HomeMy WebLinkAbout _ 4.11(b)--Project Acceptance BS 5162 Salt Creek Heights Neighborhood ParkT Y OF
REDDIN
CALIFORNIVCITY OF REDDING
REPORT TO THE CITY COUNCIL
MEETING DATE: August 15, 2023
FROM: Chuck Aukland, Public
ITEM NO. 4.11(b)
Works Director
***APPROVED
BY***
ukland, Public Warks Direct 8/3/2423
ry ippin, Ci ana e : 8/7/2423
caukland&i.redding.ca.us
btippin@cityofredding.org
SUBJECT: 4.11(b) --Project Acceptance, Bid Schedule 5162, Job No. 9618, Salt Creek
Heights Neighborhood Park
Recommendation
Accept Bid Schedule No. 5162 (Job No. 9618), Salt Creek Heights Neighborhood Park Project,
awarded to Builder Solution, Inc., as satisfactorily complete, with a final cost of $1,772,809.36.
Fiscal Impact
Sierra Pacific Land and Development Company and two state grants from the Park Development
Fund in the amount of $1,777,600 were approved for this project. The total project cost,
including surveying, design, bidding, construction, field engineering, inspection, and contract
administration, is $1,772,809.36.
Alternative Action
The City Council (Council) may choose to not accept the project as satisfactorily complete, and
advise staff on how to proceed.
Background
As of February 10, 2023, Builder Solution Inc., completed all items of work on the Salt Creek
Heights Neighborhood Park Project (Project). The contract awarded 210 working days to
complete all elements of construction. Builder Solution Inc., completed project construction
activities 22 working days beyond the contract completion date. Since the project was not
completed within the contract time frame, liquidated damages were assessed. Pursuant to the
contract, liquidated damages were defined as $1,000 per calendar day for a total assessment of
liquidated damages in the amount of $22,000. Additionally, the City penalized Builder Solution
Inc., for violating Public Contract Code 4104 & 4110 in the amount of $5,055.61 for hiring a
non -listed subcontractor to perform bid item work that the prime contractor was listed to
perform. The project warranty period expires one year from the completion date of February 10,
2023.
Report to Redding City Council August 9, 2023
Re: 4.11(b) --Project Acceptance BS 5162 Salt Creek Heights Neighborhood Park Page 2
At its meeting of October 6, 2020, the Council awarded a construction contract to Builder
Solution Inc., of Redding, California, for $1,304,806.82, an additional $17,250 for an Additive
Bid Alternate and approved a $170,000 construction contingency fund. Also authorized was
$292,930 for contract administration and construction inspection fees and $178,410 for project
development costs. The City Manager was authorized to approve additional increases in either
the construction management or construction contingency amounts up to a total of $15,000, for a
total authorized amount of $1,978,396.82. Project development costs include engineering,
environmental, and consultant services. During construction, there were 23 change orders in the
amount of $138,401.90, leaving a balance of $31,598.10 in the contingency fund. The final
project cost was $1,772,809.36 as summarized in the table below:
The project involved the construction of new park facilities; including underground utility
systems, electrical distribution, concrete paving and hardscape, irrigated landscape systems,
picnic and BBQ areas, fencing, a soccer field, playground equipment and other miscellaneous
work.
Environmental Review
Project acceptance is not a project as defined under the California Environmental Quality Act
(CEQA). On June 1.5, 2010, Council adopted resolution 2010-056 certifying the CEQA
Environmental Impact Report EIR-1-08, approving Tentative Map Application 5-15-07, and
approving the Planned Development Plan Application PD -11-07. No further action is required.
Council Priority/City Manager Goals
This agenda item is a routine operational item.
Attachments
^Site map
Previous Staff Report 1.0/06/20
Cost Summary
Awarded Amounts
Actual Cost
Project Development Costs
$178,410
$178,410
Construction Contract
$1,492,056.82
Contingency
Construction Contract +
$1,443,208.72
Contract Change Orders
Penalty Assessments
-$27,055.61
Contract Administration &
$292,930
$178,246.25
Inspection
Additional City Manager
$15,000
0
Authority
Total
$1,978,396.82
$1,772,809.36
The project involved the construction of new park facilities; including underground utility
systems, electrical distribution, concrete paving and hardscape, irrigated landscape systems,
picnic and BBQ areas, fencing, a soccer field, playground equipment and other miscellaneous
work.
Environmental Review
Project acceptance is not a project as defined under the California Environmental Quality Act
(CEQA). On June 1.5, 2010, Council adopted resolution 2010-056 certifying the CEQA
Environmental Impact Report EIR-1-08, approving Tentative Map Application 5-15-07, and
approving the Planned Development Plan Application PD -11-07. No further action is required.
Council Priority/City Manager Goals
This agenda item is a routine operational item.
Attachments
^Site map
Previous Staff Report 1.0/06/20
CITY OF REDDING EXHIBIT A
SALT CREEK HEIGHTS
PUBLIC WORKS
NEIBORHOOD PARK
DEPARTMENT LOCATION MAP
��FoA
CITY OF REDDING
REPORT TO THE CITY COUNCIL
MEETING DATE: October 6, 2020
FROM: Chuck Aukland, Public
ITEM NO. 4.110
Works Director
***APPROVED
BY***
Construction Contract + Contingency
4 A
60and, Pu blt t "s Direct /25T?—o20
iplain, Ca an° c 912 `2[120
caukland@cixed, J
btippin@cityofredding.org
SUBJECT: 4A l(f)- Award BS 5162 (Job Order No. 9618) Salt Creek Heights
Neighborhood irk
Recommendation
r
Authorize the following actions hive to Bld{'shed
Heights Neighborhood Park Pr
(1) Award to Builder Solute Inc. in the aunt c
additional $17,250 for tI I A I Mate;
(2) Approve an additional ver tl
and $178,410 for project development cad
(3) Approve $170,000 to provide constru�It'tonti
(4) Authorize the City Manager to diti
management or construction coour
(5) Authorize sole source purchase ""{Robinl
Poles, Tree Climber, Spinner Bowl, Hi11 Cliu
Fiscal Impact
No. 5162 (Job No. 9618) Salt Creek
04,806.82 for the Base Bid, and an
and inspection fees;
ma ses ilax either the construction
j.
�r
total 15,000; and
astle olor Accents, Sitting
3), aalance Net by Kompan.
The Salt Creek Heights Neighborhood Park d mainly by the Sierra
Pacific Land and Development Company and two Staff its totaling $165,000 coming from
the Park Development Fund. At its meeting on June 16, 2020, the City Council adopted a budget
resolution appropriating $1,777,600. The remaining balance will come from Engineering
Division Personnel funds for construction management services.
Cost Summary
Item
Estimated
Project Development Costs
$178,410
Construction Contract + Contingency
$1,492,056.82
Contract Administration, Inspection, Testing
$292,930
Additional City Manager Authority
$15,000
Total Project Costs
$1,978,397
Report to Redding City Council October 1, 2020
Re: 4.11(f) --Award BS No. 5162 Salt Creek Heights Neighborhood Park Page 2
Project cost components are estimates and some shifting of the project development,
construction management, and construction contingency funds may be necessary to balance the
project within the approved budget.
Alternative Action
The City Council (Council) may choose not to award the bid for the Salt Creek Heights
Neighborhood Park Project and provide staff with alternate direction. As stated in the June 16,
2020, staff report, without this project, the City of Redding (City) will be in conflict with
agreements already executed with the developers.
Background/Analysis
Attached is a tabulat�;rft�ived and opened on September 22, 2020, for the Salt Creek
Heights Neighbohark Prole' the low bid in the amount of $1,304,806.82 was received
from Builder 51n Inc. of The engineer's estimate was $1,558,000. Total
project develnt costs for this pr ct are estimated to be $178,410. Project development
costs includesgineering, surveying right-of-way, environmental, consultant services and
permit and utt,l connection fees. is $1,777,600 budgeted for this project. The remaining
project costs, to $249,000, will be funded utilizing Engineering Division Personnel funds
which are anti]able as a result of a higher than budgeted overhead rate approved
� S 3
by Caltrans.
This project includes the constr0, on of park
system, domestic water systems electrical, pa-\
picnic and BBQ areas, fencing, cer goals, a}i
Sole sourcing the playground equip j rte
playground is constructed as designed. The pla
for this location. The playground is the signat
chosen due to the unique design and the,""",n
locust which is especially robust. Koh` is
playground in the United States.
Council Priority/City Manager Goals
ities; including, storm drain, sanitary sewer
end hardscape, irrigation system, landscape,
us
0 This agenda item is a routine operational item.
Attachments
Bid Tabulation
Location Map
Notice of Determination
Resolution from June 16, 2020 (available online)
Pictures (available online)
of the
ie look and experience of the
has been selected specifically
c. Kompan's Robina line was
ide of black
this type of
BID TABULATION FOR:
SALT CREEK HIEGHTS NEIGHBORHOOD PARK
Bid Schedule No.: 5162
ITEM
Job No.: 9618
9/22/2020
IDESCRIPTION
UNIT
QTY
ENGINEER'S EST
UNIT
PRICE
TOTAL
Builder Solution
UNIT
PRICE
Inc.
TOTAL
S.T. Rhoades Construction
UNIT
PRICE TOTAL
Site Preparation & Earthwork
1
Mobilization
LS
1
$5,000.00
$5,000.00
$78,000.00
$78,000.00
$263,000.00
$263,000.00
2
Clearing & Demolition
LS
1
$15,000.00
$15,000.00
$11,102.00
$11,102.00
$9,000.00
$9,000.00
3
Temporary Construciton Fencing
LS
1
$5,300.00
$5,300.00
$13,156.00
$13,156.00
$14,000.00
$14,000.00
4
Site Layout and Stakingt
$13,200.00
$13,200.00
$33,280.00
$33,280.00
$20,000.00
$20,000.00
5
Earthwork &Rough Grading
, °" '
1 x$79,200.00
$79,200.00
$54,210.00
$54,210.00
$150,000.00
$150,000.00
6
Project Funding Sign63
2,500.00
$2,500.00
$2,444.00
$2,444.00
$1,500.00
$1,500.00
7
SWPPP (Prepare)'
LS
1
, 000.00
$2,000.00
$2,704.00
$2,704.00
$3,000.00
$3,000.00
8
SWPPP (Implement)
'v` LS
1
,,1,200.00
$11,200.00
$4,238.00
$4,238.00
$42,000.00
$42,000.00
9
Rain Event Action Action Plans (REAPS)
, ' EA
,7 A
50
$100.00
$5,000.00
$139.88
$6,994.00
$90.00
$4,500.00
Storm Drain Systems
10
11
Perforated Pipe (6")
PVC Drain Line (6")
,r "F x,10
} �'„
$34.00
«�
$17,340.00
$9,690.00
$16.90
$50.91
$8,619.00
488
$45.00
$60.00
$22,950.00
$17,100.00
12
PVC Drain Line (8")
80 ,., ,,,,,.> $35 <,��;
$9,800.00
$55.99
13
JPVC Drain Line (10")
LF
12Q„ " $45 Ot .,:,,
$5,400.00
$65.87°°'
''g4w4'
$59.00
$7,080.00
14
PVC Drain Line (12")
LF
11
$55 00 ,v,
$6,325.00
$67.03
,7,70:;3.45
$60.00
$6,900.00
15
Catch Basin (Area Drainings)
EA
1
$1,800 (
$28,800.00
$1,283.75
$20,540.00
$1,500.00
$24,000.00
16
Play Area Catch Basin
EA
3 $2,300,,, ,00.00
$1,958.67
b76fI
$1,850.00
$5,550.00
17
Sanitary Sewer System`
Sanitary Sewer Drain Line (4")
LF
300
4 ;
$45.0, $13,500(1,a
$25.48
$7,644.00
$60.00
$18,000.00
18
Sanitary Sewer Cleanouts
EA
7
$600a°
$4,200.1 r'
$1,935.14
..;$8;b45:g
$1,000.00
$7,000.00
AV
Domestic Water System
'-
19
Backflow Preventer (1.5")
EA
1
„ x,20 004 '00
1$",107.73
2M7.73
$3,000.00
$3,000.00
20
lWater Line (2")
LF
265
$25.00e, ` 25.00
$15.65
.......•.$4,147.5 '
$75.00
$19,875.00
Site Electrical System
21
Electric Service Pedestal & Distribution
LS
1
$18,500.00
$18,500 0 �,4g:�
$17,940.00
$26,900.00
$26,900.00
22
Electrical Conduit/Trenching &Future
Stubouts
LS
1
$22,000.00
$18,975.00
$18,975.00
$30,000.00
$30,000.00
l tl3
Site Paving and Hardscape
23
Concrete Paving
SF
10419
$12.00
$125,028.00
$6.90
$71,891.10
$12.00
$125,028.00
24
Concrete Play Area Containment Curb
LF
359
$40.00
$14,360.00
$55.33
M6r47
$45.00
$16,155.00
25
PI y Area Turndown
LF
67
$25.00
$1,675.00
$62.40
$4,180.80
$150.00
$10,050.00
26
Concrete Planter Curb
LF
138
$25.00
$3,450.00
$58.50
$8,073.00
$115.00
$15,870.00
27
Concrete Mowband (9")
LF
215
$15.00
$3,225.00
$66.30
$14,254.50
$55.00
$11,825.00
28
1 Redwood Header
I LF
386
$5.00
$1,930.00
$46.88
1,t8
$10.00
$3,860.00
BID TABULATION FOR:
SALT CREEK HIEGHTS NEIGHBORHOOD PARK
Bid Schedule No.: 5162
ITEM
Job No.: 9618
9/22/2020
IDESCRIPTION
UNIT
QTY
ENGINEER'S EST
UNIT
PRICE
TOTAL
Builder Solution
UNIT
PRICE
Inc.
TOTAL
S.T. Rhoades Construction
UNIT
PRICE TOTAL
29
Play Area Access Ramp
EA
1
$4,000.00
$4,000.00
$10,114.00
$10,114.00
$5,000.00
$5,000.00
30
Raised Concrete Seatwall
LF
19
$175.00
$3,325.00
$552.50
$10,497.50
$550.00
$10,450.00
31
CMU Play Area Wall
LF
71
$250.00
$17,750.00
$110.50
$7,845.50
$525.00
$37,275.00
32
Concrete Play Area Wall
LF ___66
$300.00
$19,800.00
$110.50
$7,293.00
$400.00
$26,400.00
33
Segmented Terrace Retaining Wall
Lt � �
,n $40.00
$1,720.00
$110.50
$4,751.50
$375.00
$16,125.00
34
Concrete Stairs and Cheek Wall
y, $420.00
$420.00
$11,752.00
$11,752.00
$9,500.00
$9,500.00
35
Fiber Plary Area Surfacing
„ w.�
5492 $4.00$21,968.00
$3.73
$0,4.6
' $3.50
$19,222.00
36
Resilient Play Area Surfacing'
SF
2098
$25.00
$52,450.00
$7.77
`.�1.4..
$30.00
$62,940.00
37
Decomposed Granite Paving
CY
2
„$250.00
$500.00
$2,268.50
$4,537.00
$600.00
$1,200.00
Site Furnishing
38
Group Picnic Structure
LS1
$72,#500.00
$72,500.00
$85,150.00
$85,150.00
$125,000.00
$125,000.00
39
Restroom Building Pad Preparation
L
,00
$18,000.00
$13,000.00
$13,000.00
$4,500.00
$4,500.00
40
BBQ at Group Pinic Area
i ''1 r=4,53'�.,r
$4,533.00
$4,732.00
$4,732.00
$1,450.00
$1,450.00
41
Serving Table
EA
1 , „ , $1,480 50
$1,480.50
$4,472.00
$4,472.00
$1,450.00
$1,450.00
42
43
Pinic Tables
Round Plaza Tables
EA
EA
8
2
$1,450.5 0, .t
$2,208 („ „��
$11,604.00
$4,416.00
$1,729.00
$2,756.00
$13,832.00
$5,512.00
$1,450.00
$1,450.00
$11,600.00
$2,900.00
44
Round Plaza Tables (ADA)
EA
1
$2,24,f,,,,
45.50
$4,732.00
$4,732.00
$1,500.00
$1,500.00
45
Trash Receptacles
EA
2 � f3
�3�Q0
$2,496.00
$4,992.00
$1,150.00
$2,300.00
46
47
Chain Link Fence (4")
Soccer Goals
LF
LS
830
2
WMINW.00 ,� r , 4°;0
$1,500 O(t$3,000 '�
$56.20X46,646.00
$10,088.00
$20,176.00
$42.00
$550.00
$34,860.00
$1,100.00
48
49
Ornamental Fencing and Concrete at CMUi
Wall LF
Park Sign EA
137$.1
1,
Olt.. ..,
$13,70(
$7,1"
156.76
$21,476.12
$8,788.00
$95.00
$10,500.00
$13,015.00
$10,500.00
50
Bike Racks
EA
3
�,; 00.001 „ ,„y ,�'�.'00
A0,279.33
$03`7-99,"'
$950.00
$2,850.00
51
Play Equipment & Swings (2-5 yr. & 5-12 yr.) LS
1
N
$310,000.00 $310,000.00
6,780.8 , ,« $136,780.80
$340,000.00
$340,000.00
Irrigation System
52
53
1 Irrigation System (Complete) SF
Meter & Backflow Preventer with Enclosure
(3") EA
152140
1
$1.75
$5,000.00
66,245 , „` �����°��``$0.36
,
x $8;x.00 $1,950.00
$54,770.40
$1,950.00
$1.11
$13.50
$168,875.40
$13.50
54
Irrigation Controller
LS
1
$25,000.00
$25,000.00
$2,015.00
$2,015.00
$3,000.00
$3,000.00
55
Booster Pump
LS
1
$35,000.00
$35,000.00
$2,145.00
$2,145.00
$49,000.00
$49,000.00
Landscaping
56
Finish Grade & Soil Amendments
SF
152140
$0.45
$68,463.00
$0.39
$59,334.60
$0.29
$44,120.60
57
Shrubs/Groundcovers
SF
1966
$4.50
$8,847.00
$49.99
,$- 8 80:34:
$1.65
$3,243.90
58
Box Trees (24")
EA
7
$400.00
$2,800.00
$1,723.43
`'4,0.14
$385.00
$2,695.00
BID TABULATION FOR:
SALT CREEK HIEGHTS NEIGHBORHOOD PARK
Bid Schedule No.: 5162
ITEM
Job No.: 9618
9/22/2020
IDESCRIPTION
UNIT
QTY
ENGINEER'S EST
UNIT
PRICE
TOTAL
Builder Solution
UNIT
PRICE
Inc.
TOTAL
S.T. Rhoades Construction
UNIT
PRICE TOTAL
59
Trees (15 Gallon)
EA
104
$125.00
$13,000.00
$531.00
$55,224.00
$140.00
$14,560.00
60
Tree Root Barrier Panels
LF
170
$15.00
$2,550.00
$66.19
1,23
$7.00
$1,190.00
61
Bark Mulch
CY
43
$65.00
$2,795.00
$240.50
$10,341.50
$112.00
$4,816.00
62
Hydroseed Turf
SF
1,50172
$0.15
$22,525.80
$0.26
9
$0.09
$13,515.48
TOTAL BASE BID
;:.; a,,
.r
$1,506,659.80i1,O,C16t21i,3jt?68
Additive Alternate
63
Landscape Maintenance
LS
1
X0,000 00
$40,000.00
$17,250.00
$17,250.00
$100,000.00
$100,000.00
TOTAL BASE BID PLUS ADDITIVE ALTERA
The lowest bid shall be the lowest total of the bid prices on the base cttct and the
additive alternate that were specifically identified in the bid solicitatio,y
Shaded areas indicate corrections made in accordance with the Sr)dtM Prc
BID TABULATION FOR:
SALT CREEK HIEGHTS NEIGHBORHOOD PARK
Bid Schedule No.: 5162
ITEM
Job No.: 9618
9/22/2020
IDESCRIPTION
UNIT
QTY
Randy Hill Construction
UNIT
PRICE TOTAL
Gifford Construction Inc.
UNIT
PRICE TOTAL
Trent Consntruction
UNIT
PRICE TOTAL
Site Preparation & Earthwork
1
Mobilization
LS
1
$36,479.39
$36,479.39
$411,713.00
$411,713.00
$76,316.15
$76,316.15
2
Clearing & Demolition
LS
1
$59,124.65
$59,124.65
$2,500.00
$2,500.00
$3,592.59
$3,592.59
3
Temporary Construciton Fencing
LS
1
$9,940.80
$9,940.80
$15,000.00
$15,000.00
$11,845.00
$11,845.00
4
Site Layout and Staking
$15,604.75
$15,604.75
$13,500.00
$13,500.00
$15,990.75
$15,990.75
5
Earthwork & Rough Grading
9.21
$252,169.21
$172,000.00
$172,000.00
$229,200.75
$229,200.75
6
Project Funding Sign
1
157.52
$6,157.52
$1,200.00
$1,200.00
$1,445.09
$1,445.09
7
SWPPP (Prepare)
LS
132.47
$2,132.47
$1,700.00
$1,700.00
$2,961.25
$2,961.25
8
SWPPP (implement)
LS
1
11.07
$32,911.07
$61,664.00$61,664.00
$72,662.56
$72,662.56
9
Rain Event Action Action Plans
EA
50
&1106.62
$5,331.00
$80.00
$4,000.00
$94.76
$4,738.00
Storm Drain Systems
10
11
Perforated Pipe (6")
PVC Drain Line (6")
"F o0
$1,22.20
$62,322.00
23,880.15
$74.00
$79.26
$37,740.00
$93.53
$64.02
$47,700.30
$18,245.70
12
PVC Drain Line (8")
.... . .. . .. ... ... ), ..... ... ..
80 82 $23,195.20
$7 6.00
$21,280.00
$81.24
$22,747. 20
13
PVC Drain Line (10")
LF
12 $186.34
$22,360.80
$79.00
$9,480.00
$70.35
$8,442.00
14
PVC Drain Line (12")
LF
11$185.23
$21,301.45
$80.00
$9,200.00
$75.98
$8,737.70
15
Catch Basin (Area Drainings)
EA
161j"',
_
$2,135.00
$34,160.00
$1,844.27
$29,508.32
16
Play Area Catch Basin
EA
3",'�-�',�',"%",,?",�?�,,", $2 $6 773 $2,400.00
$7,200.00
$2,009.70
$6,029.10
.Sanitary Sewer System
17
Sanitary Sewer Drain Line (4")
LF
300
$77.32,, 3,196.00
$53.00
$15,900.00
$61.67
$18,501.00
18
Sanitary Sewer Cleanouts
EA
7
$1,003, $7,021.77
$700.00
$4,900.00
$381.41
$2,669.87
K
Domestic Water System
19
Backflow Preventer (1.5")
EA
1
.62
gal J, 0.00
65.11 1 . . . ..... A_
$5,23 0.00
$3, 259.74
$3,259.74
20
Water Line (2")
LF
2 5
"$89.03
. . . . . . . . . 45.77
$61.85
$16,390.25
Site Electrical System
..........
21
Electric Service Pedestal & Distribution
LS
1
$20,269.09
$2
"ARE,
06.00
$27,768.23
$27,768.23
22
Electrical Conduit/Trenching & Future
Stubouts
LS
1
$50,973.06
23,601.00
$23,601.00
$27,778.89
$27,778.89
Site Paving and Hardscape
23
Concrete Paving
SF
10419
$12.44
$129,612.36
$10.43
$13.00
$135,447.00
24
Concrete Play Area Containment Curb
LF
359
$44.43
$15,950.37
$37.03
$89.08
$31,979.72
25
PI y Area Turndown
LF
67
$46.80
$3,135.60
$38.00
$2,546.00
$94.29
$6,317.43
26
Concrete Planter Curb
LF
138
$27.25
$3,760.50
$23.72
$70.18
$9,684.84
27
Concrete Mowband (9")
LF
215
$27.25
$5,858.75
$22.60
$4,859.00
$43.32
$9,313.80
28
Redwood Header
LF
386
$8.89
$3,431.54
$12.79
',$,*11i9
$13.58
$5,241.88
BID TABULATION FOR:
SALT CREEK HIEGHTS NEIGHBORHOOD PARK
Bid Schedule No.: 5162
ITEM
Job No.: 9618
9/22/2020
IDESCRIPTION
UNIT
QTY
Randy Hill Construction
UNIT
PRICE TOTAL
Gifford Construction Inc.
UNIT
PRICE TOTAL
Trent Consntruction
UNIT
PRICE TOTAL
29
Play Area Access Ramp
EA
1
$1,007.00
$1,007.00
$850.00
$850.00
$1,263.86
$1,263.86
30
Raised Concrete Seatwall
LF
19
$254.71
$4,839.49
$215.00
$4,085.00
$797.23
$15,147.37
31
CMU Play Area Wall
LF
71
$404.05
$28,687.55
$381.96
2W,,45.1,6:
$435.76
$30,938.96
32
Concrete Play Area Wall
LF
66
$390.95
$25,802.70
$317.06
2i}z
$511.85
$33,782.10
33
34
Segmented Terrace Retaining Wall
Concrete Stairs and Cheek Wall
. , , ,., 408
N",
,r.'"` " X6,219.69
$13,505.44
$6,219.69
$475.58
$2,250.00
Sr,4494�
$2,250.00
$4,619.55
$6,704.13
$4,619.55
35
Fiber Plary Area Surfacing„
w.�
5492„,� $2.22
$12,192.24
$3.221
17,6
$3.40
$18,672.80
36
Resilient Play Area Surfacing`
SF
2098
$34.90
$73,220.20
$28.91
f} If
; $31.15
$65,352.70
37
Decomposed Granite Paving
„�' CY
2
X10.82
$1,421.64
$975.00
$1,950.00
$387.04
$774.08
Site Furnishing
38
Group Picnic Structure
LS
1
$118,0,34.39
$118,034.39
$96,980.00
$96,980.00
$111,613.07
$111,613.07
39
Restroom Building Pad Preparation
„���
$20,963.33
$10,000.00
$10,000.00
$4,382.65
$4,382.65
40
BBQ at Group Pinic Area
i��'. ' 1,;157 95,;, $1,157,99
$1,216.00
$1,216.00
$1,042.36
$1,042.36
41
Serving Table
EA
1 v,,,,.' $1,039.52
$1,039.52
$1,231,00
$1,231,00
$1,066.05
$1,066,05
42
43
Pinic Tables
Round Plaza Tables
EA
EA
8
2
$968.86
$578.9
`'r , `r $7,750,88
,vt .� $1,15,7.98
$1,071.00
$1,701.00
$8,568.00
$3,402.00
$1,012.75
$1,748.32
$8,102.00
$3,496.64
44
Round Plaza Tables (ADA)
EA
1 ,;
$1,993 f.r�' $1,?W0
$1,726.00
$1,726.00
$1,788.60
$1,788.60
45
Trash Receptacles
EA
2
$680.50
$1,361.00
$627.79
$1,255.58
46
Chain Link Fence (4")
LF
830
6fi0.i
$42.00
$34,860.00
$49.75
$41,292.50
47
Soccer Goals
LS
2
$3,885 61
,, 7,771.22
$5,779.50
$11,559.00
$5,831.29
$11,662.58
48
Ornamental Fencing and Concrete at CMU
Wall LF
137
$11��, $99.60
iLCI.
$113.26
$15,516.62
49
50
Park Sign
Bike Racks
EA
EA
1$
3
1'„ .43
"In,$9,554 �.- $&,��.00
s ,9.5 `'� X0.00
$8,251.00
$1,200.00
$5,330.25
$604.10
$5,330.25
$1,812.30
51
Play Equipment & Swings (2-5 yr. & 5-12 yr.) LS
1
$282,536.76
$282,536.76
827.00
;289,827.00
$341,491.35
$341,491.35
Irrigation System
52
Irrigation System (Complete)
SF
152140
$1.32
$20Q 24.80
.k„A �.,,���`$1.10
$167,354.00
$1.31
$199,303.40
53
Meter & Backflow Preventer with Enclosure
(3") EA
1
$15,993.50
$15;55
$12,350.00
$12,350.00
$15,990.75
$15,990.75
54
Irrigation Controller
LS
1
$3,554.11
$3,554.11
$4,500.00
$4,500.00
$3,553.50
$3,553.50
55
Booster Pump
LS
1
$58,050.48
$58,050.48
$50,500.00
$50,500.00
$58,040.50
$58,040.50
Landscaping
56
Finish Grade & Soil Amendments
SF
152140
$0.34
$51,727.60
$0.43
$65,420.20
$1.08
$164,311.20
57
Shrubs/Groundcovers
SF
1966
$1.95
$3,833.70
$23.00
$45,218.00
$1.95
$3,833.70
58
Box Trees (24")
EA
7
$458.11
i6
$585.00
$4,095.00
$456.88
$3,198.16
BID TABULATION FOR:
SALT CREEK HIEGHTS NEIGHBORHOOD PARK
Bid Schedule No.: 5162
ITEM
Job No.: 9618
9/22/2020
IDESCRIPTION
UNIT
QTY
Randy Hill Construction
UNIT
PRICE TOTAL
Gifford Construction Inc.
UNIT
PRICE TOTAL
Trent Consntruction
UNIT
PRICE TOTAL
59
Trees (15 Gallon)
EA
104
$165.86
$17,249.44
$180.00
$18,720.00
$165.83
$17,246.32
60
Tree Root Barrier Panels
LF
170
$8.29
$1,409.30
$40.00
$6,800.00
$13.94
$2,369.80
61
Bark Mulch
CY
43
$132.69
$5,705.67
$105.00
$4,515.00
$132.66
$5,704.38
62
Hydroseed Turf
SF
1,50172
$0.1168
$0.15
;SS
$0.11
$16,518,92
TOTAL BASE BID
;,� „ at,
..
1,x,968,1 °
$2,102,433.07
$2,071,693.84
Additive Alternate
63
Landscape Maintenance
�`�
Alff.
LS
1
O' 00.00
$134,200.00
$85,200.00
$72,000.00
$72,00000
TOTAL BASE BID PLUS ADDITIVE ALTERA
The lowest bid shall be the lowest total of the bid prices on the base
additive alternate that were specifically identified in the bid solicitatic
Shaded areas indicate corrections made in accordance with the S
168.91 $2,187,633.07 $2,143,693.84
BID TABULATION FOR:
SALT CREEK HIEGHTS NEIGHBORHOOD PARK
Bid Schedule No.: 5162
ITEM
Job No.: 9618
9/22/2020
IDESCRIPTION
UNIT
Site Work Solutions
UNIT
QTY PRICE TOTAL
SEL Group
UNIT
PRICE
UNIT
TOTAL PRICE TOTAL
Site Preparation & Earthwork
1
Mobilization
LS
1
$27,474.67
$27,474.67
$12,779.00
$12,779.00
2
Clearing & Demolition
LS
1
$12,989.25
$12,989.25
$45,462.00
$45,462.00
3
Temporary Construciton Fencing
LS
1
$15,124.47
$15,124.47
$16,266.00
$16,266.00
4
Site Layout and Staking
$18,419.43
$18,419.43
$31,050.00
$31,050.00
5
jEarthwork & Rough Grading
�,"`112,560.13
$112,560.13
$212,668.00
$212,668.00
6
Project Funding Sign
�A
1 X1,244.56
$1,244.56
$4,513.00
$4,513.00
7
SWPPP (Prepare)'
LS
1,111.39
$3,111.39
$1,725.00
$1,725.00
8
SWPPP (Implement)
Am ' LS
1
,327.75
$69,327.75
$22,420.00
$22,420.00
9
Rain Event Action Action Plans (REAPS)
«' EA
50
,,$119.39
$5,969.50
$70.00
$3,500.00
Storm Drain Systems
10
11
Perforated Pipe (6")
PVC Drain Line (6")
bF x,10
$64.31
$32,798.10
$9,940.80
$48.50
$41.00
$24,735.00
$11,685.00
12
PVC Drain Line (8")
80 ,., „ ,,,.'> $3 �,' 3=,,
$9,805.60
$41.00
$11,480.00
13
PVC Drain Line (10")
LF
12Q $82 81
$9,937.20
$60.00
$7,200.00
14
PVC Drain Line (12")
LF
11's',>
$83 89
$9,647.35
$49.00
$5,635.00
15
Catch Basin (Area Drainings)
EA
1
$4,536.0 ,,
$72,576.96
$2,650.00
$42,400.00
16
Play Area Catch Basin
EA
3
$1,816«,
a I,
$3,051.00
$9,153.00
Sanitary Sewer System
17
18
Sanitary Sewer Drain Line (4")
Sanitary Sewer Cleanouts
LF
EA
300
7
$45.7q,,, 13,734.00
$9791„��$6,853,77
$45.00
�, $1,179.00
$13,500.00
$8,253,00
Domestic Water Systems
,
19
Backflow Preventer (1.5")
EA
1
4.95 t,�`"7.00
$9,327.00
20
Water Line (2")
LF
265
'$37.96 � �� `.40
4`x$21.50
$5,697.50
Site Electrical System
� ,
21
Electric Service Pedestal & Distribution
LS
1
$28,583.20
$28,583.20
.;,4,5', `
$34,087.00
22
Electrical Conduit/Trenching & Future
Stubouts
LS
1
$38,764.19
$�'23,Zia 1.00
$23,961.00
t .rriv
Site Paving and Hardscape
23
Concrete Paving
SF
10419
$12.20 $127,111.80
$16.00
$166,704.00
24
Concrete Play Area Containment Curb
LF
359
$53.26
$19,120.34
$120.50
$43,259.50
25
Play Area Turndown
LF
67
$53.81
$3,605.27
$3,576.50
$239,625.50
26
Concrete Planter Curb
LF
138
$55.29
$7,630.02
$202.00
$27,876.00
27
Concrete Mowband (9")
LF
215
$41.04
$8,823.60
$197.00
$42,355.00
28
Redwood Header
LF
386
$9.36
77:5� $24.00
$9,264.00
BID TABULATION FOR:
SALT CREEK HIEGHTS NEIGHBORHOOD PARK
Bid Schedule No.: 5162
ITEM
Job No.: 9618
9/22/2020
IDESCRIPTION
UNIT
QTY
Site Work Solutions SEL Group
UNIT UNIT
PRICE TOTAL PRICE
UNIT
TOTAL PRICE TOTAL
29
Play Area Access Ramp
EA
1
$2,898.89
$2,898.89
$5,319.00
$5,319.00
30
Raised Concrete Seatwall
LF
19
$982.30
$18,663.70
$1,118.00
$21,242.00
31
CMU Play Area Wall
LF
71
$718.07
$50,982.97
$497.00
$35,287.00
32
Concrete Play Area Wall
LF
___66
$765.72
$50,537.52
$953.00
$62,898.00
33
Segmented Terrace Retaining Wall
Lt � $713.25
$30,669.75
$493.00
$21,199.00
34
Concrete Stairs and Cheek Wall
t„12,777.33
$12,777.33
$14,585.00
$14,585.00
35
Fiber Plary Area Surfacing
414 `!=
5492
$4.61
$25,318.12
$5.40
$29,656.80
36
Resilient Play Area Surfacing
SF
2098
$27.62
$57,946.76
$21.00
$44,058.00
37
Decomposed Granite Paving
CY
2
X746.74
$1,493.48
$1,540.00
$3,080.00
4
Site Furnishing
38
Group Picnic Structure
LS
j
$182,489.73
$182,489.73
$21,519.00
$21,519.00
39
Restroom Building Pad Preparation
„
,x t
$7,479.87
$18,600.00
$18,600.00
40
BBQ at Group Pinic Area
i ' 1 M,`362 ft
$1,362.52
$1,630.00
$1,630.00
41
IServing Table
EA
1 $1,293.5(Dq
$1,293.50
$1,606.00
$1,606,00
42
43
Pinic Tables
Round Plaza Tables
EA.
EA
2 ,
98,,
$2,066.0 f ,.nj
84
? $9,887,84
$4,132.04
$1,155.00
$1,590.00
$9,240,00
$3,180.00
44
Round Plaza Tables (ADA)
EA
1 ,;
$2,107,h, �
$ 9.11
$1,645.00
$1,645.00
45
Trash Receptacles
EA
2 am
j
$2,048.00
$4,096.00
46
Chain Link Fence (4")
LF
83040:040,0.
..,.;;.
$49.00
$40,670.00
47
Soccer Goals
LS
2
$6,857.4 0 " 714 84
$6,035.00
$12,070.00
48
Ornamental Fencing and Concrete at CMU
Wall LF
137
$21�, ;j
$29,718.04,,,,,,,',''$x,11.00
$15,207.00
49
Park Sign
EA
1
$1 t 08„ i,
$11,06Q V
$t,,r0.00
$8,110.00
50
Bike Racks
EA
3,
, ���07.24 ;a s Q``
x$3.00
$5,349.00
51
Play Equipment & Swings (2-5 yr. & 5-12 yr.) LS
1
$347,933.65
$347,933.65,000.00
„x$253,000.00
Irrigation System
52
Irrigation System (Complete)
SF
152140
$1.49
$22,6 �.��$1.30
$197,782.00
53
Meter & Backflow Preventer with Enclosure
(3") EA
1
$16,801.51
$1,0.1
$11,440.00
$11,440.00
54
Irrigation Controller
LS
1
$3,733.67
$3,733.67
$5,227.00
$5,227.00
55
Booster Pump
LS
1
$60,983.25
$60,983.25
$52,262.00
$52,262.00
Landscaping
56
Finish Grade & Soil Amendments
SF
152140
$0.57
. i 6 19.9
$5.00
$7 f7,700�00
57
Shrubs/Groundcovers
SF
1966
$2.49
$4,895.34
$33.00
$64,878.00
58
1 Box Trees (24")
EA
7
$479.15 1
$3,354.05
$680.00
$4,760.00
BID TABULATION FOR:
SALT CREEK HIEGHTS NEIGHBORHOOD PARK
Bid Schedule No.: 5162
Job No.: 9618
9/22/2020
ITEM IDESCRIPTION UNIT
QTY
Site Work Solutions
UNIT
PRICE TOTAL
SEL Group
UNIT
PRICE
UNIT
TOTAL PRICE TOTAL
59
Trees (15 Gallon)
EA
104
$174.24
$18,120.96
$210.00
$21,840.00
60
Tree Root Barrier Panels
LF
170
$18.67
$3,173.90
$47.00
$7,990.00
61
Bark Mulch
CY
43
$139.39
$5,993.77
$122.00
$5,246.00
62
Hydroseed Turf
SF
1„50172
$0.14
$21,024.08
$0.20
$30,034.40
TOTAL BASE BID
2t10,1,8,r22,8#3Ia93i.70'
Additive Alternate
63
Landscape Maintenance;
.`� LS
1
$x,835.85
$151,835.85
$83,600.00
$83,600,00
TOTAL BASE BID PLUS ADDITIVE ALTERt�
The lowest bid shall be the lowest total of the bid prices on the base
additive alternate that were specifically identified in the bid solicitatic
Shaded areas indicate corrections made in accordance with the SDE
BID TABULATION FOR:
SALT CREEK HIEGHTS NEIGHBORHOOD PARK
Bid Schedule No.: 5162
Job No.: 9618
9/22/2020
ITEM
IDESCRIPTION
UNIT
QTY
Site Preparation & Earthwork
1
Mobilization
LS
1
2
Clearing & Demolition
LS
1
3
Temporary Construciton Fencing
LS
1
4
Site Layout and Staking
r t ,,
5
Earthwork & Rough Grading.,
�`'
1�
6
Project Funding Sign
1
7
SWPPP (Prepare)''
LS
1
8
SWPPP (Implement)
LS
1
9
Rain Event Action Action Plans (REAPS)E',°
EA 1
50
Storm Drain Systems
10
Perforated Pipe (6")LF
,
x,10
11
PVC Drain Line (6")
12
PVC Drain Line (8")
80
13
PVC Drain Line (10")
LF
12Q
14
PVC Drain Line (12")
LF
11,w,,
15
Catch Basin (Area Drainings)
EA
16
Play Area Catch Basin
EA
3
Sanitary Sewer System
17
Sanitary Sewer Drain Line (4")
LF
300
18
Sanitary Sewer Cleanouts
EA
7
Domestic Water System
19
Backflow Preventer (1.5")
EA
1
20
Water Line (2")
LF
265
Site Electrical System
21
Electric Service Pedestal & Distribution
LS
1
22
Electrical Conduit/Trenching & Future
Stubouts
LS
1
Site Paving and Hardscape
23
Concrete Paving
SF
10419
24
Concrete Play Area Containment Curb
LF
359
25
Play Area Turndown
LF
67
26
Concrete Planter Curb
LF
138
27
Concrete Mowband (9")
LF
215
28
Redwood Header
LF
386
UNIT
PRICE I TOTAL
BID TABULATION FOR:
SALT CREEK HIEGHTS NEIGHBORHOOD PARK
Bid Schedule No.: 5162
Job No.: 9618
9/22/2020
ITEM IDESCRIPTION UNIT
UNIT
QTY PRICE
29
Play Area Access Ramp
EA
1
30
Raised Concrete Seatwall
LF
19
31
CMU Play Area Wall
LF
71
32
Concrete Play Area Wall
LF
,..66
33
Segmented Terrace Retaining Wall'.
EA
34
Concrete Stairs and Cheek Wall
Round Plaza Tables
EA
35
Fiber Plary Area Surfacing
Round Plaza Tables (ADA)
5492
36
Resilient Play Area Surfacing
SF
2098
37
Decomposed Granite Pavinq�
Cy
2
TOTAL
Site Furnishing
38
Group Picnic Structure
,LS
,1
39
Restroom Building Pad Preparation
L �,
40
BBQ at Group Pinic Area
, �WWI
41
Serving Table
EA
1 ,.
42
Pinic Tables
EA
8,1
43
Round Plaza Tables
EA
2
44
Round Plaza Tables (ADA)
EA
1
45
46
Trash Receptacles
Chain Link Fence (4")
EA
LF
2
830
47
Soccer Goals
LS
2
48
Ornamental Fencing and Concrete at CMU
Wall LF
137
49
Park Sign
EA
1
50
Bike Racks
EA
3
51
Plav Equipment & Swinas (2-5 vr. & 5-12 vr.) LS
1
TOTAL
irrigation System
52
Irrigation System (Complete)
SF
152140
53
Meter & Backflow Preventer with Enclosure
(3")
EA
1
54
Irrigation Controller
LS
1
55
Booster Pump
LS
1
Landscaping
56
Finish Grade & Soil Amendments
SF
152140
57
Shrubs/Groundcovers
SF
1966
58
Box Trees (24")
EA
7
BID TABULATION FOR:
SALT CREEK HIEGHTS NEIGHBORHOOD PARK
ITEM
Bid Schedule No.: 5162
Job No.: 9618
9/22/2020
IDESCRIPTION
UNIT
UNIT
QTY PRICE TOTAL
59
Trees (15 Gallon)
EA
104
60
Tree Root Barrier Panels
LF
170
61
Bark Mulch
CY
43
62
Hydroseed Turf
SF
1„50172
TOTAL BASE BID
Additive Alternate � � I My
63 ILandscape MaintenanceLS 1 1 T �1 d
TOTAL BASE BID PLUS ADDITIVE ALTS
The lowest bid shall be the lowest total of the bid prices on the base
additive alternate that were specifically identified in the bid solicitatic
Shaded areas indicate corrections made in accordance with the S
r /L
A
h �
ft VEN3URPECVO Q
t BUENA W
uj
Z � Z
MO COVE OR
s W Y O
t � l
J
UJ M
WLLJ
Q
U
0RE00N 1R�Y V J
z to
p�0 .'N838V i s s uj
.
M31A Vl5VH5 z f^, t fy y�
y W
m m 8010IA 08 N3360 NBnH3 " / 7
a ' W r a aJ
" o N83 N8nHo y�.oE ^ a e
J 6_ 4 1
I113H038 / pa
�-�
Q ON Y
G d��
58273
✓p c w
_ {/YJ L
N Y
® W
do m JFe= U
W
� t
Ff
= tll
t}
H Z
,t
V O CUYAHOGA PKWY
♦ F—
pQ % u
(L 0y
P
�,
6nx
CITY G.REDDING
DEVELOPMENT SERVICES DEPARTMENT
PLANNING DIVISION
777 Cypress Avenue, Redding, CA 96001-271
P.O. Box 496071, Redding, CA 96049-6071
530.225.4020 FAX 530.225.4495
SHASTA COUKrY CLERK
NOTICE OF DETERMINATION
To: 0 Office of Planning and Research FROM: City of Reddin
P.O. Box 3044, 1400 Tenth Street, Room 212 Development Ttervices Department
Sacramento, CA 95814 777 Cypress Avenue
Redding, CA 96001
IR
County Clet,
Filing of
i of Determination in
U=
(If submitted to Clearinghouse)
ect
Subject:
with Section 21108 or 21152 of the Public Resources Code
530-225-4020
Person Area Code/Telephone/Extension
VAI
g
A
Project Description: 440 residential nedwith ix of housing types, including single-
family, multiple -family, cluster homes with garden C1 ts, andGusto( sites; 127 acres of natural open
'j"
space; and a 13,9 -acre neighborhood park with a Firs. The project'o includes construction of an internal
circulation network, on- and off-site utility exdrape rmplrements necessary to serve the
lots; an extension of Buenaventura Bottle oposed Project; and two new
street connections to SR 299 at buildout.
This is to advise that the City of Redding has approved the above-described ne 15, 2
and has made the following determinations regarding the above -describe
- ...........
1. The project 0 will N will not have a significant effect on the
2. ®An Environmental Impact Report was prepared for"'b"
kht to provisions of CEQA.
..... . . ..
..........
0 A Negative Declaration was prepared for this project pursuant to the provisions of CEQA.
3. Mitigation measures N were 0 were not made a condition of the approval of the project.
4. A Mitigation Report or Monitoring Plan IR was 0 was not made a condition of the approval of the project.
5. A statement of Overriding Considerations 0 was X was not adopted for this project.
6. Findings IR were 0 were not made pursuant to the provisions of CEQA.
This is to certify that the final EIR with comments and responses and record of project approval, or the Negative Declaration, is available
to the general public at Redding City Hall, 777 Cypress Avenue, Redding, California.
Date Mailed: tic
Date Received 0as Dea
for filing: Development
Se es Department
Envirdoc I O\NOD-S 1507-SaItCreek,wpd
RESOLUTION NO. 2020-071
A RESOLUTION OF THE CITY OF REDDING APPROVING AND ADOPTING THE
41ST AMENDMENT TO CITY BUDGET RESOLUTION NO. 2019-050
APPROPRIATING 51,777,600 FOR THE SALT CREEK HEIGHTS PARK
DEVELOPMENT PHASE ONE FOR FISCAL YEAR 2019-20
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OFREDDING
THAT Budget Resolution No. 2019-050 be and is hereby amended as follows:
FUND DIVISION DESCRIPTION INCREASE DECREASE
128 619 Salt Creek Heights $1,627,600
128 618 Creek Heights $150,000
THAT acconumbers re ing adjustments by this Resolution are as follows:
USE SOURCE
OF FUNDS OF FUNDS
Decrease (Ince
128-618-1-0001
Increase Revenues
128-619-9-5400-01
Increase Expenditures
128-619-4747-03
128-618-4747-03
nning Balance
THAT the purpose is to app
for fiscal year 2019-20.
I HEREBY CERTIFY that
Council of the City of Reddii
by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
COUNCIL M
COUNCIL MEMBERS: None
COUNCIL MEMBERS: None
COUNCIL MEMBERS: None
AT 'ST:
r
PAMELA MIZE, Ci (Cl rk
ADAM McELVAIN, Mayor
FORM APPROVED:
BARRY E. DeWALT, City Attorney
150,000
1,627,600
1,777,600
nt phase one
of the City
?id meeting
,.Elvain