HomeMy WebLinkAboutReso. 1976-072 - Approving actual cost contract between City and PG&E covering relocation of electric pole line facilities at the north end of Hilltop DriveRESOLUTION NO. Jl.- J7i
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF REDDING
APPROVING AN ACTUAL COST CONTRACT BETWEEN THE CITY AND
PACIFIC GAS AND ELECTRIC COMPANY COVERING THE RELOCATION
OF ELECTRIC POLE LINE FACILITIES AT THE NORTH END OF
HILLTOP DRIVE.
WHEREAS, the City of Redding is in the course of construct-
ing the north end of Hilltop Drive within the City, and
WHEREAS, Pacific Gas and Electric Company maintains
certain electric pole line facilities at said location, which will
interfere with City's project, and
WHEREAS, at the request of City, Pacific Gas and Electric
Company has agreed to relocate said electric facilities, at City's
expense, to accommodate City's project, and has submitted an Actual
Cost Contract to cover said relocation work, and
WHEREAS, the City Council deems it to be in the best
interests of the City and its citizens to approve said Actual Cost
Contract, so that said project may be completed,
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Redding that the Actual Cost Contract between the City
of Redding and P.G. & E., dated July 6, 1976, is hereby approved, and
the Mayor is authorized to execute same on behalf of the City.
I HEREBY CERTIFY that the foregoing Resolution was intro-
duced and read at a regular meeting of the City Council of the City
of Redding on the 6th day of July , 1976, and was duly adopted at
said meeting by the following vote:
AYES: COUNCILMEN: Anderson, Demsher, Gard, Pugh and Fulton
NOES: COUNCILMEN: None
ABSENT: COUNCILMEN: None
ATTEST:
MILDRED L. BRAYTON, City Clerk
FORM APPROVED:
EARL D. MURPHY, Zity ttorney
EE D. FULTON, M.D.
Mayor of the City of Redding