HomeMy WebLinkAbout _ 4.11(c)--Consider Approval of the Magnums Area Remote Sewer Project GI �" Y C� F
� � �- ' � ° � � i � CITY OF REDDING
��
REPORT TO THE CITY COUNCIL
MEETING DATE: October 7, 2025 FROM: Michael Webb, Public Works
ITEM NO. 4.11(c) Director
***APPROVED BY***
ie ael � iiEali� oaks L)arector �3(?9/242� t�s�a a �, t�t � 10(1(202�
mwebb@cityofredding.org sbade@cityofredding.org
SUBJECT: 4.ll(c)--Adopt the Mitigated Negative Declaration and Mitigation Monitoring
Pro ram; and Approve the Ma ums Area Remote Sewer Project
Recommendation
Authorize and approve the following actions relative to the Magnums Area Remote Sewer
Proj ect:
(1) Adopt the Mitigated Negative Declaration, and the Mitigation Monitoring and
Environmental Commitment Program; and
(2) Approve the Magnums Area Remote Sewer Project as described, thereby satisfying the
requirements of the California Environmental Quality Act Guidelines §15074.
Fiscal Impact
Approval of the Magnums Area Remote Sewer (Project) along with adoption of the Mitigated
Negative Declaration (MND) and the Mitigation Monitoring Program (MMP) allows the project
to move toward the final design and construction phases. There is no fiscal impact as a direct
result of adopting the MND, MMP, and approving the project.
The project construction costs are estimated to be approximately $3.4 million and has been
budgeted through the City of Redding's (City) Wastewater Utility Fund.
Alternative Actzon
The City Council (Council) may choose not to adopt the 1VIND and the MMP, and not approve
the project as described. Without approval, the project would not be able to proceed as a City
project, as it would not comply with the California Environmental Quality Act (CEQA).
Report to Redding City Council October 1,2025
Re: 4.11(c)--ConsiderApproval of the MagnumsArea Remote Sewer Project Page 2
Background/Analysis
The project will replace existing sewer lines to address deterioration due to age, lines which
require a high level of maintenance, and/or lines which are undersized. Construction activities
would span approximately 5,060-feet long across multiple locations, from Mishka Court,
Greenback Lane, Calexico Drive, Dickson Drive, E. Keswick Dam Road, Lake Boulevard,
Shamrock Street, sections along the back sections of Magnums Way and Guinevere Court and
along portions o�the railroad.
The project would require trenching, sub-surface pipe bursting, vegetation removal, utility
relocation, paving, sign installation, and striping. The sub-surface pipe bursting method will be
used to minimize stream impacts in multiple locations. This method will require an excavated pit
on each end of the sewer line. The new sewer pipe will be placed in the pit and fed into the
existing pipe replacing it in its original alignment.
The majority of work would occur within City right-of-way and utility easement areas; however,
temporary permits to enter and construct on adjacent private lands may be needed to conform
driveways, replace/relocate utilities, or modify drainage. Permanent right-of-way acquisition
would not be required. Staging areas will occur within City right-of-way and on City property,
and one-way traffic control wi11 be required for work near roadways.
An Initial St�udy (IS) was prepared to satisfy the requirements of the CEQA. It describes why the
project is being proposed and the potential impacts to the existing environment. The IS shows
that the proposed project could have a significant effect on biological resources, but with
implementation of mitigation measures, those impacts will be reduced to a level considered less
than significant. The mitigation and conservation measures to be implemented are common
practices and include, but are not limited to, biological pre-construction surveys, environmental
awareness training, impact minimization, and sediment control measures.
Based on the conclusions made in the IS, an MND was prepared. The MND describes the
project, including mitigation measures, and makes the determination that there will be no
significant effect on the environment provided that the defined mitigation measures are
implemented as part of the project. In addition, an MMP has been written and incorporated into
the MND (CEQA Section 21081.6). The MMP will be used by City staff, contractors, agencies,
and monitoring personnel during and after the project to ensure effective implementation of the
adopted mitigation measures outlined in the MND.
The IS/MND/MMP documents were sent to the State Clearinghouse for a 30-day public review
period and distribution to pertinent state agencies. They were sent to local resource agencies, the
Shasta County C1erk, and posted on the Public Works Department website. A public notice was
also sent to landowners in the vicinity of the project and posted in the local newspaper. No
comments were received during the public review period.
Environmental Review
The City is the lead agency for the project pursuant to CEQA. As the lead CEQA agency, the
Council is authorized to adopt the MND per Redding Municipal Code Section §18.24.070.E and
state law. Upon adoption of the MND and approval of the project by the Council, a Notice of
Determination will be filed with the Shasta County Clerk's Office and the State Clearinghouse,
completing the environmental review process. The IS/MND is available in the Public Works
Department and is currently available online at
Report to Redding City Council October 1,2025
Re: 4.11(c)--ConsiderApproval of the MagnumsArea Remote Sewer Project Page 3
h�t s.11w��e��t ��r�c�cli� . �c�v/ csv��������tld� ��� ��tsl �bli� vac��l�sl�a�virc�r����nt�1 ar�a �
���tli���xAp1��.
Council Priority/City Manager Goals
• This is a routine operational item.
Attachments
^Location Map
Mitigated Negative Declaration
Mitigation Monitoring and Environmental Commitment Program
�,.,�„ .w""� � "°"� �.k�Y s':d" . � �. ��.
� � � �g �� '�....
4-Rk' � ' '.,,� �"."... �"�tt A � � . ��y }1
��.� • � "a-^��p�.y��Y � � �� ��'^v �lN��qi ���� n�£ '�M u%.C.����N5��.
`Yv:p v .�,, �"R'�� * '� ',�..., ..:��i°„s p� t ryry}� � 2aA`" �` ..
t � `'�p �"�, �t �' r} " y� �.� �S,�
�� � � �
'� '� �� +�`s �, �'�� �d"' �..,:�� `� � � �x; �'�,`��k�a�'� �„�, "` '� � �� � .
� `` 4� i �'" 'a. 2 �.�
� �, , �;,�" f'�.', . � "^�,�" ..�`.�'��' n: m
F� �; `�n. �. $t � .s`�a..�.
� � ;k � �� e � �,� �,i3 �"��. x� � ;� i f� w��, ���
"�� � .�.`���' sE' � t' ,�� � .�.
�
�. � '. � . . �, .
,�`�^,..,��""" �" �,����,��„ � d�,�" .�t �., a �,.. � ' �,''�,„�.� _..�,..
� ry i �
�d �,�' .. �� � .�` � `¢r�.,.M:,�
�N'"� x �, ��� � , s^ ''� ia`�
��� � ��n.�' * � �'S�� � iW��f"�.,..
, .,., �' .. .. +'n �� 4 fl
,. ,. . ,� Y *. : ya �"*
�.
� ' c;.; ...,.:. ..+���'^�&�,F�' `'�, .. „� . .�
� r9 ��
.,� A�. � 'r Q"�.+��'R�#i°A�
` � � a .b-.'"�`� „ 2 �;� a:v�dY�P .�.
���,.�� �. ,� , .� �; �'`� `' � ,.. '�°, �� �.
�� `� 40e626612 � �� ; �
w
.
�
« , � z
x � �22.�oa3as - � k �h
�.
�
, �� � � ��
�
�
�u; � rv�m �� � � � . � �� � �������
x
�
� �� � � � �� � � �`;t� � �,��
. � � ,�� �,�� � �
� � ����� ���� � ��.� � "� � � °4w � ��;�;
�� � ��� � � ��, ��r�� � �� '_'��� ����' � , ,��
� � �° ��, � ���w � �_�_ �, � "� ""�" �."`� �, ����>�
� . � �� '� ���u� ' � � �
�
_„�° ' �w���. ��. �' �. "w� �.� i �� 4 a��
�,:�"e +� ��� �'' .� �'�,�.. `� �. �� �"�
��.,^� �'"" , ��$t� ���„�, '�`'�° � � �...^.�,,��� � � ,, „,�,�^ m. `�,... .. , � „
`"�` ,�F�`. `�'*��"a ��!E.� �`ror �,� � �� � ' ��. �:`'� ?� .. �" � � � � � � +�
� �
� ��'� `"^�..'i�;��'" a �"°�' ; .� •. ,. � r� � � .. w ��x
^�`'e i`"° ., � c v�Gk� '�+ 'T.� '`", �" �.� � �w„�� .., ��� . i�
� �
,»"� „#�. � '" '�y"w�"� � � �,�.,� < „ ��� ..� �.� .*� 4 . 4 �
� �„ 'y�� '�� � µ � , y,. h.� �. l ,„„� ,�0Y ,.R`,. x� ;
��� � � ��:�i k �R i P . �w^'"^� h � ��. .�
'k �i v` k: �: b � `� �� ?
�t� �� �ti �� � ��� � �� ��
� *�A � � �
� � � � � � ,
���`�'�* c� "�.,�, � � _, � �.�� � � ��� �"� '� . °�, ,.���
� �� �' � �. � � � � ��° ����„�'�� �w � x��� 40�61722� ,�ti '�-��� �;
� � � � .° �'� � ��'� � a � ���� '�; �� � �� � �"� =122 3$91,3��'
�'�- �, x . r ,.,��� ` ``\ ���'�, �'�"> � *��.,m .� � Y ���e,: i � �,.. ��e
� � �.���. ,,.��� � ,��„a""� ' "a 3 � ��,r .v� k � *�n����,'c� +� r� .�:� � ,�'��"� �3. r��' �`�`°�..
#' �ix' ^v ,� a ��' ;..� � ar �. �
r � �
3..
r � 't a�
�� �w �"`�`"�,� �,�, ;�"'��g�"�'� �� �h'�� �, � �..`� i '�.�e�.��^ �,�,"''�,�^ � � `� �.
�._,� `ao- `��.. ��..- *�aar�' � �"� �,t'�+ �``c t a��. u�'� �...,, `w �"�' `�?� ���� x ���
'� �.��� � ��� �+� � ���- � ��� � � ��.r, -� � ��� ,
.,. � � � �3 �� , �� '`� w � ,� c s ��' v \ �..�°'"""�,'
.,. �p. ... ...'S'�m' J` $ �" �� ^�` y� '� `�rt' �t� � `w.,.0 � �� `y ys�� +{�* `�`"�
� "'6.41 .� � K, 1'�., °w
"`�:'� k�il�, '�,�Y+,'� �'�m ��,4 � 'N+��,� ��„ �,.�.y =�.L'w,.*`�e ��k,v� �"a �'z''��"�� , �� d,�� �� '�'
�
�4'4 �� � '� ^.,7v �. � s �`�. �" � '"�.,. '.-,��.x�` 4��'k�, "r ��....�g ���^ m �
�'��'� � � , � ,� �, � � � `t� "�� �' "� �4 $ t � � �
i �°� ��. �� �. �r, , � �"""'„�,t,i �,�,�,�.��, "�y� � '� r��.,� '� �..g � �,�.
'�� ��'�� �"�`.� �; ?s L^l:�""" i �" ""w.� 4 `a"�a'",, �'* ��aa�".�;�;'t� �� � �^`� ��.�:�"���� � � .��r��.
�: '" � �v, �„' "���,,�,`�"'" bare.a.:
�� �`^a���� �,""°„��� 5 �� �'� � i`i �'� �,� �� � �s��..
�� � �,, �� �`.^ � � . � � ��� � .��� ' �.
,��,.�.°a �"a'y""'� `'`"""`'-.�.. a�i� ^�*�,tiw.� �„�� � � �il . a� �, � , � ,`,.�..� ��.,��"w' * �.
� ��4��a �"� � r � � ; `. ����"� � � � � `a,�, �j`,s^ �a�.� � ' '
{ � � �w�
�"-" „ �;��r�����,..�"� � a ,s, �'"`�.��`��a,�""��w �� s4 � "�..� �'�..��..�^� �n �� ; t y ` � ��" :��b°�
;?°� ✓� r�,� � �b `�v ���� , �`"��� �� „�`� � � �� "a,� `w� r'��yv,����� ;p ��
� """'"� t'5��� `,ah��'�ka �''t 't�, �4 w�° �`y�,4 ,.k'�..�' �.,,v� �4� ,�.� �� ,�� �$�..�*.��,..��t �t^�`
.. '� a � ��*- 4., �, � ., c y � 3 .
� «����t"� � �„ � , � �"�� `r � � a 3�s , ^.,' 4 „� r^ �«.;
*�` �+'rc3 � x,.: ",.;,, �iy. �Z �`.� v`"� '+.., *�.�# y i g�s. �" ,u� ,�.t*w,-„ p£ ��$ .
��:,�..�; '� � `.`.n � s'�`' ��" �� � .� ������ � �t�� ��,�' '� } '"�-�,�i � �` ��''"�„�..'���` ,��+',' ��� � �" t �' ,,.�4V
}�.�^ �� .�. , '�h��� „��w� � � .,..-,���,�'`r� ' z�.^�. ' � �^�� `'`���,� ����' `�`^i ,��..,,`��;�,
� �r�&� �s �o� r°� ti`�t�"�y� °�*. `�� "�`��,q ir� "'�" '��"��r�w �,„;�„�� � �� ,� "��� � a� 4:��,� �w
at�., ..'S'��.�=k Y.� A.m, "��i <°:„.�' "i .r'k " .w.�i � ���k „°i&' 4 � l��;
° imm�wwu�.u;u;�wvnew..�smus�u�a�swmvweumw..ur�.m
u e �asm.ssvoror�ti.aastsatt�.�a�s.xwasanevm� . ..
O te,� a, �,,,.: . e..,� .3:, v....:....
� Z.�Q� �
Feet
,n<= C?R � WY �ap Reference Poink ��„cn-zoo�r�er fatpGg�s�zeors.sx,���a
�a �� u� ; Study Area(8.66 acres)
fit
3 �:, �
` �
� '
4t� � GA
� P -.tl f IH�06839
�4 ��'� qry SI s' C y.0: ; f` -'b �02 0506
� S'�f�'y � � !"lL USGS S � D'7i',Redding 12.rew-,c1�SS or 202.�-O:i-OG
�5;�j S��� ���- ��.� I'+US-132N h03W 513.1 A.23.24
�'3s.�Cs,J ffl�' ,r� ,��� Clent/P�o.e..f
- Nofes City of Reddinc�
1_c' .1 aie Svsre,�n_ �tno is3a Sr.. P�ane ce�i;�mlo i
�=�Psoa� MagnumsArea Remote Sewer Project
_ er
2.Base map�,Esn USA Topo Maps
— 3.Pvblic Lnnd Survsy.i 32N,R O5W,Sec.13,14,23.24 FgureNo.
�
litie
G'sd Si..i . �„p k li�f. C.I �I I�. .I. ,.i_t F"..i�
r u . �se y ..:'�v�„�t a MpP,���, �,aa.�.m �F�o�:�r �i`�J�C'��.��CB'�fOil
sao
r�i3a.nas S}ani0c,?s o(fico5,employees,consvHants and agesifs,`rom qny and all
� cia�msa�i�ingiranywayfFomiTeconiantorprovisionoFYnedaYa.
U
MITIGATED NEGATIVE DECLARATION
MAGNUMS AREA REMOTE SEWER PROJECT
(STATE CLEARINGHOUSE NO. 2025-080307)
SUBJECT
Magnums Area Remote Sewer Project
PROJECT DESCRIPTION
The City of Redding(City)is proposing the Magnums Area Remote Sewer Project in the City of
Redding, Shasta County, California. The purpose of the project is to replace existing sewer lines to
address deterioration due to age, lines which require a high level of maintenance, and/or lines which are
undersized. The project would require trenching, sub-surface pipe bursting,vegetation removal,utility
relocation,paving, sign installation,and striping.
The project would span approximately 5,060-feet long across multiple locations, from Mishka Ct.,
Greenback Ln., Calexico Dr., Dickson Dr., E. Keswick Dam Rd., Lake Blvd., Shamrock St., sections
along the bacic sections of Magnums Way and Guinevere Ct. and along portions of the railroad. The
project would cross Boulder Creek in approximately 4 separate sections and will parallel the sxream
closely in a few others. The sub-surface pipe bursting method will be used to minimize stream impacts in
these locations. This method will require an excavated pit on each end of the sewer line. Each excavated
pit will be approximately 6-feet wide, 10-feet long, and have an excavation depth ranging from 6 to 12
feet. The new sewer pipe wi11 be placed in the pit and fed into the existing pipe replacing it in its original
alignment. The new pipes will be connected to manholes at each end, and the pits will be backfilled with
slurry and native materiaL The old siphon pipes,the removed manhole material, and the excavated
earthen material would be taken to a land�ll. Construction is expected to require one construction season
(July 1 through October 31)beginning in suinmer 2026.
ENVIRONMENTAL SETTING
The project area is centered on Boulder Creek, an intermittent stream,in a residential neighborhood.
Va11ey foothill riparian habitat occurs along Boulder Creelc through most of the study area. Work would
be primarily located within existing easement areas and City owned property zoned open space.
FINDINGS AND DETERMINATION
The City of Redding eonducted an Initial Study(attached)that determined that the proposed project could
have significant environmental effects on biological resourees. Implementation of specific mitigation
measures identified below will avoid or mitigate the potentially significant environmental effects
identified, and the preparation of an environmental impact report will not be required. If there are
substantial changes that alter the character or impaets of the proposed projeet, another environmental
impact determination will be necessary.
Prior to approval of the project, the lead agency may conclude, at a public hearing,that certain mitigation
measures identified in the Mitigated Negative Declaration are infeasible or undesirable. In accordance
Magnums Area Remote Sewer Project Pa�c 1
September 2025
City of Redding
Public Works Deparhnent,Engineering Division Mitigated Negative Declaration
with California Environmental Quality Act(CEQA) Section 15074.1,the lead agency may delete those
mitigation measures and substitute other measures that it determines are equivalent or more effective. The
lead agency would adopt written findings that the new measure(s)is(are) equivalent or more effective in
mitigating or avoiding potential significant effects and that it would not cause any potentially significant
effect on the environment.
1) Based on the whole record(including the Initial Study and any supporting documentation) and the
mitigation measures incorporated into the project,the City of Redding has determined that there is no
substantial evidence that the project will have a significant effect on the environment.
2) The Mitigated Negative Declaration,with its supporting documentation,reflects the independent
judgment and analysis of the lead agency,which is the City of Redding.
DOCUMENTATION
The attached Initial Study documents the reasons to support the above determination.
MITIGATION MEASURES
The following mitigation measures will be incorparated into the project to minimize potential effects on
biological resources:
• MM-1. Environmental awareness training for construction personnel will be conducted by a
qualified biologist prior to onset of work to brief them on how to recognize and avoid
impacts to a11 applicable species.
• MM-2.A qualified biologist will conduct at least one survey within suitable aquatic and
upland habitat for northwestern pond turtles and their nests within one week of construction
activities.
• MM-3.If northwestern pond turtles or their nests are encountered in the work area during
construction and could be harmed by construction activities,work will stop in the area.
Individual turtles will be allowed to inove away from the study area on their own accord.If a
northwestern pond turtle nest is found, a qualified biologist(in consultation with CDFW and
USFWS)will determine the extent of a construction-free buffer zone to be established around
the nest.
• MM-4. If western spadefoot toads are encountered anytime during construction,project
activities will cease in the immediate vicinity until the toads move to a new location(out of
hann's way)without human interference. Should relocation activity become necessary,
consultation will be re-initiated with USFWS.
• lVIM-5.Prior to moving equipment or materials each day, construction personnel shall inspect
underneath and around equipment,other project materials(e.g., stored pipes greater than 2
inches in diameter), and trenches located within 200 feet of aquatic habitat for western
spadefoot toads.
• IVIM-6.Far work conducted during the western spadefoot toad migration and breeding season
(November 1 to May 31), a qualified biologist will survey the active work areas(including
access roads)in mornings following measurable precipitation events. Construction may
Page 2 Magnums Area Remote Sewer Project
September 2025
Ciry of Redding
Mitigated Negative Declaration Public Warks Department,Engineering Division
commence once the biologist has confirmed that no spadefoot toads are in the work area.
• MM-7.To the extent practicable,removal of brush will occur outside of the maternai denning
period(i.e.,July 1 through Apri130)for ringtail cat. If vegetation removal is to occur during the
maternal denning period(May 1 through June 30), a qualified biologist will conduct a pre-
construction survey of the study area to locate maternity dens and identify measures to protect
those maternity dens from disturbance. The pre-construction survey will be performed no more
than seven days prior to the vegetation removal.
• MM-8.If construction or vegetation removal occurs d�uring the nesting season,February 1
through August 31 for birds and November 1 through July 15 for raptors,a qualified biologist
shall conduct a preconstruction survey to locate active nests. The pre-construction survey will
be performed no more than'7 days prior to the implementation of construction activities. If a
lapse in construction activities occurs for 7 days or longer, another pre-construction survey
will be performed. If an active nest is found, a qualified biologist(in consultation with the
CDFV�wi11 determine the extent of a buffer zone to be established around the nest.
PUBLIC REVIEW DISTRIBUTION
Draft copies or notice of this Mitigated Negative Declaration were distributed to:
■ State Clearinghouse
■ Shasta County Clerk
■ California Department of Fish and Wildlife District 1
■ Central Valley Regional Water Quality Control Board
■ California Native Plant Society
■ Native American Heritage Commission
■ State Office of Historic Preservation
■ All property owners within 300 feet of the property boundary
PUBLIC REVIEW
(X) Draft document referred for comments Au�ust l, 2025—September 1, 2025
Date
(X) No comments were received during the public review period.
O Coinments were received but did not address the draft Mitigated Negative Declaration fmdings or
the accuracy/completeness of the Initial Study. No response is necessary. The letters are attached.
O Coinments addressing the findings of the draft Mitigated Negative Declaration and/or accuracy or
coinpleteness of the Initial Study were received during the public review period. The letters and
responses follow(see Attachment D, Response to Comments).
Copies of the Mitigated Negative Declaration,the Initial Study,documentation materials, and the
Mitigation Monitoring Program may be obtained at the Public Works Department,Engineering
Division,City of Redding,777 Cypress Avenue,Redding, CA 96001. Contact: Tiffany Durette,
Associate Environmental Specialist,(530)225-4171 or tlightle@cityofredding.org.
Pagc 3
Magnums Area Remote Sewer Project
September 2025
City of Redding
Public Works Department,Engineering Division Mitigated Negative Declaration
<�
Date of ��/'�
_.#-- f �
Draft Repart: August l, 2t125 By: P y��
Name/Title: Tiffan urette
Associate Environmeiltal Specialist
Date of
Final Report: 4'--��, � �Rr �c:�"Z.:�
Attachments:
A. Project Lacation Map
B. Initial Study
C. Mitigation Monitol°ing and Enviranmental Ccammitment Pr€�gram
I3. Cc�mments and Response to Camrnents {if any)
Page 4 Ganter Court Sewer Project
August 2�24
ATTAC H M E N T A
Project Location Map
MITIGATION MONITORING AND
ENVIRONMENTAL COMMITMENT PROGRAM
MAGNUMS AREA REMOTE SEWER PROJECT
(STATE CLEARINGHOUSE NO. 2025-080307)
MITIGATION MONITORING PROGRAM CONTENTS
This document is the Mitigation Monitoring and Environmental Commitment Program(MMP/ECP)for
the Magnums Area Sewer Project(project). The MMP/ECP includes a brief discussion of the legal basis
for, and the purpose of,the program, discussion, and direction regarding complaints about
noncompliance; a key to understanding the monitoring matrix; and the monitoring maxrix.
LEGAL BASIS OF AND PURPOSE FOR THE MITIGATION MONITORING PROGRAM
California Public Resources Code Section 21081.6 requires public agencies to adopt mitigation
monitoring or reporting programs whenever certifying an environmental impact report(EIR)or a
mitigated negative declaration(MND).This requirement facilitates implementation of all mitigation
measures adopted through the California Environmental Quality Act(CEQA)process.
The MMP contained herein is intended to satisfy the requirements of CEQA as they relate to the Initial
Study/Mitigated Negative Declaration prepared for the project. It is intended to be used by City of
Redding(City) staff,participating agencies,project contractors, and mitigation monitoring personnel
during implementation of the project.
Miti�;ation is de�ned by CEQA Guidelines Section 15370 as a measure that does any of the following:
■ Avoids im�pacts altogether by not taking a certain action or parts of an action.
■ Minimizes impacts by limiting the degree or ma�nitude of the action and its implementation.
■ Rectifies impacts by repairing,rehabilitating, or restoring the impacted environment.
■ Reduces or elim.inates impacts over time by preservation and maintenance operations during the life
of the proj ect.
■ Coinpensates for impacts by replacing or providing substitute resources or environments.
The intent of the MMP is to ensure the effective implementation and enforcement of adopted mitigation
measures and permit conditions. The MMP will provide for monitoring of construction activities as
necessary, onsite identification and resolution of environmental problems, and proper reporting to City
staf'f.
In addition to meeting the CEQA MMP requirements,this document incorporates environmental
colnmitments, standard practices, conservation measures, and best management practices (B1VIPs). The
environmental commitments may be part of the project design, standard contract specifications, City
requirements, or conservation measures. These commitments are part of tbe project,but they do not
constitute mitigation under CEQA as they have not been incorporated to reduce a potentially sigt�ificant
im�pact.
Magnums Area Remote Sewcr Projcct Pa�c 1
Scptcmbcr 2025
City of Redding
Public Works Deparhnent,Engineering Division Mitigatio�l Monitoring Program
MITIGATION MONITORING/ENVIRONMENTAL COMMITMENT PROGRAM TABLE
The MMP/ECP Table identifies the�nitigation measures and commitments proposed for the project.
The tables have the following columns:
■ Mitigation Measure: Lists the mitigation measures identified within the Initial Study for a specific
potentially significant impact, along with the nuinber for each measure as enumerated in the Initial
Study.
■ Environmental Commitment: Lists the commitments identified within the project that are not
related to a potentially significant CEQA impact,but further ensure environmental resource
protection.
■ Timing: Identifies at what point in tune,review process, or phase the mitigation measure will be
completed.
■ Agency/Department Consultation: References the City department or any other public agency with
which coordination is required to satisfy the identified mitigation measure.
■ Verification: Spaces to be initialed and dated by the individual designated to verify adherence to a
specific mitigation measure.
NONCOMPLIANCE COMPLAINTS
Any person or agency may file a complaint asserting noncompliance with the mitigation measures and
commitments associated with the project. The complaint shall be directed to the City in written form,
providing specific information on the asserted violation. The City sha11 investigate and determine the
validity of the complaint. If noncompliance with a mitigation measure has occurred,the City shall take
appropriate action to remedy any violation. The compliant shall receive written confirmation indicating
the results of the investigation or the�nal action corresponding to the particular noncompliance issue.
Page 2 Magnums Area Remote Sewcr Projcct
Scptcmber 2025
City of Redding
Public Works Deparhnent,Engineering Division Mitigarion Monitoring Progam
MITIGATION MONITORING AND ENVIRONMENTAL COMMITMENT PROGRAM TABLE
MAGNUMS AREA REMOTE SEWER PROJECT
MITIGATION MONITORING PROGRAM
(STATE CLEARINGHOUSE NO. 2025-080307)
ENVIRONMENTAL COMMITMENTS
The following environmental commitments will be incorporated into the project to further protect environmental and biological resources:
' Timingl Enforcem�nt/ Verification'
Best Managernent 1'ractices ' Implementation ' Monitoring (Date and Initials�
Bialogical i2esoarces(BIO)
BIO-1.A Stormwater Pollution Prevention Plan(SWPPP),as required by the City of Redding Preconstruc�ion/ City/
Stormwater Quality Management and Discl�arge Control Ordinance,will be prepared to address Construcrion Construction
BMPs that wili be used to prevent erosion and sediment loss within the project site.BMPs such Management
as silt fence,mulching and seeding,and straw wattles will be placed where needed to prevent
sediment from leaving the site during and after construction.
BIO-2.Appropriate sediment control measures(e.g.,silt fences,straw wattles)will be in place Preconstruction/ City/
prior to the onset of construction ac�ivities near waters of the United States and in project areas Construction Construction
where there is a potential for surface runoff to drain into jurisdictional waters. Sediment control Management
measures will be monitored and maintained until construction activities have ceased.
BIO-3.High visibility fencing,flagging,or markers will be installed along the edges of the work Preconstruction/ City/
zone near avoided waters and riparian areas.In addition,equipment entry and exit points;and Construction Construction
staging, storage,and stockpile areas must be ciearly marked prior to the enhy of inechanized Management
equipment or vehicles into the construction area.
Cultural Resources(CR)
CR-1.If previously unidenrified cultural materiais are unearthed during construction,it is the Construction City/
City's policy that work be haited in that area until a gualified archaeologist can assess the Construction
significance of the find.Additional archaeological surveys will be needed if the proposed project Management
undertaking limits are extended beyond the present survey area of potential effect limits.
Magnums Area Remote Sewer Projcct Page 3
Scptembcr 2025
City of Redding
Public Works Deparhnent,Engineering Division Mitigarion Monitoring Progam
Tirning/ Enfarcement! Verification
Best Mana�ement Practices Implementation ' Monitoring (Date and initials)'
CR-2.If human reinains are discovered during project activi�ies,all activities near the find wili Construcrion City/NAHC/
be stopped,and the Shasta County Sheriff-Coroner's Office will be notified.If the coroner Counry Coroner
determines that the remains may be those of a Native American,the coroner will contact the
Native American Heritage Commission(NAHC).Treatment of the remains will be conducted in
accordance with further direction of the County Coroner or NAHC,as appropriate.
Hazards and I-Iazardous Materials(HAZ)
HAZ-1.Hazardous materials,including fuels,oils,cement,and solvents wiil be stored and Construction City/
contained in an area protected from direct runoff and away from areas where they could enter Construction
waters of the United States. Management
HAZ-2.Construction equipment will be inspected daily for leaks. Leaking fluids will be Construction City/
contained upon detection,and equipment repairs will be made as soon as practicable,or the Construction
leaking equipment will be moved offsite. Management
HAZ-3. Secondary containment such as drip pans or absorbent materials will be used to catch Construction City/
spills or leaks when removing or changing fluids. Secondary containment will be used for Construction
sYorage of ail hazardous materials. Management
HAZ-4. Spili containment and clean-up materials will be kept onsite at ail times for use in the Construcrion City/
event of an accidental spi11. Construction
Management
HAZ-5.Absorbent materials will be used on smali spills rather than hosing down or burying the Construcrion City/
spi1L The absorbent material wi11 be promptly removed and disposed of properly. Construction
Management
HAZ-6.With the exception of vegetation clearing equipment,no vehicles or construction Construction City/
equipment may be operated in areas of tall,dry vegetation. Construction
Management
HAZ'7.A Fire Prevention and Suppression Plan would be developed for any maintenance and Preconstruction City/
repair activities that require welding or otherwise carry a higher risk of starting a wildfire. Construction
Management
HydroIogy and Water Quality tWQ)
WQ-1.All construction work and stockpiling of materials will be confined to the project Construction City/
disturbance area. Construction
Management
Magnums Area Remote Sewer Projcct Page 4
Scptembcr 2025
City of Redding
Public Works Deparhnent,Engineering Division Mitigarion Monitoring Progam
Tirning/ Enfarcement! Verification
Best Mana�ement Practices Implementation ' Monitoring (Date and initials)'
WQ-2.Temporary stockpiling of excavated or imported materiai will be placed in upiand areas. Construcrion City/
Construction
Management
WQ-3.Excess soil wili be used onsite or disposed of at a regional landfill or other appropriate Construction City/
fa�cility. Construction
Management
Magnums Area Remote Sewer Projcct Page 5
Scptembcr 2025
City of Redding
Public Works Deparhnent,Engineering Division Mitigarion Monitoring Progam
CALIFORNIA ENVIRONMENTAL QUALITY ACT MITIGATION MEASURES
Resource-specific mitigation measures that will be used during project implementation include the following:
Tirning! Enforcement! "Veri�catian
Mitigatian Measure(M1V1} ' Implementation Monitoring (Date and Initials)'
Biological Resources(BIO)
MM-l.Environmentai awareness training for construction personnel will be conducted by a Preconstruction City/
qualified biologist prior to onset of work to brief them on how to recognize and avoid impacts Construction
to all applicable species ManagemenY
MM-2.A qualified biologist will conduct at least one survey within suitable aquaric and upland Preconstruction City/
habitat for narthwestern pond turtles and their nests within one week of construction activities. Construction
Management
MM-3.If northwestern pond turtles or their nests are encountered in the work area during Construction City/
construction and could be harmed by construction activities,wark will stop in the area. Construction
Individual turtles will be allowed to move away from the study area on their own accord.If a Management
northwestern pond turtle nest is found,a qualified biologist(in consultation with CDFW and
USFWS)will determine the extent of a construction-free buffer zone to be established around
the nest.
MM-4.If western spadefoot toads are encountered anytime during construction,project Construction City/
acriviries wi11 cease in the immediatE vicinity until the toads move to a new locarion(out of Construction
harm's way)without human interference. Should relocation activity bEcomE necessary, Management
consultation will be re-initiated with USFWS.
MM-5.Prior to moving equipment or materials each day,construction personnel shall inspect Preconstruction City/
underneath and around equipment,other project materials(e.g.,stored pipEs greater than 2 Construction
inches in diameter),and trenches located within 200 feet of aquatic habitat for western Management
spadefoottoads.
MM-6.For work conducted during the western spadefoot toad migration and breeding season Construction City/
(November 1 to May 31),a qualified biologist will survey the active wark areas(including Construction
access roads)in mornings following measurable precipitation events. Construction may Management
commence once the biologist has confirmed that no spadefoot toads are in the work area.
Magnums Area Remote Sewer Projcct Page 6
Scptembcr 2025
City of Redding
Public Works Deparhnent,Engineering Division Mitigarion Monitoring Progam
Tirningl Enforcement! ' "�erification'
Mitiga�ian Measure(MM) Itnplement�tion Mnnit�rring (Date and Initials)''
MM-7.To the extent practicable,removal of brush wiil occur outside of the inaternal denning Construction City/
period(i.e.,July 1 through April 30)for ringtail cat.If vegetation removal is Yo occur during the Construction
maternal denning period(May 1 through June 30),a qualified biologist will conduct a pre- Management
construction survey of the study area to locate maternity dens and identify measures to protect
those maternity dens from disturbance. The pre-construction survey will be performed no more
than seven days prior to the vegetation removal.
MM-8.If construction or vegetation removal occurs during the nesting season,February 1 Construction City/
through August 3 l for birds and November 1 through July 15 for raptors,a qualified biologist Construction
shall conduct a preconstruction survey to locate active nests. The pre-construction survey will Management
be performed no more than 7 days prior to the impiementarion of construcrion acrivities.If a
lapse in construcrion activiYies occurs for 7 days or longer,another pre-construction survey will
be performed. If an acrive nest is found,a qualified biologist(in consultarion with the CDFW)
will determine the extent of a buffer zone to be established around the nest.
Magnums Area Remote Sewer Projcct Page 7
Scptembcr 2025