to eontinue carrying the burden of covering costs without compensation. Report to Redding City Council December 12, 2025 Re: 4.11(a)--Retention Reduction Bid Neg. 5451 RDD Airport Runway 16-34, Taxiway and MAGVAR Improvements Page 2 Background/Analysis At its regular meeting on May 6, 2025, the Council awarded the construction contract for the project to the low bidder, Redding Airport Constructors, in the amount of$20,111,190 for the Base Bid and an additional $7,666,587 for Additive Alternate-1 for a total amount of $27,777,777. The contractor began work on June 13, 2025, and the work was nearly completed in November 2025. As of the end of November 2025, the remaining work includes runway signage, taxiway reflectors, runway striping/markings and minor punch list items. As stated above, sufficient funds remain to complete the project. The contractor has requested, in the attached correspondence, a partial release of retention funds that would reduce monies withheld on all completed and partially accepted bid items as per the contract specification section 90-06 (a.l), "Contractor may request release of retainage on work that has been partially accepted by the Owner in accordance with section 50-14". Additionally, Per Public Contract Code (PCC) section 9203, "at any time after 50 percent of the work has been completed, if the legislative body finds that satisfactory progress is being made, it may make any of the remaining progress payments in full for actual work completed." As 95-percent of the contract has been completed, staff is requesting, in accordance with the Contract Documents and in accordance with the PCC to release retention on all partially accepted bid items of work withheld and be released to the contractor. EnviNonmental Review On May 6, 2025, Council determined that the project is categorically exempt from environmental review under the California Environmental Quality Act, pursuant to Section 15301. Existing Facilities, Section 15302. Replacement or Reconstruction, and Section 15303. New Construction ar Conversion of Small Structures. No further action is required. On February 21, 2024, the FAA determined that the project is categorically excluded from environmental review under the National Environmental Policy Act, pursuant to FAA Order 1050.1F Council Priority/City Manage�^ Goals This is a routine operational item. Attachments Redding Airport Constructors Request for Retention Letter(with revised address) May 6, 2025 Staff Report . �---r� : /�IRRORT GQNST�UCTORS '' 11555 Ll�ahlis�Banlevard P:{�Box 2�1�9 I�ublisi,Cal�faiYi�a 94568-2909 CONTRAGTORS LI�'E�ISE NO.I 116768 December 2, 2025 RAC Letter Number 724101-174 Mead&Hunt 1360 19`h Hole Dr, Ste. 200 Windsor, CA 95492 Attention: Edoardo Barber,PE Subject: Redding Regional Airport Runway Rehabilitation RAC Job No. 724101 Request for Information No.48-Section 90-06—Partial Payments—Reduction in Retention Mr. Barber, Reference is made to Section 90-06,Partial Payments, of the FAA General Contract Provisions and to previous discussions between Redding Airport Constructors(RAC) and the City of Redding (City)regarding reducing the overall amount retained on the contract. Please find this correspondence as RAC's formal request to reduce the current retention on the contract from 5%to a percentage equaling the amount of$41,400. We look forward to the City's favorable response to this request and the processing of this on the December estimate. Should you have any questions regarding this matter,please contact our Project Of�ce. Respectfully, REDDING AIRPORT CONSTRUCTORS � Brian O'Rourke Project Director Cc: R.Peterson, T. McGrew,B. Brown,P. Davos,RFI 48 � � �' � �i � � � � ' � � � � � � CITY OF REDDING ..� F�EPORT TO TFIE CITY COUNCIL MEETING DATE: May 6, 2025 FROM: Michael Webb, Public Works ITEM NO. 9.11(c) Director ***APPROVED BY*** , �.� � � a� �w� rc ��l e , aal�li�: c�rks II�iee�tc�r 4r''��,`�(12�5 a-y sppit�„C'��k an��.e� �� 4,!3t�/2G?5 � mwebb@cityofredding.org btippin@cityofredding.org SUBJECT: 9.11(c)--Award Bid Negotiation N�o. 5451 Redding Regional Airport Runway 16- 34 and Taxiwa Connectors Rehabilitation and MAGVAR Im rovements Recommendation Authorize and approve the following regarding Bid Negotiation No. 5451 (Job No. 9944-33), Redding Regional Airport Runway 16-34 and Taxiway Connectors Rehabilitation and MAGVAR Improvements :Project(Project): (1) Award the Project to Redding Airport Constructors in the amount of$20,111,190 for the Base Bid, and an additional $7,666,587 for Additive Alternate 1 for a total amount of $27,'7'7'7,777; (2) Authorize the City Manager, or designee, to approve, execute, and appropriate funds for amendments up to 15 percent of the final Federal Aviation Administration Airport Improvement Program grant for contract change orders or other eligible contract modifications; (3) Approve $270,000 for the cost of City administration and $1,717,000 in construction administration and inspection fees for Mead & Hunt Inc. for a total amount of $1,987,000; (4) Approve $1,5'73,336 for project development fees; (5) Authorize City Manager, or designee, to sign and execute an Authorization of Services (tentatively numbered 25-06) in the amount of $1,'71'7,000 for the purpose of Construction Administration Services for the Project with Mead & Hunt Inc. (C-8976); and (6) Find that the Project is categorically exempt from environmental review under the California Environmental Quality Act, pursuant to Section 15301, Existing Facilities; Section 15302, Replacement or Reconstruction; and Section 15303, New Construction or Conversion of Small Structures. Fiscal Impact The Redding Regional Airport (RD:D) Runway 16-34 and Taxiway Connectars Rehabilitation and MAGVAR Improvements Project (Project) is funded by federal transportation capital improvement grants under the Federal Aviation Administration (FAA) Airport Improvement Report to Redding City Council Apri130, 2025 Re: 9.11(c)--Awara'Bid RDD Runway 16-34& Taxiway Connectors Rehabilitation &MAGVAR Improvements Page 2 Program at a rate of ninety-five percent with the remaining five percent City match funds coming from revenues generated by the RDD Passenger Facility Charge (PFC) program. On October l, 2024 City Council (Council) authorized the City Manager to appropriate all grants �unds received to the City of Redding's Airport Funds for this project - authorized funding includes $29,938,491 in various FAA grant funds and $1,665,008 in City match funds for a total amount of$31,603,499. Cost Summar Table Item Estimated Pro�ect Develo ment Costs $1,573,336 Construction Contract $27,777,777 Contract Administration, Ins ection, Testin $1,987,000 Total Pro'ect Costs $31,338,113 Pro'ect Bud et $31,603,499 Alter�native Action The Council may choose not to authorize award of the bid for the project and provide staff with alternate direction. If Council chooses not to award the project, the City would lose a fairly- priced bid from a 1oca1 contractor; risk increasing project costs due to escalation in materials and labor pricing; and likely, if the project were to be rebid, it would delay critical runway improvements included in this project to late 2026 or even 2027. In addition, the City may potentially lose out on the FAA $30 million grant funding for the project by disrupting an established timeline in which final bids are needed in order to submit a grant application. Background/Analysis The City is responsible for maintaining runways, taxiways, and other paved surfaces at :RDD in sufficient condition to meet federal regulations and airport certification requirements while facilitating safe use of the airport. The proposed project will extend the useful life of aeronautical infrastructure at RDD by rehabilitating the runway pavement; reconstructing taxiway connectors and blast-pads; replacing high intensity runway lighting (HIRL); addressing magnetic variance on Runway 16-34; and updating airfield signage to meet the latest FAA standards. This project is crucial for airfield operations as the most recent runway rehabilitation at RDD took place in 2001. Furthermore, replacement of I�IRLs at RDD will increase the safety and efficiency of night-time and low-visibility operations. The City's Airports Division intended to originally complete the project in October of 2024 with grant funding anticipated in Federal Fiscal Year (FFY) 2024. Ultimately, the FAA could not award an FFY 2024 grant far the requested amount at the time because of an FAA administrative error coupled with funding limitations resulting �rom the �ederal budget process including the repeated use of continuing resolutions which held in place previous funding levels. Due to the FAA's inability to fund this project in FFY 2024, the City postponed the project into calendar year 2025 with the intention of requesting an FFY 2025 grant from the FAA. At this time, funding is awaiting disbursement into the FAA system - the FAA San Francisco Airport District Office has indicated that this project is a top priority for FFY 2025. Attached is a tabulation of bids opened on March 5, 2024. The low bid amount of$2'7,777,'7'7'7, comprised of a Base Bid and Bid Alternative 1 of$20,111,190 and $7,666,587, respectively, was received from Redding Airport Constructors, a Joint Venture of J.F. Shea Construction, Inc. of Report to Redding City Council Apri130, 2025 Re: 9.11(c)--Awara'Bid RDD Runway 16-34& Taxiway Connectors Rehabilitation &MAGVAR Improvements Page 3 Redding, California, and DeSilva Gates Construction LLC of Dublin, California. The contractor has agreed to honor this bid so long as a notice to proceed is issued by June 5, 2025. The engineer's estimate for the Base Bid was $16,361,895 and $'7,670,140 for Bid Alternative 1 for a total of amount of$24,032,035. Total project development costs are estimated to be $1,573,336. Project development costs include engineering, surveying, environmental, and consultant services. The City has already selected Mead & Hunt Inc. for construction management and inspection (CM) services due to their expertise in airport construction and regulations per the consulting and professional services agreement (C-89'76) executed on July 23, 2021 and attached to this report. For AIP projects, the FAA requires the airport sponsors to competitively select from among qualified consultants for various categories of AIP-related work including construction management. As the selected qualified consultant, Mead & I�unt, Inc. has already been contracted for engineering design and construction management for other phases of the project including the Preliminary Design Concept Study, Design Phase 2, and Procurement. Under the existing consulting and professional services agreement(C-89'76) a new Authorization of Service in an amount not to exceed $1,717,000 would be issued to Mead & I�unt, Inc. �or construction management on the upcoming project phase. The project includes the installation of storm drain pipe, cold milling the existing asphalt, repairing cracks after cold milling, paving multiple courses and grade transitions on runway shoulders, constructing runway grooving, constructing a blast pad, application of pavement markings, and installation of signage and runway lighting. Project Risks While the FAA continues to reassure staff that the project at RDD is the number one priority for funding at the district office and regional level, the FAA is unable to make any guarantees of funding prior to announcing grant awards. Based on the level of communications and reassurances made as to the priority of the project, staff is confident that this project will receive an award by July 2025. In order to meet the target construction period in late September and early October, the City needs to award the project to RAC no later than June 6, 2025 - otherwise, the received bids may expire as RAC has agreed to hold the bids to this respective date. By awarding the project prior to June 6, 2025, the City will be awarding the project without receiving an FFY 2025 FAA AIl' grant which staff anticipates receiving before July 2025. Conversely, if the FAA does not award the FFY 2025 FAA AIP grant to the City, staff have conservatively identified approximately $2,000,000 in potential contract payments that could likely be due to the contractor in the event that the City is forced to terminate the contract as a result of not receiving the grant. Some o� the potential contract payments likely due to the contractor would be eligible for reimbursement by the FAA through grants already issued, RD:D FAA entitlement funds or, potentially, RDD passenger fare charge (PFC) funds in the amount of approximately$3.6 million. As a side note, the reimbursement eligibility of any contract payments is dependent on the completion of ineasurable units of work - as decided by the FAA. Funding for any potential required contract payments determined by the FAA to be ineligible for reimbursement would Report to Redding City Council Apri130, 2025 Re: 9.11(c)--Awara'Bid RDD Runway 16-34& Taxiway Connectors Rehabilitation &MAGVAR Improvements Page 4 need to be provided by other funding sources within the City. In the unlikely event of contract termination, staff will present to Council the amounts owed to the contractor with the recommended sources of funding as described above. Additionally, any RDD FAA entitlement or RDD PFC funding utilized for reimbursement in the event of contract termination will likely create a funding need for the project in the future. Environmental Review Staff has determined that the project is categorically exempt from environmental review under the California Environmental Quality Act, pursuant to Section 15301. Existing Facilities, Section 15302. Replacement or Reconstruction, and Section 15303. New Construction or Conversion of Small Structures. Class 1 exemptions include the minor alteration of existing public structures and facilities. Class 2 exemptions consists of replacement or reconstruction where the new structure will be located on the same site and will have substantially the same purpose and capacity. Class 3 exemptions consist of construction and location of new small facilities and equipment, ar conversion of existing structures. The existing airport facilities will be rehabilitated and improved to better serve the public. The project will be located within the existing airport facility and the project will result in a negligible expansion of use, as the project does not increase airport capacity. The action area has been reviewed and it does not have significant values for wildlife habitat or other environmental resources. The project has no potential to have a significant effect on the environment. On February 21, 2024 the FAA determined that the project is categorically excluded from environmental review under the National Environmental Policy Act, pursuant to FAA Order 10501F Council Priority/City ManageN Goals • Government of the 21 st Century — `Be relevant and proactive to the opportunities and challenges of today's residents and workforce. Anticipate the future to make better decisions today." Attachments ^Bid Tab ^Location Map NOE RDD Runway 16-34 Rehab & MAGVAR Imp NEPA FAA Redding RDD Rwy 16-34:Phase 2 Improvements_ltr 2-21-2024 G8976 - Agreement- 2021 - Mead & Hunt, Inc Previous Staff Report