HomeMy WebLinkAbout _ 4.11(c)--Airport Road Improvement Project Phase 2 Project � � �' � � �
� � � ' � �' � � ' � ` CITY OF REDDING
REPORT TO THE CITY COUNCIL
MEETING DATE: December 17, 2024 FROM: Michael Webb, Public Works
ITEIVI NO. 4.11(c) Director
***APPROVED BY***
�
�c a� � �bEi� 'c�r�Csl7�reetcsr 1�f1?t2t}`?� r5�' �p�i��,C�i �r� �, 1?�'1(l�'2{�?
mwebb@cityofredding.org btippin@cityofredding.org
SUBJECT: 4.11(c)--Airport Road Improvement Project Phase 2 Project
Recommendation
Approve and authorize the following actions relative to the Airport Raad Improvement Project
Phase 2:
(1) Adopt the Mitigated Negative Declaration, and the Mitigation Monitoring and
Environmental Commitment Program; and
(2) Approve the Airport Road Improvement Projec� Phase 2 as described, thereby satisfying
the requirements of the California Environmental Quality Aet Guidelines §15074.
Fiscal Impact
Approval of the Airport Road Improvement Project Phase 2 (Project) along with adoption of the
Mitigated Negative Declaration (MND) and the Mitigation Monitoring Program (MMP) allows
the project to move toward the final design and construction phases. There is no fiscal impact as
a direct result of adopting the MND, MMP, and approving the project.
The project construction costs are estimated to be approximately $1.5 million and has been
budgeted through the Public Works' Streets Division.
Alternative Action
The City Council (Council) may chaase not to adopt the MND and the MMP, and not approve
the project as described. Without approval, the project would not be able to proceed as a City of
Redding (City) project, as it would not comply with the California Environmental Quality Act
(CEQA).
Report to Redding City Council December 12,2024
Re: 4.12(c)--Airport Road Improvement Project Phase 2 Project Page 2
BackgroundlAnalysis
The project will improve safety along the Airport Road corridor by providing paved shoulders
for cyclists and pedestrians and turn lanes for motorists. The project would span approximately
0.75 mile along Airport Road, from 190 feet south of Bi11y J�ean Gane to Hartnell Avenue. Phase
I (successfully completed in 2019) made similar improvements along Airport Road from Electro
Way to Bi11y Jean Lane.
This project will provide two 12-foot-wide travel lanes; 8-foot-wide paved shoulders with 3 feet
of shoulder backing. A northbound left-turn pocket will be added at the intersection with Billy
Jean Lane and the existing southbound right-turn pockets at Preserve Boulevard and Argyle
Road will be lengthened. Road widening will be intermittent (based on current widths) and vary
from zero to 15-feet. Widening will alternate between the east and west sides of the road and, in
some locations, the road wi11 be widened along both sides. Utility relocation may include fire
hydrants and utility poles with their associated electrical, cable, and telephone lines. The
anticipated utility relocation work will require soil disturbances ranging from 2-8 feet in depth.
Trenching for underground lines would require a depth of 2-feet, fire hydrant relocation would
require a depth of three to four-feet, and utility pole relocation would require a depth of six to 8-
feet.
Drainage in the area consists primarily of roadside ditches, with only a few culverts. Relocation
of the ditches would require a maximuin vertical depth of two-feet. Approximately 125-feet
north of Billy Jean Lane, an existing 30-inch diameter and 77-foot long reinforced concrete
culvert will be extended eight feet to the west and six-foot concrete flared end sections will be
added to the inlet and the outlet.
An Tnitial Study(IS) was prepared to satisfy the requirements of the CEQA. It describes why the
project is being proposed and the potential impacts to the existing environment. The IS shows
that the proposed project could have a signifieant effect on biological resources, but with
implementation of mitigation measures, those impacts will be reduced to a level considered less
than significant. The mitigation and conservation measures to be implemented are common
practices and include, but are not limited to, biological pre-construction surveys, impact
minimization, compensatory mitigation, and erosion control.
Based on the conclusions made in the IS, an MND was prepared. The MND describes the
project, including mitigation measures, and makes the determination that there will be no
significant effect on the environment provided that the defined mitigation measures are
implemented as part of the project. In addition, an MMP has been written and incorporated into
the MND (CEQA Section 21081.6). The MMP will be used by City staff, contractors, agencies,
and monitoring personnel during and after the project to ensure effective implementation of the
adopted mitigation measures outlined in the MND.
The IS/MND/MMP documents were sent to the State Clearinghouse for a 30-day public review
period and distribution to pertinent state agencies. They were sent to local resource agencies, the
Shasta County Clerk, and posted on the Public Works Department website. A public notice was
also sent to landowners in the vicinity of the projeet and posted in the local newspaper. Two
comment letters were received during the public review period.
Report to Redding City Council December 12,2024
Re: 4.12(c)--Airport Road Improvement Project Phase 2 Project Page 3
Environmentccl Review
The City is the lead agency for the project pursuant to CEQA. As the lead CEQA agency, the
Council is authorized to adopt the MND per Redding Municipal Code Section §18.24.070.E and
state 1aw. Upon adoption of the MND and approval of the project by the Council, a Notice of
Determination wi11 be filed with the Shasta County C1erk's Office and the State Clearinghouse,
completing the environmental review process. The TS/MND is available in the Public Works
Department and is currently available online at
�t� s;%/�vv�v��.c°i� c�t��cldi�«. �c�v/c�csver��rm����1d� a��1z��t��s/ ublic ��arks/�noji�°��a�1����ta1 ��Z�a���<$�n7.
��atli�ac�c;�.�a� •
Council PrioNity/City NfanageN Goal
This agenda item is a routine operational item.
Attachments
^Mitigated Negative Declaration
^Mitigation Monitoring and Environmental Commitment Program
^Location Map
^Comments Airport Road Improvements Project Phase 2
MITIGATED NEGATIVE DECLARATION
AIRPORT ROAD IMPROVEMENTS PROJECT PHASE 2
(STATE CLEARINGHOUSE NO. 2024-1011 04)
SUBJECT
Airport Road Improvements Project
PROJECT DESCRIPTION
The City of Redding(City)is proposing the Airport Road Improvements Project in the City of Redding,
Shasta County, California. The purpose of the project is to unprove travel safety along the Airport Road
corridor by providing paved shoulders for cyclists and pedestrians and turn lanes for motorists. The
project would require road widening, earthwork, culvert extension, drainage modifcation,vegetation
removal,utility relocation,paving, guardrail replacement, sign installation, and striping.
The project would provide two 12-foot wide travellanes with 8-foot paved shoulders including
3-feet of shoulder backing. A north bound left turn pocket would be constructed at Bi11y Jean
Lane and the southbound right turn pockets at Preserve Boulevard and Argyle Road would be
lengthened. The road widening would be intermittent (based on current widths) and vary from 0—
15 feet. Widening would alternate between the east and west sides of the road, and in some
locations the road would be widened along both sides. Drainage in the area consists primarily of
roadside ditches, with only a few culverts. Relocation of existing ditches would be included with
the project. Approximately 125 feet north of Billy Jean Lane an existing One 30-inch diameter
and 7'7-foot long reinforced concrete culvert will be extended 8-feet to the west, and 6-foot
concrete flared end sections will be added to the inlet and the outlet. Utility relocation may
include fire hydrants and utility poles with their associated electrical, cable, and telephone lines.
This work would require a vertical disturbance ranging from 2-8 feet. The majority of work
would occur within City and County right-of-ways; however, temporary use permits to enter and
construct on adjacent private lands may be needed to conform driveways, relocate utilities, or
modify drainage. Permanent right-of-way acquisition would not be required.
ENVIRONMENTAL SETTING
Airport Road in the project area is bordered by a mix of commercial,industrial,residential,retail, and
undeveloped properties. Airport Road in the project area is bordered by a mix of commercial,industrial,
residential,retail, and undeveloped properties.
FINDINGS AND DETERMINATION
The City of Redding conducted an Initial Study(attached)that determined that the proposed project could
have significant environmental effects on biologica] resources. Implementation of specific mitigation
measures identified below will avoid or mitigate the potentially significant environmental effects
identified, and the preparation of an environmental impact report wi11 not be required. If there are
Airport Road Improvement Project Phase 2 Pa�e 1
October 2024
City of Reddin�
Public Works Department,Engineering Division Miti�ated Negative Declaration
substantial changes that alter the character or impacts of the proposed project, another environmental
impact determination will be necessary.
Prior to approval of the project, the lead agency may conclude,at a pub]ic hearing,that certain mitigation
measures identified in the Mitigatecl Negative Declaration are infeasible or undesirable. In accordance
with California Environmental Quality Act(CEQA) Section 15074.1,the lead agency may delete those
mitigation measures and substitute other measures that it determines are equivalent or more effective. Tl�e
lead agency would adopt written findings that the new measure(s)is(are) equivalent or more effective in
mitigating or avoiding potential significant effects and that it would not cause any potentially significant
effect on the environment.
1) Based on the whole record(including the Tnitial Study and any supporting documentation) and the
mitigation measures incorporated into the project,the City of Redding has determined that there is no
substantial evidence that the project will have a significant effect on the environment.
2) The Mitigated Negative Declaration,with its supporting documentation,reflects the independent
judgment and analysis of the lead agency,which is the City of Redding.
DOCUMENTATION
The attached Initial Study documents the reasons to support the above determination.
MITIGATION MEASURES
The following mitigation measures will be incorporated into the project to minimize potential effects on
biological resources:
• MM-l.All on-site construction personnel shall receive instruction regarding the presence of
listed species and the importance of avoiding impacts to these species and their habitat.
• MM-2.To compensate for direct impacts on potential habitat for vernal pool tadpole shrimp
and vernal pool fairy shrimp,the City wi11 purchase the appropriate mitigation credits from a
U.S.Fish and Wildlife(USFWS)-approved mitigation bank or another site to be approved by
the U�SFWS.Permanent impacts will be mitigated at a minimum ratio of 3:1 (three acres
preserved for each acre of potential habitat removed). Temporary impacts will be mitigated
on-site at a 1:1 ratio.
• MM-3.If vegetation removal or construction activities will occur during the nesting season
for birds(February 1 through August 31),a qualified biologist shall conduct a preconstruction
survey"7 days before construction activities begin. If nesting birds are found, California
Department of Fish and Wildlife(CDFW)will be notified and consulted.An appropriate
buffer, as determined by CDFW and the qualified biologist, shall be placed around the nest
until the young have fledged. If construction activities cease for a period greater than 7 days,
additional preconstruction surveys shail be required.
PUBLIC REVIEW DISTRIBUTION
Draft copies or notice of this Mitigated Negative Declaration were distributed to:
Pa�e 2 Airport Road Improveinent Project Phase 2
October 2024
City of Reddin�
Mitigated Ncgative Declaration Public Works Department,En�ineerin�Division
■ State Clearinghouse
■ Shasta County Cierk
■ California Department of Fish and Wildlife District 1
■ Central Valley Regional Water Quality Control Board
■ California Native Plant Society
■ Native American Heritage Commission
■ State Office of Historic Preservation
■ All property owners within 300 feet of the property boundary
PUBLIC REVIEW
(X) Draft doeument referred for comments October 25 2024—N�ovember 25 2024
Date
O No comments were reeeived during the public review period.
(X ) Comments were received but did not address the draft Mitigated Negative Declaration findings or
the accuraey/completeness of the Initial Study. N�o response is necessary. The letters are attached.
O Comments addressing the findings of the draft Mitigated Negative Declaration and/or accuracy or
eompleteness of the Initial Study were received during the public review period. The letters and
responses follow(see Attachment D,Response to Comments).
Copies of the Mitigated Negative Declaration,the Initial Study, documentation materials, and the
Mitigation Monitoring Program may be obtained at the Public Works Department,Engineering
Division,City of Redding,777 Cypress Avenue,Redding,CA 96001. Contact: Tiffany Lightle,
Associate Environmental Specialist, (530)225-4171 or tlightle@cityofredding.org.
Date of �
Draft Report: October 24,2024 By: �
Name/Title: Tif any Li tle
Associate Environmental Specialist
Date of
Final Report: December 18, 2024
Attachments:
A. Project Location Map
B. Initial Study
C. Mitigation Monitoring and Environmental Commitment Program
D. Comments and Response to Comments (if any)
Airport Road Improvement Project Phase 2 Pa�e 3
October 2024
ATTACHMENT A
Project �ocation Map
`
,.,
, ,
` . , � __
, y
,�
��� , �..� `
,,
, � -� � o� ` �� J�
� .-� � �`�- / v
� .. . � �
�
�.
�
\ {,f
�
\'\ \
� r i \�£
Er ' _
,• , !� l � — _ �
..� �G� v� � i ���� �_ _ - �- ,
_
f �
� �-� 1��p�. ,�... ..� � � f / 1- _ _ _ , ✓
�
f,� ' l�� L� f - �, � \.
t ., � I�/
�. _ , 1
�� �,PJe _.
e.. N�. _ 1� `
,
, -
r
- r� .
�e �N� r. �.�r ����
I
r � r
�� N � -
� ry
�t �, �� .� �..��-��� ��, o�a
, r�,.l ,r. .
1 � , ..
� , .
. . ..
�, - - ,..
.
, _
, ,. ,.
__�.�.��_ =� ; , r, r�9,�
� �t , ��� ; ,, o� ��
, _ ..__..�
, �,. , �
�
_ i a._ �.� ----� , Tr
_ _�...
1 � i � '�t
��
� -_� � �
�� �._�-. , � �s
� 't
� ��__— ''� ��,� ��\ ` � � ��t�
�.. 1 \
,` �
4 �" �
__,. < �
r —�— �
[ ��� �� ���___ ��_
,
-----_. � —
_
�� ��--� � � i __�� �'�, � -- _.
_Federer��Pkwy � ; i
_� � -- d
o;-- � � , oo�a9°- t
�-� ( � i ! � � ��' g�v
_ �. _....��_ �_.. �
� i
4 �
' � i�. �, � � ',
s
m�� " j �` �fi�"—� � 1
---� _' � � `� � �,
_ _��--�--- .� � t
� � � �. ,
z�__ �� ; � � �� �, ��� �, ,
��_ �.�.. �
t � '�
� __ _� �
�. ,
' T � ' � l , i
-
� ..
_ , ;
t _.__ -- . ';
�
;
i t ,„ � �
- ` Carlsbad Ln -'c �
�, , - , - � J _�
Z7 I _
� 1 �. ,
r •,„ t� , �
�------.. ......._� ---- L' i
� � � � i
, -
l�r ��-� ,
,-� �� � � f ._ - -_____ � ' I
� , �w
, �r- � ,N �
,•. t �
'
---
—
i� �, �4�,� --' .c� � �+, -�
;
f��% -�'...... `�,lr' �i)\ 1�� ' �, ---___.., —. Q
� ��- N�- �`__. Q � �
_ �. �
f f r � Q �
��` \% � �__. -}-� f�
r�
'" Y t ,'
� r
� ; � i r I�c j�1
_� _.-�-1 � , 1 ,
t
_.... �
.�...� �' � r i I , 1 j � � i
( ��....
_.�. r / ' j � ._�„ f
__ � t l�L+� ,. jt _ - _
i 7 ` � .
i i .'.".....J %
�;> �,� ��1. 1 , t �� �e�� - _ _ �
� � ,
� ,y , � ���.._, , , ,-
� �
�� ,�, , , 1 ��/ � 0�
�' '``��,��'� � �1 /� �� "L ���
,, � Ja ,,
�,�,,,;>'"' � ,.!� �� i ;
O�.F� � 1 ,�;� � �
,' /` \,„� i v ; � i
,� ` / ��'� ' i
/ ti 4 �5, ;
�� Q'� ` i
�,� /j
`�
> ������������:������� �� , ���������� �c��� ��J =������m�����������j���� � ��������=4 ����t����
; � t ;
, , ,- ��_ �_ � '1
' �. � � " G
' � Billy Jean--L-n
; � __ � ibson� Ct
� � r _ ._ �_ __ � _ ' i_ , , � � ,% '',,
�; � i � t
, ; �
--1 , -'� -__� �' �- -- r , �� _� �\
; ; _._,_ -__- _i__
-
, � �__._ � , A
; ; ; � ; � j �' �
�. ________ . „
_ ii i i ^� i i h,., -..y , 1 � � �.....,,�..._.
; � i .....�__„� i � � �,��- q ....,� < <
, .,...� ...��.
� � f � �, �m E ...... i r I f �—�
i I ' y_ .....{ E � i t 1 ��`�-�.
i � � i i i —� ---_..__; _._ '
,
� � _________
a , ; �.__________________ - � ( , � l _... --—,_,._- ---_._ .
- ' �,
-# --_.�-- �_m..�_ ! � ,
-----,�..�
� '
i �
� � ; i ._ � � _' . � ,/
...._. . . , v---�
N GIS DIVISION �OCATION MAP MTG.DATE:
INFORMATION TECHNOLOGY DEPARTMENT
W E DATE PRODUCED: ITEM:
SEPTEMBER18,2024
S o Zoo 400Feet AIRPORT ROAD IMPROVEMENT
� ATTACHMENT:
P:\Engineering\ProProjects\,4irportRdPhase LocationMap.aprx
MITIGATION MONITORING AND
ENVIRONMENTAL COMMITIVIENT PROGRAM
AIRPORT ROAD IMPROVEMENT PROJECT PHASE 2
(STATE CLEARINGHOUSE NO. 2024-101104)
1VIITIGATION MONITORING PROGRAM CONTENTS
This document is the Mitigation Monitoring and Environmental Commitment Program(MMP/ECP) for
the Airport Road I�nprovements Project Phase 2(project). The MMP/ECP includes a brief discussion of
the legal basis for, and the purpose of, the program, discussion, and direction regarding complaints about
noncompliance; a key to understanding the monitoring matrix; and the monitoring matrix.
LEGAL BASIS OF AND PURPOSE FOR THE M1TIGATION MONITORING PROGRAlYI
California Public Resources Code Section 210$1.6 requires public agencies to adopt mitigation
monitoring or reporting programs whenever certifying an environmental impact report(EIR) or a
mitigated negative declaration(MND). This requirement facilitates implementation of all mitigation
measures adopted through the California Environmental Quality Act(CEQA)process.
The MMP contained herein is intended to satisfy the requirements of CEQA as they relate to the Initial
Study/.Mitigated Negative Declaration prepared for the project. It is intended to be used by City of
Redding(City) staff,participating agencies,project contractars, and mitigation monitoring personnel
during implementation of the project.
Mitigation is defined by CEQA Guidelines Section 1.5370 as a ineasure that does any of the following:
■ Avoids impacts altogether by not taking a certain action or parts of an action.
■ Minimizes impacts by limiting the degree or magnitude of the action and its implementation.
■ Rectifies impacts by repairing,rehabilitating, ar restoring the impacted environment.
■ Reduces or eliminates impacts over tiine by preseroation and maintenance operations during the life
of the project.
■ Compensates for impacts by replacing or providing substitute resources or environments.
The intent of the MMP is to ensure the effective implementation and enforcement of adopted mitigation
zneasures and permit conditions. The 1VIMP will provide for monitoring of construction activities as
necessary, onsite identification and resolution of environmental problems, and proper reporting to City
staff.
In addition to meeting the CEQA MMP requirements,this document incorporates environmental
commit�nents, standard practices, conservation measures,and best management practices (BMPs). The
environmental commitments may be part of the project design, standard contract specifications, City
requirements, or conservation measures. These conunitments are part of the project,but they do not
constitute mitigation under CEQA as they have not been incorporated to reduce a potentially significant
im�pact.
Airport Road Improvements Project Phase 2 Pa�e 1
October 2024
City of Reddin�
Public Works Department,Engineering Division Miti�ation Monitorin�Program
MITIGATION MONITORING/ENVIRONMENTAL COMMITMENT PROGRAM TABLE
The MMP/ECP Table identifies the mitigation ineasures and commit�nents proposed for the project.
The tables have the following columns:
■ Mitigation Measure: Lists the mitigation measures identified within the Initial Study for a specific
potentially signi�cant impact, along with the number for each measure as enumerated in the Initial
Study.
■ Environmental Commitment: Lists the commitments identified within the project that are not
related to a potentially signi�cant CEQA impact,but further ensure environmental resource
protection.
■ Timing: Identi�es at what point in time,review process, or phase the mitigation measure wi11 be
completed.
■ Agency/Department Consuitation: References the City departme�nt or any othe�r public agency witl�.
which coordination is required to satisfy the identified mitigation measure.
■ Verification: Spaces to be initialed and dated by the individual designated to verify adherence to a
specific mitigation measure.
NONCOMPLIANCE COMPLAINTS
Any person or agency may file a complaint asserting noncoinpliance with the mitigation measures and
commitments associated with the project. The complaint sha11 be directed to the City in written form,
providing specific information on the asserted violation. The City shall investigate and determine the
validity of the complaint. If noncompliance with a mitigation measure has occurred,the City shall take
appropriate action to remedy any violation. The compliant shall receive written confirmation indicating
the results of the investigation or the final action corresponding to the particular noncompliance issue.
Pa�e 2 Airport Road I�nprovements Project Phase 2
October 2024
City of Reddin�
Public Works Department,Engineering Division Miti�ation Monitorin�Program
MITIGATION MONITORING AND ENVIRONMENTAL COlVIMITMENT PROGRAM TABLE
FOR T�IE AIRPORT ROAD IMPROVEMENTS PROJECT PHASE 2
MITIGATION MONITORING PROGRAM
(STATE CLEARINGHOUSE NO. 2024-101104)
ENVIRONMENTAL COMMITMENTS
The following environmental commitments will be incorporated into the project to further protect environmental and biological resources:
Tirningl Enforcementl Uerificatic�n
Best Manage�nent Practices ' Implernentatian ' Mt�nitoring {Date and Initials};
Air Quality(AQ};
AQ-1.Nontoxic soil stabilizers shall be applied according to manufacturer's specification to all Preconstruction/ City/
inactive construction areas. Construction Construction.
Management
AQ-2.All grading operations shall be suspended when winds(as instantaneous gusts)exceed preconstruction/ City/
20 miles per hour. Construction Construction
Management
AQ-3.All stockpiles,access roads,and disturbed or exposed areas shall be watered, Preconstruction/ City/
as necessary,to prevent airborne dust. Conshuction Construction
Management
AQ-4.Pursuant to the California Vehicle Code(Section 23114(e)(4))(California Legislative Preconstnzction/ City/
Information 2016),all trucks hauling soil and other loose material to and from the construetion Construction Construction
site shall be eovered or shall maintain at least 6 inches of freeboard(i.e.,minimum vertical Management
distance between top of load and the trailer).
AQ-5.All public roadways used by the project contractar shall be maintained free from dust, Preconstruction/ City/
dirt,and debris caused by construction activities. Streets shall be swept at the end of the day if Construction Construction
visible soil materials are carried onto adjacent public pavcd roads. Management
Airport Road Improvements Project Pha�e 2 Pa�;e 3
October 2024
City of Reddin�
Public Works Department,Engineering Division Miti�ation Monitorin�Program
Timing/ Enforcementl �erifzeatian
Best Management Practices Imp�ementation ; NLonitoring (I}at�and Initia�s),
Biological Resources(BIO}
BIO-1.A Stormwater Pollurion Prevention Plan(SWPPP),as required by the City of Redding Preeonstruction/ City/
Stonnwater Quality Management and Discharge Control Ordinance,wiil be prepared to address Construction Construction
BMPs that will be used to prevent erosion and sediment loss within the project site.BMPs such Management
as silt fence,mulching and seeding,and straw wattles will be placed where needed to prevent
sediment from leaving the site during and after construction.
BIO-2.Appropriate sediment con�rol measures(e.g.,silt fences,straw wattles)will be in place Preconstruction/ City1
prior to the onset of construction activities near waters of the United States and in project areas Construction Construction
where there is a potential for surface runoff to drain into jurisdictionai waters. Sediment control Management
measures will be monitored and maintained until construction activities have ceased.
BIO-3.High visibility fencing,flagging,or markers wi11 be installed along the edges of the work Preconstruction/ City/
zone near avoided waters and riparian areas.In addition,equipment entry and exit points;and Construction Construction
stagin�,stora�e,and stockpile areas must be elearly marked prior to the entry of inechanized Management
equipment or vehieles into the eonstruetion area.
Cultaral Resaurces(CR)�
CR-L If previously unidentified cultural materials are unearthed durin�eonstruction,it is the Construction City/
City's policy that work be halted in that area until a qualified archaeologist ean assess the Construction
significance of'the find.Additional archaeological surveys will be needed if the proposed project Management
undertaking liinits are extended beyond the present survey area of potential effect limits.
CR-2.If human remains are diseovered during project activities,all activities near the find will Construction City/NAHC/
be stopped,and the Shasta County Sheriff-Coroner's Office will be notified.If the eoroner County Coroner
determines that the remains may be those of a Na�ive American,the coroner will contact the
N�ative American Heritage Commission(NAHC).Treatment of the remains will be conducted in
accordance with further direction of the County Coroner or NAHC,as appropriate.
Hazards and Hazardaus Materials(HAZ}
HAZ-L Hazardous materials,including fuels,oils,cement,and solvents will be stored and Constnzction City/
contained in an area protected from direct runoff and away from areas where they couid enter Construction
waters of the United States. Management
HAZ-2.Construction equipment will be inspected daily for leaks.Leaking fluids will be Construction CityJ
contained upon deteetion,and equipment repairs will be made as soon as practicable,or the Construction
leaking equipment will be moved offsite. Management
Airport Road Improvements Project Phase 2 Pa�e 4
October 2024
City of Reddin�
Public Works Department,Engineering Division Miti�ation Monitorin�Program
Timing/ Enforcementl �erifzeatian
Best Management Practices Imp�ementation ; NLonitoring (I}at�and Initia�s),
HAZ-3.Secondary containment sueh as drip pans or absorbent materials will be used to catch Construction City/
spills ar leaks when removing or changing fluids. Secondary containment will be used for Construction
storage of all hazardous materials. Management
HAZ-4.Spill contaimnent and clean-up materials will be kept onsite at all times for use in the Construction City/
event of an accidental spill, Construction
Management
HAZ-5.Absorbent materials will be used on small spills ra�her than hosing down ar burying the Construction City/
spill.The absorbent material will be promptly removed and disposed of properly. Construction
Management
Hydralogy and Water QualitY(V�'Q)
WQ-1.Ail construction work and stockpiling of materials will be confined to the project Construction City/
disturbance area. Construction
Management
WQ-2.Temporary stockpiling of excavated or imported material will be placed in upland areas. Construction City/
Construction.
Management
WQ-3.Excess soil will be used onsite or disposed of at a regional landfill ar other appropriate Construction City/
facility. Construction
Management
CALIFORNIA ENVIRONMENTAL QUALITY ACT MITIGATION MEASURES
Resource-specific mitigation measures that will be used during project implementation include the following:
������ Timing/ Enfor�cement/ � Yeri�ication����
Mitigation NLeasure(MM) ', Implernentation ' M�nitoring (Date and Initials);
Bialagical Resaurces{BIO)
MM-1.All on-site construction personnel shall receive instrucrion regarding the presence of Preconstruction/ City1
listed speeies and the importance of avoiding impaets to these species and their habitat. Construction Construcrion
Management
Airport Road Improvements Project Phase 2 Pa�e 5
October 2024
City of Reddin�
Public Works Department,Engineering Division Miti�ation Monitorin�Program
���� TimingJ Enf�o-rcement! ` "t�erifaeati�c�n�����
Mitigation Measure(MM} , Implernentation ' l�onitoring (I)ate and Initials);
MM-2.To compensate for direct impaets on potential habitat for vernal pool tadpole shrimp Construetion City/
and vernal pool fairy shrimp,the Ciry will purchase the appropriate mitigation credits from a Construcrion
U�,S.Fish and Wildlife(U�SFWS)-approved mitigaYion bank or another siYe to be approved by Management
the USFW S.Permanent impacts will be mitigated at a ininimum ratio of 3:1 (three acres
preserved for each acre of potential habitat removed). Temporary impacts will be mitigated
onsite at a 1:1 ra�io.
MM-3.If vegetation removal or construction activities will occur during the nesting season for Construction City/
birds(February 1 through August 31),a qualified biologist shall conduct a preconstruction Construction
survey 7 days before construction activities begin.If nesting birds are found,California Management
Department of Fish and Wildlife(CDFW)shall be notified and consulted.An appropriate
buffer,as determined by CDFW and the qualified biolo�ist,sha11 be plaeed around the nest until.
the young have fledged.If construction activities cease for a period�reater than 7 days,
additional preeonstruction surveys shall be required.
Airport Road Improvements Project Phase 2 Pa�e 6
October 2024
`
,.,
, ,
` . , � __
, y
,�
��� , �..� `
,,
, � -� � o� ` �� J�
� .-� � �`�- / v
� .. . � �
�
�.
�
\ {,f
�
\'\ \
� r i \�£
Er ' _
,• , !� l � — _ �
..� �G� v� � i ���� �_ _ - �- ,
_
f �
� �-� 1��p�. ,�... ..� � � f / 1- _ _ _ , ✓
�
f,� ' l�� L� f - �, � \.
t ., � I�/
�. _ , 1
�� �,PJe _.
e.. N�. _ 1� `
,
, -
r
- r� .
�e �N� r. �.�r ����
I
r � r
�� N � -
� ry
�t �, �� .� �..��-��� ��, o�a
, r�,.l ,r. .
1 � , ..
� , .
. . ..
�, - - ,..
.
, _
, ,. ,.
__�.�.��_ =� ; , r, r�9,�
� �t , ��� ; ,, o� ��
, _ ..__..�
, �,. , �
�
_ i a._ �.� ----� , Tr
_ _�...
1 � i � '�t
��
� -_� � �
�� �._�-. , � �s
� 't
� ��__— ''� ��,� ��\ ` � � ��t�
�.. 1 \
,` �
4 �" �
__,. < �
r —�— �
[ ��� �� ���___ ��_
,
-----_. � —
_
�� ��--� � � i __�� �'�, � -- _.
_Federer��Pkwy � ; i
_� � -- d
o;-- � � , oo�a9°- t
�-� ( � i ! � � ��' g�v
_ �. _....��_ �_.. �
� i
4 �
' � i�. �, � � ',
s
m�� " j �` �fi�"—� � 1
---� _' � � `� � �,
_ _��--�--- .� � t
� � � �. ,
z�__ �� ; � � �� �, ��� �, ,
��_ �.�.. �
t � '�
� __ _� �
�. ,
' T � ' � l , i
-
� ..
_ , ;
t _.__ -- . ';
�
;
i t ,„ � �
- ` Carlsbad Ln -'c �
�, , - , - � J _�
Z7 I _
� 1 �. ,
r •,„ t� , �
�------.. ......._� ---- L' i
� � � � i
, -
l�r ��-� ,
,-� �� � � f ._ - -_____ � ' I
� , �w
, �r- � ,N �
,•. t �
'
---
—
i� �, �4�,� --' .c� � �+, -�
;
f��% -�'...... `�,lr' �i)\ 1�� ' �, ---___.., —. Q
� ��- N�- �`__. Q � �
_ �. �
f f r � Q �
��` \% � �__. -}-� f�
r�
'" Y t ,'
� r
� ; � i r I�c j�1
_� _.-�-1 � , 1 ,
t
_.... �
.�...� �' � r i I , 1 j � � i
( ��....
_.�. r / ' j � ._�„ f
__ � t l�L+� ,. jt _ - _
i 7 ` � .
i i .'.".....J %
�;> �,� ��1. 1 , t �� �e�� - _ _ �
� � ,
� ,y , � ���.._, , , ,-
� �
�� ,�, , , 1 ��/ � 0�
�' '``��,��'� � �1 /� �� "L ���
,, � Ja ,,
�,�,,,;>'"' � ,.!� �� i ;
O�.F� � 1 ,�;� � �
,' /` \,„� i v ; � i
,� ` / ��'� ' i
/ ti 4 �5, ;
�� Q'� ` i
�,� /j
`�
> ������������:������� �� , ���������� �c��� ��J =������m�����������j���� � ��������=4 ����t����
; � t ;
, , ,- ��_ �_ � '1
' �. � � " G
' � Billy Jean--L-n
; � __ � ibson� Ct
� � r _ ._ �_ __ � _ ' i_ , , � � ,% '',,
�; � i � t
, ; �
--1 , -'� -__� �' �- -- r , �� _� �\
; ; _._,_ -__- _i__
-
, � �__._ � , A
; ; ; � ; � j �' �
�. ________ . „
_ ii i i ^� i i h,., -..y , 1 � � �.....,,�..._.
; � i .....�__„� i � � �,��- q ....,� < <
, .,...� ...��.
� � f � �, �m E ...... i r I f �—�
i I ' y_ .....{ E � i t 1 ��`�-�.
i � � i i i —� ---_..__; _._ '
,
� � _________
a , ; �.__________________ - � ( , � l _... --—,_,._- ---_._ .
- ' �,
-# --_.�-- �_m..�_ ! � ,
-----,�..�
� '
i �
� � ; i ._ � � _' . � ,/
...._. . . , v---�
N GIS DIVISION �OCATION MAP MTG.DATE:
INFORMATION TECHNOLOGY DEPARTMENT
W E DATE PRODUCED: ITEM:
SEPTEMBER18,2024
S o Zoo 400Feet AIRPORT ROAD IMPROVEMENT
� ATTACHMENT:
P:\Engineering\ProProjects\,4irportRdPhase LocationMap.aprx
Airport Road Improvements Project Phase 2
Response to Pubiic Comments Received on CEQA Initial Study/Mitigated Negative
Declaration, State Clearinghouse#2024101104
In accordance with the California Environmental Quality Act (CEQA), an Initial Study/Mitigated
Negative Declaration (IS/MND) for the Airport Road Improvements Project Phase 2 was made
available to the public and interested agencies for a minimum 30-day review period. The agency
review period was managed by the State Clearinghouse(SCH) and closed on November 25, 2024.
The public review period was managed by staff and closed on November 25, 2024.
Two comment letters were received during the public and agency review period. None of the
comments received address the draft Mitigated Negative Declaration findings or the
accuracy/completeness of the Initial Study and therefore do not require written responses. In
addition, comments received on the public draft IS/MND do not identify new significant impacts
or significant new information that would require recirculation of the draft IS/MND pursuant to
CEQA Guidelines Section 15073.5.
Comments that are unrelated to the CEQA document have been routed to the appropriate
department or division, and the commenter has been contacted directly by staff.
Letter 1
Docusi�n Envelope ID:4421�CD2-D4&4-4A21-�B91-QDB9G1733DQ8
k �, , State of�aliforr�ia—�iatural Resc�urc�s R�ency ���1�������. �csv��rr�r �� ���
�� C7E��RTME��1T t�F �IS�I�Ai��WILQLI���� ��1����t���.����t� ���������r� �' '������� `��'�
° IUarthern �2egion G� �`
6�1 Lt�cusf Street ,`t�+ `"
1�edding, �A 96401
� vrx+.ls'ef�t�l��lv .5.�::.;.'',.C.,�(,�=:r'.
�IC7V�1�'i1�7�:C `�i�, ����
T1��Gt'1� �ii,�ft�'��'
Assc�ciate �nvironmental Specialist
City c�f Redding Pubfic Works C��partment
Engineering aivisiar�
777 �y�ress Aver�ue
��dding; CA 9bC�01
�il<��iml������:l;y'�.�I��c�'�:'���I,������:C ��wR
s � r. � � ' r i �� T � r s �;
�i��ST� �C�Ui�T�, ST�TE �LE�RI �H�USE �U �ER ��2410i 1��
Dear T�ffany Lightle:
The �alifc�rnia C7e�artmen# c�f Fish a�d V�lildlif� (CaFW) has reviewed the Initia(
St�t�y ar�d 1vlitigat�d Negafive C�ec[aration (IS/tv9NDj, dated 4cfober 2024, f�r
th� abav�=ref�rencec! proj�ct �Prc�jecf}. CC�FW a�preeiat�s fihis o�p�r�unity to
��mm�nt on the Prc�j�ct, pursuar�f ta the Ccsliforr�i� Envirc�nmen#al C�uality Act
{CEC�Aj �uic��lin�s�:
F ,s �i�
CDFW is �alifc�rr�ic�°s Trustee Ac�ency far fish an�l wiidlife resc��arc�s an� holz�s
thc�s� r�sc�urces ir� trust by statut� for all the q�eopie of fhe state (Fish � G;
c�c�e, §� �i �.�; subd, �a) � i���; �u�. �es�urce� co�e, � 2��70; c�c�,�
�uid�lines � 15�86, subd. (aJJ. CD�W, in its Trustee Ager�cy ca�acity, hc�s
jurisdic#�an �ver the conservatic�n, �rc�tectic�n, ar�c� mane��emen� �f fish;w1dlife,
native plants, and habitafi r�ecessary far biologically susfiainabie �c�p�latic�ns c�f
th�se species (Id., � l�tJ2). Simil�rly, ��r �urpos�s c�f CEC��,, C'DFW is charged by
law to provide, as avaiicsble. bic�lc�gic�1 expertise durir�g public agency
�r�vironmer�tal r�view effc�rts, fo��sing specff�cally c�r� prc�jects ancl related
activ�#ies t�at have the poter�tial fic� aclversely affect fish and w�ldlife resc�urces.
� GEQA is cc�dified in the Califc�rnia Pvblic R�saurces Cade in secti�n 21�00 et seq. The
'"CEQA Guiclelines" ar� foun�l in Title 14 of th� Califc�rnic� Cc�de af Regula#ians,
cQmrrrencing with secti�n 15�Q0.
�c�ns��in� �'a��c��nia's `�il�cllli��a5'anc� ����
aacusign Envelppe ID;4421RCd2-D484-4A21-8B91-ODB9G1733D08
Tiff�ny Lightl�, Assc��iafie Envirc�nmenfial Specialisf
City of Redding Public Wcarks Department
R�ovember 22, �U24
Page 2
�DFW is alsQ s�bmittinr� cc�mmen#s as a R�spc�ns�ble Agency u�cler CEQA (Pub.
�esources Cr�t��, � 21�69; CECC�A Guidelir�es; § �538i J. CaFW' expecfs �i�afi it
mc�y need tc� exercise re�ulatc�ry authdrify as pravided by the Fish and �ame
Code. Lidc�vvise; tc� the ext�r�t irn�lerner�fiatic�n c�f the Prt�ject as prc�posed may
res�dfi ir� "take" �s defir��d by sfic�t� lavv, �af c�ny speci�s �arr�t�;cfed ur�der fihe
Calift�rnia E�dan�ered Spec�es Act (CESAj (F�sh � �: Cc�de> � 2t�50 et s�q.) or
stafe listed re�re plar�#s pursuar�fi tc� th�; Nc��iv� Plant Prc��ection Rcfi (NPP�, Fis� �
G. C�de � 1940 efi seq.j, authc�rizc�tic�r� as p�rc�videcl by the appli�c�ble �►sh ar�d
Garr�e CQde may be required:
r�j��t ���ri fi�r�;
The prc�j�c# area is Ic�cc.�ted alor�g �,irp�rfi R�ad in Redding, Caiifc�rnia frc�m
Harfnell Avenue fc� Biliy Jear� Lane. T�e Project as cl�scribed ir� fhe 1SMND, is as
fall�ws:
",Tl�e prajeet wc�ulc� provide twc� 12-foot wide firavel laries with 8-fc�ot paved
shc�ulders rnciu�in� 3-�eet of shc�vJderbcrc�in�. A nc�rth bc�und left turn �ocket
wc�uld b� �onsfructed at Billy Jean Lane and the sc�uthbourid right turn pockets
at Preserve Boulevard anc!Argyfe Rc�ad wc�uld be lerrgfhe�ed. The road
widenr'ng wavld i�e intermrffent (based c�n currer�t widthsJ ar�c� vary frc�rn Q- I5
fieet. Widenit�g would'alternate between the east and west sides c�f the re�ad,
anc� in some facations thc raac� would be wi��ned a�Qng �ath s�des. C�rar'rrage
irr the area cr�nsisfi�primarily of rc�ac�sid� ditches, with onPy a few culverts;
RelQ�afic�n nf exisfir,g difches wQuld be included wifh the praject:
Apprc�ximately 125 f�et north c�f 8illy Jean Lane c�n �xisting One 3t7=i�c1�
diameter an�( 77-fc�c��fc�ng reinf�rced cc�ncrete cvlvert will be extended 8-feet
fe� the wes�, and 6-facat cc�ncrete flared encl sectiQns wi{! k�e add�d to the inlet
ar�d the c�utlet."
� �r��� � ��� �� �ti�ras
CC�FW sficaff rec�gnize fha# the Gity c�f R�dding (Lead AgerrcY) have tak�r�;
many c�f the apprc�priate steps needed fifl evaluafie fhis PrQject's im�acts fc�
bi�ic��ical resources: CdFW offers the folle,wir�g camments ancl
recomm�ndations fc� furfher as�isfi fihe Lec�d Agency in aclequately identifyir�g,
avc�ic�in�; and minimizin� pc�terrtially significanf, dir�ct, and indirect im�act� an
b�c�lc�c�icc�l resvurc�s with fihe irr�plementcstic�n �f fihe Projecf.
�fl�r� �r� 5tr� I ����s
The ISNI�lD indicates apprc�xirr�ately �:001 c�cre c�f�ecasc�n�l w�#1and, U,C�tJ4 acre
c�f fresh �merc��nt wefianc�, and 0,001 acre afi intermitt�n� stream wc�ulc� be
poeusign Envelope ID:4421RCD2-[�484-4A21-8B91-0DB9G1733D08
l�iffany Lightl�, Associate Env►ronmer�tal Sp�cialist
City c�f R�ddir�g Public Works De�artrrient
i�c�vem��r 22, 2�24
Page 3
p�rmc�nently im}�acted wifih �he im�lementatic�r� c�f the Prc�jecfi. �,c�ditior�ally,
th� I5M�JC� ►ndicafies appraximately 0.�24 c�cre of r�c��-vegetc�#ed clitch would
be relocafi�c� tc� accomrn�cic�#� fhe n�w wid�h of the rc�c�dway a�d pc�fiential
indir�cfi irnpc��ts may �ccur due tc� erasic�n an�l sedimentatic�r�, accider�fial fu�l
leaks; ar�d spills: The I�N1i�d prc�pased Mitigati�n Nte��ure 2, �ar im�acts fc�
wetlar�ds vv�ich states "To com�ensate for direct im�acts on ,�c�fential habitat
fr�r vernal ,�c�r�l tad��le shrimp and vernal pool fatry shrimp, the City wiil
purct�ase the crppr��ricste mifigation credits frc�m a U.S. Fish ar�d �lilclirf�
{USFWSJ-a,�prc�vec� mitigatic�� ban��r ar�other site to k�e ap�rc�ved by the
USFWS. Permanent im�acts will be miti�ate�' afi a min�mum rati� c�f 3:1 (�hr�e
acres presenred for each acre of pc�tet�tial habrfaf re�nc�vedJ. Tempc�rary
impacts will be mitig�ted c�n-site at a i:1 ratac�:„
Vernal poals �rcavid� unique wetlanci habitc�t �or mar�y spe�ial status and
endemic g�lanf ar�d aquc��ic wildlife speci�s.The Fish ar�c� �am� Commissiar�
palicy r�garding wetland re�ourc�s discc��rag�s devel�pment or cc�nversicr� r�f
w�tlar�d� fihafi results ar� any net Igss c�f w�filand acr�a�� c�r hak�itat vc�lue�:
Hak�itai� cc�nv�rsior�, canstructic�n, grading, c�nd fill activ�ti�s wi#hin these
f�c�fiur�s also hc�s the pc�fiential tQ im�act de�wnsfr�am wc�t�rs �s a resuifi r�f
Pr��ect site impacts leading t� �rc�sian, scour, and changes in str�am
marphc�ivgy. A mi#igafiion ratrc� of 3;l, c�r mc�re, begins t4 address fhe temporal
and fur�cfic�r�al ioss of#he wetlands in the Pr�ject area, �sn�9 accc�unts fc�r the
loss of a resc�u�c� a�d l�abitc�t #yp� fihat has declir�ed more than 90`��
throughc�uf Calif�rnic��_ There#ore, Ct�FW suppc�rts the mitiga#ic�n ratic� af a
minimum o# 3.� fc�r #he perman�n� impacfis to w�tlands in the Prc�j�cfi ar�a, an�l
Ic�c�ks f�rwc�rd tv reviewing t�e La�� and Str�ambed ,�It�ration r�c�tificc�tian, as
nated in the ISMND;
L k� r� �tr� � It r ti�r� r�� �r�#
Fish and �ame Cc�de secfit�n 1602 r�quGres any p�rsc�r�, state or lacai
�ov�rr�menfic�l agency, c�r public utilify ta r��tify CDFW prior tc� b�gir�ning any
ac�ivity fhat may d� ar�e �r m�r� af the fc�llc�wing:
� Subsf�sr�tfal{y divert �r c�b�truef th� natural flov�r �f th� bed, chann�i, �r
bank c�fi ar�y r�ver, strec�m, c�r lake; c�r
� Substan#ialiy change or us� ar�y mc�t�rial fram th� bed> chann�l, or bank
Qf any river, stret�m, or fake; Qr
� https:/Jfgc.ca,gc�v/Abc�ut/Pc�iicies/Miscellanedus#V�letlands
3 htfps;/jwildlife.�a.gov/��ns�rvatic�n/Plr�ntsJVernal-Pools
Dacusign Envelope l�:4421ACD2-Q484-4A21-8B99-QQ89G1733�U8
Tiffany Lightle, Assc�ciate Eravirc�nm�r�tal Speciafis#
C►ty c�f Redding Puk�lic VVc�rks Depar�mer��
Nc�v'ember 22, 2024�
Pac,�'e 4
� Deposit c�r dispc�s� of d�bris, wt�si�e, or ather rr��fierial cc�ntaining
cru�abled; flaked, c�r �rc�unc� pc�vern�nt wher� if mc�y pc�ss ir�tc� ar�y rav�r,
sfiream, or i��e.
To e�btain ir�formatian ak�o�t the 1602 i�r�fiification prc�cess, please acces� the
9 ����-���r���..��rc� E���;��a�.�3�.,�,���_���f's���,�_���r�4�����W��,�:
Sa� � �� c�#a
CEC�A requires tha# ir�formatEon developed in e�virc�nmenfic�l dQcuments is
inccar�orated intc� a databc�s� v�hich may b� used tc� make subsequer�t �r
supplemenfial env6rc�nmet�t�! determir+atic�r�s. (Puk�lic �esaurces Cc�de, § 210U3,
s�bd: (e).) Accc�rdingly> pfease r�pc�rt any spe�ial status species and natcaral
cQmmunities detected during surveys tc� fhe �_�_����t���._�?_.__���_���,¢._},:��� �{+`�:'�`���°;�,
��;����-���:����:� (CNQi�6).
r� ��at� ��ll �� �i
CDFW is charr��d with preservinc� and pratecfiing th� stafe's diverse ecc�sys#erns
and wildllfe; therefQre, CC7FW maintains a sfirc�ng commifiment tc� collabe�r�fie
with other sfate ag�ncies. CC�fW ►s �nthusiasfic ta cc�ntinue assisting the Lea�l
Agency�n impl�men#inc� cc�mpr�hensive avoidance ar�d m'rr�imizc�tian
strategies for th� benefit af Cali#orraia's ser�sitive res�urc�s anc� aligni�g
r�gulatc�ry framewc�rks.
��r��l�s��
�L3FW appreciates the ap}�ortunifiy tc�camment crn fh� iSt�h�D �nd to assisf the
Lead A�er�cy in idenfifying, avoiding, minimizing �nd mi#igatir�g pc�fienfially
significant Prc�ject impac#s fc� biolac�ical resources. lf you have c�nY quesfiic�ns;
please c�nfiact Erika lacc�na, Senic�r Envirc�nmental Scientr�f (Specia[isfi} by
�+��.�1 al f��€ ��i_^`i',�17'�f....�,.d�,..k����.l.w�� ��'v"�§E�.R����..`.�LL��.��Ev'��. . � .
�ICI��":I"Uw�/,
�Oacu3lgned�py:�
�� ��
. iQ82ADE7363R474.,�.
Tina Bartlett, Regianal Mc�nag�r
N�rthern Re�ic�n
� ht�ps:/1wildlife.ca.g�vJCor�servatic�nlEnvirc�nmentai-ReviewJ��A
� htt�s;liwildlifie,ca.g�v/DataJCN�DB
docusign Envelope 1L:4421,4CC?2-D484-4A21-8B91-ODB9G1733D48
Tif�any Lightle, �ssc�ciat� E�vironr�ner�fai Sp�e�i�list
Cifiy c�f R�dcling Puk�lic Works Dept�rtmer�t
Nc�vember 22, 2Q24
�ag� 5
ec: State Clearinghouse
�3i��1 � �= t ���]��€ 8�"f.;`.i✓', `�"� �t � tW.� � g�a"��
EI'I�� IC�CC�i'1Cy
Califc�rn►a I�epcsrtr�nent �fi Fish and Wildli�e
i��_' �������'t i{ ��4 �:;� �t' i�{ (�#1 �_.� � C�°�?..w
Letter 2
From: Ben Abrahamsen <benCc�frontierc�,cam>
Sent:Tuesday, October 29, 2024 6:12 PM
To: Lightle, Tiffany<�Ei htle(�citvafreddin ,or�>
Subject:Airport Road Phase 2 Project Inquiry
Cx��1�}C"��I:T��is ert��il;:�r€�;[r��t�d fr�rrs r��.t�s€��r t}�fk�City uf Red�i3��; }?l�e�st�he car{xF��€with Iir7kGa�.�r�tt�chr�����^.,,
Hi Tiffany,
I live on Billy Jean Lane, and I read your mitigated negative declaration statement regarding
Airport Road Phase 2 project. Are the plans developed yet for this project? We're thrilled to
hear the improvements. Turning left onto Billy Jean lane when travelling northbound on
Airport Road has always been hazardous. Will the new left-turn pocket provide for safe
turning onto Billy Jean Lane from Airport? Will there be a southbound right turn pocket for
Billy Jean Lane as well?
I understand that you are not the designer, so you may not be able to answer these
questions. But, if you're able to pass them along to the responsible party, I
would appreciate it.
Thank you!
r
Mechanical Engineer
530.232.6160 ext. 110��ag�
wvorvvofron�ierceocorrr ' ,
���a
2727 Bechelli Lane
Redding, CA 96002