HomeMy WebLinkAbout _ 4.11(e)--Project Acceptance BS 5222 Redding Aquatic Center 50 Meter PoolC IT Y OF REMDINO�" AN CITY OF REDDING REPORT TO THE CITY COUNCIL MEETING DATE: February 20, 2024 FROM: Michael Webb, Public Works ITEM NO. 4.11(e) Director ***APPROVED BY*** Am 6eau *'orksMirectcrs ?.tit}? ry 1pis n, Ci ars e 2'13/202 mwebb@cityofredding.org btippin@cityofredding.org SUBJECT: 4.11(e) --Project Acceptance, Bid Schedule No. 5222, Job No. 7336, Redding Aquatic Center 50 Meter Pool Improvements Recommendation Accept Bid Schedule No. 5222 (Job No. 7336), Redding Aquatic Center 50 -Meter Pool Improvements, awarded to Western Water Features, Inc., as satisfactorily complete, with a final cost of $1,255,347. Fiscal Impact The Redding Aquatic Center 50 -Meter Pool Improvement Project (Project) was funded by the General Fund. The total project cost is $1,255,347 and includes surveying, design, bidding, construction, field engineering, inspection, and contract administration. Alternative Action The City Council (Council) may choose not to accept the project as satisfactorily complete, and advise staff on how to proceed. Background/Analysis On November 2, 2021, the Council awarded a construction contract for the project to Western Water Features, Inc. for $908,765 and approved a $110,000 construction contingency fund. Also authorized was $118,000 for contract administration and construction inspection fees, and $50,000 for project development costs. The City Manager was authorized to approve additional increases in either the construction management or construction contingency amounts up to $15,000, for a total authorized project amount of $1,201,765. Project development costs include engineering, environmental, and consultant services. Report to Redding City Council February 14, 2024 Re: 4.11(e) --Project Acceptance BS 5222 Redding Aquatic Center 50 Meter Pool Page 2 Western Water Features, Inc., has completed all items of work for the project as of May 26, 2023, which was within the contract time frame. The project warranty period expires one year from the completion date. Subsequently, the Public Works Department filed a notice of completion with Shasta County. During construction, additional funds were requested or transferred to cover the costs of change orders as detailed in the attached reports. Additional funds included an increase of $20,000 to the construction management budget and $145,000 to the construction contingency budget to fund change orders, for a new total authorized amount of $1,351,765. During construction, there were six change orders in the amount of $239,582 leaving a balance of $15,418 in the contingency fund. The final project cost was $1,255,347. The project included the removal of existing 50 -meter pool plaster and tile, as well as the removal of the activity pool water slide. Environmental Review This action is not a project as defined by the California Environmental Quality Act (CEQA). On November 2, 2021, Council determined that the project is categorically exempt from environmental review under CEQA Guidelines, pursuant to Section 15301, and no further action is required. Council Priority/City Manager Goals • This agenda item is a routine operational item. Attachments ^Location Map 11-2-21 Previous Staff Report 02-06-23 Transfer of Project Funds Memorandum 2-21-23 Previous Staff Report Cost Summary Awarded Amounts Adjusted Amounts Actual Cost 1 �= Additional New Total $ d i $50,000 Project Development Costs $50,000 $0 $50,000 Construction Contract $1,018,765 $145,000 $1,163,765 ; Contingency a r Construction Contract �� $1,148,347 Contract Change Orders 4� $118,000 $20,000 $138,000 Contract Administration & $57,000 Inspection City Manager Funds $15,000 ($15,000) $0 $0 Total $1,201,765 $150,000 $1,351,765 $1,255,347 The project included the removal of existing 50 -meter pool plaster and tile, as well as the removal of the activity pool water slide. Environmental Review This action is not a project as defined by the California Environmental Quality Act (CEQA). On November 2, 2021, Council determined that the project is categorically exempt from environmental review under CEQA Guidelines, pursuant to Section 15301, and no further action is required. Council Priority/City Manager Goals • This agenda item is a routine operational item. Attachments ^Location Map 11-2-21 Previous Staff Report 02-06-23 Transfer of Project Funds Memorandum 2-21-23 Previous Staff Report b0 0 SACRAIWSAfro RIVER CITY OF REDDING PUBLIC WORKS DEPARTMENT 4ya EXHIBIT A REDDING AQUATIC CENTER 50 METER POOL IMPROVEMENTS LOCATION MAP REPORT TO THE CITY COUNCIL MEETING DATE: November 2, 2021 FROM: Chuck Aukland, Public ITEM NO. 4.11(g) Works Director ***APPROVED BY*** Construction Contract + Contingency $1,018,765 2 u and, Public Works s erec00 n„� aSa, Dffcc r z > caukiand0a d.redding.ca.usbtippin@cityofredding.org $15,000 : 4.1l(g)--Award Bid Schedule No. 5222 (Job No. 7336) Redding Aquatic Center =Meter ool Improvements Recommendation Authorize the following actions relative to Bid Schedule No. 5222 (Job No. 7336) Redding Aquatic Center 50 Meter Pool Improvements Project: (1) Award to Western Water Features, Inc. in the amount of $908,765; (2) Approve an additional $118,000 to cover the cost of administration and inspection fees; and $50,000 for project development costs; (3) Approve $110,000 to provide construction contingency funding; (4) Authorize the City Manager to approve additional increases in either the construction management or construction contingency amounts up to a total of $15,000; and (5) Find that the Project is categorically exempt from the California Environmental Quality Act per Section 15301(d) - Existing Facilities. Fiscal Impact The Redding Aquatic Center 50 Meter Pool Improvement Project (Project) is being funded by the General Fund. Cost Summar Item Estimated Project Development Costs $50,000 Construction Contract + Contingency $1,018,765 Contract Administration, Inspection, Testing $118,000 Additional City Manager Authority $15,000 Total Pf*ct Costs $1,201,765 Project Budget $1,800,000 Project cost components are estimates and some shifting of the project development, construction management, and construction contingency funds may be necessary to balance the Report to Redding City Council October 25, 2021 Re: 4.11(g) --Award BS No. 5222, Redding Aquatic Center 50 Meter Pool Page 2 project within the approved budget. Alternative Action The City Council (Council) could choose not to award the bid for the Redding Aquatic Center 50 Meter Pool Improvement Project and provide staff with alternate direction. If the project is not awarded, the 50 -meter pool at the Aquatic Center, as well as the waterslide at the activity pool, will have ongoing maintenance and be in jeopardy of failing. Background/Analysis Attached is a tabulation of bids received and opened on October 1.4, 2021, for the Redding Aquatic Center 50 Meter Pool Improvement Project. The low bid in the amount of $908,765 was received from Western Water Features, Inc., of El Dorado Hills, California. The engineer's estimate was $1,100,000. Total project development costs for this project are estimated to be $50,000. Project development costs include engineering, surveying, right-of-way, environmental, consultant services, and permit fees. There is $1,800,000 budgeted for the total project. This project includes the removal of the existing 50 -meter pool plaster and tile, in addition to the removal of the activity pool water slide. The project will install new plaster, tile, activity pool water slide, and complete water slide refurbishment. Staff has determined that the project qualifies as Categorically Exempt from environmental review under California Environmental Quality Act Guidelines Section 15301. The project area does not have significant values for wildlife habitat or other environmental resources, and the project has no potential to have a significant effect on the environment. Council Priority/City Manager Goals • This agenda item is a routine operational item. Attachments Bid Tabulation Location Map Notice of Exemption DATE: January 30, 2023 TO: Barry Tippin, City Manager FROM: Chuck Aukland, Director of Pulbic Works SUBJECT: Request for Transfer of Project Funds Redding Aquatic Center 50 Meter Pool Improvements Bid Schedule 5222, Job No. 7336 In accordance with the Council Approved Award of Bid Schedule No. 5222, City Manager Funds (Job No. 7336) to Project Contingency Funds in the amount of fifteen thousand dollars ($15,000) is requested. Additional contingency funds are necessary to cover the change order costs for the replacement of the slide landing. A transfer of $15,000 from the available remaining City Manger Budget is necessary to fully fund these change orders. Current Requested Newly Expended Balance Authorized Increase Authorized Projected Projected Contract $908,765 0.00 $908,765 $908,765 0.00 Contingency $110,000 $15,000 $125,000.00 $123,573 $1,427 Construction Management $118,000 0.00 $118,000 $118,000 0.00 City Manager Funds $15,000 0.00 0.00 0.00 0.00 Total $1,151,765.00 $15,000.00 $1,151,765.00 $1,150,338.00 $1,427.00 There is currentl a balance of $15,000 available in y i City Manager Funds. The existing Construction Management budget has sufficientfun-Wrig -wjj Please call me at 245-7155 or Nick Visconti at 225-4582 if you have any questions or need additional informatio-c. 11,;V2 City Engineer Date City Manager - Date nv/mk Attachments c: Construction Manager Resident Engineer Finance APPROVED CITY OF REDDING REPORT TO THE CITY COUNCIL MEETING DATE: February 21, 2023 FROM: Chuck Aukland, Public ITEM NO. 4.11(a) Works Director ***APPROVED BY*** 4r ikland, Public Winks [erect 2/8/21023 yy ippin,4rtl n e 2/13/202.3 caukland@ci.redding.ca.us btippin@cityofredding.org SUBJECT: 4.11(a) --Approve Increase to Project Budget for the Redding Aquatic Center 50 Meter Pool Improvement Project Recommendation Approve increases to the project budget in the amount of $150,000 for the completion of Bid Schedule No. 5222, Redding Aquatic Center 50 Meter Pool Improvement Project as outlined below for additional improvements: (1) Increase of $20,000 to the construction management budget, bringing the construction management total to $1.38,000; and (2) Increase of $130,000 to the construction contingency budget, bringing the construction contingency total to $240,000. Fiscal Impact The Redding Aquatic Center 50 -meter Pool Improvement Project is being funded by the General Fund. The proposed $150,000 increase in funding is available in the existing allocation for the project in the Parks Division Budget. The total project cost, including the proposed increase, is expected to be $1,950,000. Alternative Action The City Council (Council) may choose to reject the request and provide alternative direction to staff. Background/Analysis On November 2, 2021, the Council awarded the construction contract for the project to Western Water Features, Inc. The project includes the removal of the existing 50 -meter pool plaster and tile, as well as the removal of the activity pool water slide. APPROVED Report to Redding City Council February 15, 2023 Re: 4.11(x) --Approve Increase to Project Budget for Redding Aquatic Center 50 Meter Improvement Project Page 2 During the course of construction, conditions in the field warranted design revisions to meet the original project intent. After the resurfacing of the 50 -meter pool was completed, the water -stop in the expansion joint failed. The pool is leaking a significant amount of water and will continue to do so until it is repaired. The consultant design team recommends replacing the expansion joint with a poured -in place repair. The scope of work for this repair includes the following: providing daily moisture conditioning to the new plaster finish, saw -cutting the old expansion joint (approximately 40" wide by 95 feet), removing and disposing of concrete, placement of dowel in new rebar, using shotcrete in new concrete section, tiling of new sections to match existing sections, repairing any damaged plaster areas (if needed), and finally filling and balancing the pool. The noted changes will result in the contract bid item exceeding the bid quantity and the additional time needed will increase the construction management services required. The additional work will cause the project budget to exceed the awarded amounts. An additional $150,000 is requested to cover increases to the construction contingency ($130,000) and construction management ($20,000) project components. COST SUMMARY Item Awarded Amount Projected Amount Increase Contract Administration, Inspection, Testing $118,000 $138,000 $20,000 Construction Contingency $110,000 $240,000 $130,000 Revised Totals $228,000 $378,000 $1.50,000 Environmental Review This action is not a project as defined by the California Environmental Quality Act (CEQA) Guidelines, and no further action is required. On November 2, 2021, the Council determined that the Redding Aquatic Center 50 -Meter Pool Improvement Project is categorically exempt from review under the CEQA Guidelines, per Section 15301(d) — Existing Facilities. Council Priority/City Manager Goals • This agenda item is a routine operational item. Attachments Previous Staff Report It -2-21. APPROVED REPORT TO THE CITY COUNCIL MEETING DATE: November 2, 2021 FROM: Chuck Aukland, Public ITEM NO. 4.11(g) Works Director ***APPROVED BY*** Construction Contract + Contingency $1,01.8,765 Contract Administration, Inspection, Testing $118,000 kland, Public Works Direct 0/20/202 1 i • . i 4 � Y1 "Y I FI Y L)l"SS SCR St" )fTa'CkL1P caukland@ci.redding.ca.us H btippin@cityofredding.org SUBJECT: 4.1l(g)--Award Bid Schedule No. 5222 (Job No. 7336) Redding Aquatic Center 50 Meter Pool Improvements Recommendation Authorize the following actions relative to Bid Schedule No. 5222 (Job No. 7336) Redding Aquatic Center 50 Meter Pool Improvements Project: (1) Award to Western Water Features, Inc. in the amount of $908,765; (2) Approve an additional $118,000 to cover the cost of administration and inspection fees; and $50,000 for project development costs; (3) Approve $110,000 to provide construction contingency funding; (4) Authorize the City Manager to approve additional increases in either the construction management or construction contingency amounts up to a total of $15,000; and (5) Find that the Project is categorically exempt from the California Environmental Quality Act per Section 15301(d) - Existing Facilities. Fiscal Impact The Redding Aquatic Center 50 Meter Pool Improvement Project (Project) is being funded by the General Fund. Cost Summar Item Estimated Project Development Costs $50,000 Construction Contract + Contingency $1,01.8,765 Contract Administration, Inspection, Testing $118,000 Additional. City Manager Authority $15,000 Total Project Costs $1,201,765 Project Bud et $1,800,000 Project cost components are estimates and some shifting of the project development, construction management, and construction contingency funds may be necessary to balance the APPROVED Report to Redding City Council October25, 2021 Re: 4.11(8) --Award BS No. 5222, Redding Aquatic Center 50 Meter Pool Page 2 project within the approved budget. Alternative Action The City Council (Council) could choose not to award the bid for the Redding Aquatic Center 50 Meter Pool Improvement Project and provide staff with alternate direction. If the project is not awarded, the 50 -meter pool at the Aquatic Center, as well as the waterslide at the activity pool, will have ongoing maintenance and be in jeopardy of failing. Background/Analysis Attached is a tabulation of bids received and opened on October 14, 2021, for the Redding Aquatic Center 50 Meter Pool Improvement Project. The low bid in the amount of $908,765 was received from Western Water Features, Inc., of El Dorado Hills, California. The engineer's estimate was $1,100,000. Total project development costs for this project are estimated to be $50,000. Project development costs include engineering, surveying, right-of-way, environmental, consultant services, and permit fees. There is $1,800,000 budgeted for the total project. This project includes the removal of the existing 50 -meter pool plaster and tile, in addition to the removal of the activity pool water slide. The project will install new plaster, tile, activity pool water slide, and complete water slide refurbishment. Staff has determined that the project qualifies as Categorically Exempt from environmental review under California Environmental Quality Act Guidelines Section 15301. The project area does not have significant values for wildlife habitat or other environmental resources, and the project has no potential to have a significant effect on the environment. Council Priority/City Manager Goals • This agenda item is a routine operational item. Attachments Bid Tabulation Location. Map Notice of Exemption