Loading...
HomeMy WebLinkAbout _ 4.11(b)--Project Acceptance BS 5162 Salt Creek Heights Neighborhood ParkT Y OF REDDIN CALIFORNIVCITY OF REDDING REPORT TO THE CITY COUNCIL MEETING DATE: August 15, 2023 FROM: Chuck Aukland, Public ITEM NO. 4.11(b) Works Director ***APPROVED BY*** ukland, Public Warks Direct 8/3/2423 ry ippin, Ci ana e : 8/7/2423 caukland&i.redding.ca.us btippin@cityofredding.org SUBJECT: 4.11(b) --Project Acceptance, Bid Schedule 5162, Job No. 9618, Salt Creek Heights Neighborhood Park Recommendation Accept Bid Schedule No. 5162 (Job No. 9618), Salt Creek Heights Neighborhood Park Project, awarded to Builder Solution, Inc., as satisfactorily complete, with a final cost of $1,772,809.36. Fiscal Impact Sierra Pacific Land and Development Company and two state grants from the Park Development Fund in the amount of $1,777,600 were approved for this project. The total project cost, including surveying, design, bidding, construction, field engineering, inspection, and contract administration, is $1,772,809.36. Alternative Action The City Council (Council) may choose to not accept the project as satisfactorily complete, and advise staff on how to proceed. Background As of February 10, 2023, Builder Solution Inc., completed all items of work on the Salt Creek Heights Neighborhood Park Project (Project). The contract awarded 210 working days to complete all elements of construction. Builder Solution Inc., completed project construction activities 22 working days beyond the contract completion date. Since the project was not completed within the contract time frame, liquidated damages were assessed. Pursuant to the contract, liquidated damages were defined as $1,000 per calendar day for a total assessment of liquidated damages in the amount of $22,000. Additionally, the City penalized Builder Solution Inc., for violating Public Contract Code 4104 & 4110 in the amount of $5,055.61 for hiring a non -listed subcontractor to perform bid item work that the prime contractor was listed to perform. The project warranty period expires one year from the completion date of February 10, 2023. Report to Redding City Council August 9, 2023 Re: 4.11(b) --Project Acceptance BS 5162 Salt Creek Heights Neighborhood Park Page 2 At its meeting of October 6, 2020, the Council awarded a construction contract to Builder Solution Inc., of Redding, California, for $1,304,806.82, an additional $17,250 for an Additive Bid Alternate and approved a $170,000 construction contingency fund. Also authorized was $292,930 for contract administration and construction inspection fees and $178,410 for project development costs. The City Manager was authorized to approve additional increases in either the construction management or construction contingency amounts up to a total of $15,000, for a total authorized amount of $1,978,396.82. Project development costs include engineering, environmental, and consultant services. During construction, there were 23 change orders in the amount of $138,401.90, leaving a balance of $31,598.10 in the contingency fund. The final project cost was $1,772,809.36 as summarized in the table below: The project involved the construction of new park facilities; including underground utility systems, electrical distribution, concrete paving and hardscape, irrigated landscape systems, picnic and BBQ areas, fencing, a soccer field, playground equipment and other miscellaneous work. Environmental Review Project acceptance is not a project as defined under the California Environmental Quality Act (CEQA). On June 1.5, 2010, Council adopted resolution 2010-056 certifying the CEQA Environmental Impact Report EIR-1-08, approving Tentative Map Application 5-15-07, and approving the Planned Development Plan Application PD -11-07. No further action is required. Council Priority/City Manager Goals This agenda item is a routine operational item. Attachments ^Site map Previous Staff Report 1.0/06/20 Cost Summary Awarded Amounts Actual Cost Project Development Costs $178,410 $178,410 Construction Contract $1,492,056.82 Contingency Construction Contract + $1,443,208.72 Contract Change Orders Penalty Assessments -$27,055.61 Contract Administration & $292,930 $178,246.25 Inspection Additional City Manager $15,000 0 Authority Total $1,978,396.82 $1,772,809.36 The project involved the construction of new park facilities; including underground utility systems, electrical distribution, concrete paving and hardscape, irrigated landscape systems, picnic and BBQ areas, fencing, a soccer field, playground equipment and other miscellaneous work. Environmental Review Project acceptance is not a project as defined under the California Environmental Quality Act (CEQA). On June 1.5, 2010, Council adopted resolution 2010-056 certifying the CEQA Environmental Impact Report EIR-1-08, approving Tentative Map Application 5-15-07, and approving the Planned Development Plan Application PD -11-07. No further action is required. Council Priority/City Manager Goals This agenda item is a routine operational item. Attachments ^Site map Previous Staff Report 1.0/06/20 CITY OF REDDING EXHIBIT A SALT CREEK HEIGHTS PUBLIC WORKS NEIBORHOOD PARK DEPARTMENT LOCATION MAP ��FoA CITY OF REDDING REPORT TO THE CITY COUNCIL MEETING DATE: October 6, 2020 FROM: Chuck Aukland, Public ITEM NO. 4.110 Works Director ***APPROVED BY*** Construction Contract + Contingency 4 A 60and, Pu blt t "s Direct /25T?—o20 iplain, Ca an° c 912 `2[120 caukland@cixed, J btippin@cityofredding.org SUBJECT: 4A l(f)- Award BS 5162 (Job Order No. 9618) Salt Creek Heights Neighborhood irk Recommendation r Authorize the following actions hive to Bld{'shed Heights Neighborhood Park Pr (1) Award to Builder Solute Inc. in the aunt c additional $17,250 for tI I A I Mate; (2) Approve an additional ver tl and $178,410 for project development cad (3) Approve $170,000 to provide constru�It'tonti (4) Authorize the City Manager to diti management or construction coour (5) Authorize sole source purchase ""{Robinl Poles, Tree Climber, Spinner Bowl, Hi11 Cliu Fiscal Impact No. 5162 (Job No. 9618) Salt Creek 04,806.82 for the Base Bid, and an and inspection fees; ma ses ilax either the construction j. �r total 15,000; and astle olor Accents, Sitting 3), aalance Net by Kompan. The Salt Creek Heights Neighborhood Park d mainly by the Sierra Pacific Land and Development Company and two Staff its totaling $165,000 coming from the Park Development Fund. At its meeting on June 16, 2020, the City Council adopted a budget resolution appropriating $1,777,600. The remaining balance will come from Engineering Division Personnel funds for construction management services. Cost Summary Item Estimated Project Development Costs $178,410 Construction Contract + Contingency $1,492,056.82 Contract Administration, Inspection, Testing $292,930 Additional City Manager Authority $15,000 Total Project Costs $1,978,397 Report to Redding City Council October 1, 2020 Re: 4.11(f) --Award BS No. 5162 Salt Creek Heights Neighborhood Park Page 2 Project cost components are estimates and some shifting of the project development, construction management, and construction contingency funds may be necessary to balance the project within the approved budget. Alternative Action The City Council (Council) may choose not to award the bid for the Salt Creek Heights Neighborhood Park Project and provide staff with alternate direction. As stated in the June 16, 2020, staff report, without this project, the City of Redding (City) will be in conflict with agreements already executed with the developers. Background/Analysis Attached is a tabulat�;rft�ived and opened on September 22, 2020, for the Salt Creek Heights Neighbohark Prole' the low bid in the amount of $1,304,806.82 was received from Builder 51n Inc. of The engineer's estimate was $1,558,000. Total project develnt costs for this pr ct are estimated to be $178,410. Project development costs includesgineering, surveying right-of-way, environmental, consultant services and permit and utt,l connection fees. is $1,777,600 budgeted for this project. The remaining project costs, to $249,000, will be funded utilizing Engineering Division Personnel funds which are anti]able as a result of a higher than budgeted overhead rate approved � S 3 by Caltrans. This project includes the constr0, on of park system, domestic water systems electrical, pa-\ picnic and BBQ areas, fencing, cer goals, a}i Sole sourcing the playground equip j rte playground is constructed as designed. The pla for this location. The playground is the signat chosen due to the unique design and the,""",n locust which is especially robust. Koh` is playground in the United States. Council Priority/City Manager Goals ities; including, storm drain, sanitary sewer end hardscape, irrigation system, landscape, us 0 This agenda item is a routine operational item. Attachments Bid Tabulation Location Map Notice of Determination Resolution from June 16, 2020 (available online) Pictures (available online) of the ie look and experience of the has been selected specifically c. Kompan's Robina line was ide of black this type of BID TABULATION FOR: SALT CREEK HIEGHTS NEIGHBORHOOD PARK Bid Schedule No.: 5162 ITEM Job No.: 9618 9/22/2020 IDESCRIPTION UNIT QTY ENGINEER'S EST UNIT PRICE TOTAL Builder Solution UNIT PRICE Inc. TOTAL S.T. Rhoades Construction UNIT PRICE TOTAL Site Preparation & Earthwork 1 Mobilization LS 1 $5,000.00 $5,000.00 $78,000.00 $78,000.00 $263,000.00 $263,000.00 2 Clearing & Demolition LS 1 $15,000.00 $15,000.00 $11,102.00 $11,102.00 $9,000.00 $9,000.00 3 Temporary Construciton Fencing LS 1 $5,300.00 $5,300.00 $13,156.00 $13,156.00 $14,000.00 $14,000.00 4 Site Layout and Stakingt $13,200.00 $13,200.00 $33,280.00 $33,280.00 $20,000.00 $20,000.00 5 Earthwork &Rough Grading , °" ' 1 x$79,200.00 $79,200.00 $54,210.00 $54,210.00 $150,000.00 $150,000.00 6 Project Funding Sign63 2,500.00 $2,500.00 $2,444.00 $2,444.00 $1,500.00 $1,500.00 7 SWPPP (Prepare)' LS 1 , 000.00 $2,000.00 $2,704.00 $2,704.00 $3,000.00 $3,000.00 8 SWPPP (Implement) 'v` LS 1 ,,1,200.00 $11,200.00 $4,238.00 $4,238.00 $42,000.00 $42,000.00 9 Rain Event Action Action Plans (REAPS) , ' EA ,7 A 50 $100.00 $5,000.00 $139.88 $6,994.00 $90.00 $4,500.00 Storm Drain Systems 10 11 Perforated Pipe (6") PVC Drain Line (6") ,r "F x,10 } �'„ $34.00 «� $17,340.00 $9,690.00 $16.90 $50.91 $8,619.00 488 $45.00 $60.00 $22,950.00 $17,100.00 12 PVC Drain Line (8") 80 ,., ,,,,,.> $35 <,��; $9,800.00 $55.99 13 JPVC Drain Line (10") LF 12Q„ " $45 Ot .,:,, $5,400.00 $65.87°°' ''g4w4' $59.00 $7,080.00 14 PVC Drain Line (12") LF 11 $55 00 ,v, $6,325.00 $67.03 ,7,70:;3.45 $60.00 $6,900.00 15 Catch Basin (Area Drainings) EA 1 $1,800 ( $28,800.00 $1,283.75 $20,540.00 $1,500.00 $24,000.00 16 Play Area Catch Basin EA 3 $2,300,,, ,00.00 $1,958.67 b76fI $1,850.00 $5,550.00 17 Sanitary Sewer System` Sanitary Sewer Drain Line (4") LF 300 4 ; $45.0, $13,500(1,a $25.48 $7,644.00 $60.00 $18,000.00 18 Sanitary Sewer Cleanouts EA 7 $600a° $4,200.1 r' $1,935.14 ..;$8;b45:g $1,000.00 $7,000.00 AV Domestic Water System '- 19 Backflow Preventer (1.5") EA 1 „ x,20 004 '00 1$",107.73 2M7.73 $3,000.00 $3,000.00 20 lWater Line (2") LF 265 $25.00e, ` 25.00 $15.65 .......•.$4,147.5 ' $75.00 $19,875.00 Site Electrical System 21 Electric Service Pedestal & Distribution LS 1 $18,500.00 $18,500 0 �,4g:� $17,940.00 $26,900.00 $26,900.00 22 Electrical Conduit/Trenching &Future Stubouts LS 1 $22,000.00 $18,975.00 $18,975.00 $30,000.00 $30,000.00 l tl3 Site Paving and Hardscape 23 Concrete Paving SF 10419 $12.00 $125,028.00 $6.90 $71,891.10 $12.00 $125,028.00 24 Concrete Play Area Containment Curb LF 359 $40.00 $14,360.00 $55.33 M6r47 $45.00 $16,155.00 25 PI y Area Turndown LF 67 $25.00 $1,675.00 $62.40 $4,180.80 $150.00 $10,050.00 26 Concrete Planter Curb LF 138 $25.00 $3,450.00 $58.50 $8,073.00 $115.00 $15,870.00 27 Concrete Mowband (9") LF 215 $15.00 $3,225.00 $66.30 $14,254.50 $55.00 $11,825.00 28 1 Redwood Header I LF 386 $5.00 $1,930.00 $46.88 1,t8 $10.00 $3,860.00 BID TABULATION FOR: SALT CREEK HIEGHTS NEIGHBORHOOD PARK Bid Schedule No.: 5162 ITEM Job No.: 9618 9/22/2020 IDESCRIPTION UNIT QTY ENGINEER'S EST UNIT PRICE TOTAL Builder Solution UNIT PRICE Inc. TOTAL S.T. Rhoades Construction UNIT PRICE TOTAL 29 Play Area Access Ramp EA 1 $4,000.00 $4,000.00 $10,114.00 $10,114.00 $5,000.00 $5,000.00 30 Raised Concrete Seatwall LF 19 $175.00 $3,325.00 $552.50 $10,497.50 $550.00 $10,450.00 31 CMU Play Area Wall LF 71 $250.00 $17,750.00 $110.50 $7,845.50 $525.00 $37,275.00 32 Concrete Play Area Wall LF ___66 $300.00 $19,800.00 $110.50 $7,293.00 $400.00 $26,400.00 33 Segmented Terrace Retaining Wall Lt � � ,n $40.00 $1,720.00 $110.50 $4,751.50 $375.00 $16,125.00 34 Concrete Stairs and Cheek Wall y, $420.00 $420.00 $11,752.00 $11,752.00 $9,500.00 $9,500.00 35 Fiber Plary Area Surfacing „ w.� 5492 $4.00$21,968.00 $3.73 $0,4.6 ' $3.50 $19,222.00 36 Resilient Play Area Surfacing' SF 2098 $25.00 $52,450.00 $7.77 `.�1.4.. $30.00 $62,940.00 37 Decomposed Granite Paving CY 2 „$250.00 $500.00 $2,268.50 $4,537.00 $600.00 $1,200.00 Site Furnishing 38 Group Picnic Structure LS1 $72,#500.00 $72,500.00 $85,150.00 $85,150.00 $125,000.00 $125,000.00 39 Restroom Building Pad Preparation L ,00 $18,000.00 $13,000.00 $13,000.00 $4,500.00 $4,500.00 40 BBQ at Group Pinic Area i ''1 r=4,53'�.,r $4,533.00 $4,732.00 $4,732.00 $1,450.00 $1,450.00 41 Serving Table EA 1 , „ , $1,480 50 $1,480.50 $4,472.00 $4,472.00 $1,450.00 $1,450.00 42 43 Pinic Tables Round Plaza Tables EA EA 8 2 $1,450.5 0, .t $2,208 („ „�� $11,604.00 $4,416.00 $1,729.00 $2,756.00 $13,832.00 $5,512.00 $1,450.00 $1,450.00 $11,600.00 $2,900.00 44 Round Plaza Tables (ADA) EA 1 $2,24,f,,,, 45.50 $4,732.00 $4,732.00 $1,500.00 $1,500.00 45 Trash Receptacles EA 2 � f3 �3�Q0 $2,496.00 $4,992.00 $1,150.00 $2,300.00 46 47 Chain Link Fence (4") Soccer Goals LF LS 830 2 WMINW.00 ,� r , 4°;0 $1,500 O(t$3,000 '� $56.20X46,646.00 $10,088.00 $20,176.00 $42.00 $550.00 $34,860.00 $1,100.00 48 49 Ornamental Fencing and Concrete at CMUi Wall LF Park Sign EA 137$.1 1, Olt.. .., $13,70( $7,1" 156.76 $21,476.12 $8,788.00 $95.00 $10,500.00 $13,015.00 $10,500.00 50 Bike Racks EA 3 �,; 00.001 „ ,„y ,�'�.'00 A0,279.33 $03`7-99,"' $950.00 $2,850.00 51 Play Equipment & Swings (2-5 yr. & 5-12 yr.) LS 1 N $310,000.00 $310,000.00 6,780.8 , ,« $136,780.80 $340,000.00 $340,000.00 Irrigation System 52 53 1 Irrigation System (Complete) SF Meter & Backflow Preventer with Enclosure (3") EA 152140 1 $1.75 $5,000.00 66,245 , „` �����°��``$0.36 , x $8;x.00 $1,950.00 $54,770.40 $1,950.00 $1.11 $13.50 $168,875.40 $13.50 54 Irrigation Controller LS 1 $25,000.00 $25,000.00 $2,015.00 $2,015.00 $3,000.00 $3,000.00 55 Booster Pump LS 1 $35,000.00 $35,000.00 $2,145.00 $2,145.00 $49,000.00 $49,000.00 Landscaping 56 Finish Grade & Soil Amendments SF 152140 $0.45 $68,463.00 $0.39 $59,334.60 $0.29 $44,120.60 57 Shrubs/Groundcovers SF 1966 $4.50 $8,847.00 $49.99 ,$- 8 80:34: $1.65 $3,243.90 58 Box Trees (24") EA 7 $400.00 $2,800.00 $1,723.43 `'4,0.14 $385.00 $2,695.00 BID TABULATION FOR: SALT CREEK HIEGHTS NEIGHBORHOOD PARK Bid Schedule No.: 5162 ITEM Job No.: 9618 9/22/2020 IDESCRIPTION UNIT QTY ENGINEER'S EST UNIT PRICE TOTAL Builder Solution UNIT PRICE Inc. TOTAL S.T. Rhoades Construction UNIT PRICE TOTAL 59 Trees (15 Gallon) EA 104 $125.00 $13,000.00 $531.00 $55,224.00 $140.00 $14,560.00 60 Tree Root Barrier Panels LF 170 $15.00 $2,550.00 $66.19 1,23 $7.00 $1,190.00 61 Bark Mulch CY 43 $65.00 $2,795.00 $240.50 $10,341.50 $112.00 $4,816.00 62 Hydroseed Turf SF 1,50172 $0.15 $22,525.80 $0.26 9 $0.09 $13,515.48 TOTAL BASE BID ;:.; a,, .r $1,506,659.80i1,O,C16t21i,3jt?68 Additive Alternate 63 Landscape Maintenance LS 1 X0,000 00 $40,000.00 $17,250.00 $17,250.00 $100,000.00 $100,000.00 TOTAL BASE BID PLUS ADDITIVE ALTERA The lowest bid shall be the lowest total of the bid prices on the base cttct and the additive alternate that were specifically identified in the bid solicitatio,y Shaded areas indicate corrections made in accordance with the Sr)dtM Prc BID TABULATION FOR: SALT CREEK HIEGHTS NEIGHBORHOOD PARK Bid Schedule No.: 5162 ITEM Job No.: 9618 9/22/2020 IDESCRIPTION UNIT QTY Randy Hill Construction UNIT PRICE TOTAL Gifford Construction Inc. UNIT PRICE TOTAL Trent Consntruction UNIT PRICE TOTAL Site Preparation & Earthwork 1 Mobilization LS 1 $36,479.39 $36,479.39 $411,713.00 $411,713.00 $76,316.15 $76,316.15 2 Clearing & Demolition LS 1 $59,124.65 $59,124.65 $2,500.00 $2,500.00 $3,592.59 $3,592.59 3 Temporary Construciton Fencing LS 1 $9,940.80 $9,940.80 $15,000.00 $15,000.00 $11,845.00 $11,845.00 4 Site Layout and Staking $15,604.75 $15,604.75 $13,500.00 $13,500.00 $15,990.75 $15,990.75 5 Earthwork & Rough Grading 9.21 $252,169.21 $172,000.00 $172,000.00 $229,200.75 $229,200.75 6 Project Funding Sign 1 157.52 $6,157.52 $1,200.00 $1,200.00 $1,445.09 $1,445.09 7 SWPPP (Prepare) LS 132.47 $2,132.47 $1,700.00 $1,700.00 $2,961.25 $2,961.25 8 SWPPP (implement) LS 1 11.07 $32,911.07 $61,664.00$61,664.00 $72,662.56 $72,662.56 9 Rain Event Action Action Plans EA 50 &1106.62 $5,331.00 $80.00 $4,000.00 $94.76 $4,738.00 Storm Drain Systems 10 11 Perforated Pipe (6") PVC Drain Line (6") "F o0 $1,22.20 $62,322.00 23,880.15 $74.00 $79.26 $37,740.00 $93.53 $64.02 $47,700.30 $18,245.70 12 PVC Drain Line (8") .... . .. . .. ... ... ), ..... ... .. 80 82 $23,195.20 $7 6.00 $21,280.00 $81.24 $22,747. 20 13 PVC Drain Line (10") LF 12 $186.34 $22,360.80 $79.00 $9,480.00 $70.35 $8,442.00 14 PVC Drain Line (12") LF 11$185.23 $21,301.45 $80.00 $9,200.00 $75.98 $8,737.70 15 Catch Basin (Area Drainings) EA 161j"', _ $2,135.00 $34,160.00 $1,844.27 $29,508.32 16 Play Area Catch Basin EA 3",'�-�',�',"%",,?",�?�,,", $2 $6 773 $2,400.00 $7,200.00 $2,009.70 $6,029.10 .Sanitary Sewer System 17 Sanitary Sewer Drain Line (4") LF 300 $77.32,, 3,196.00 $53.00 $15,900.00 $61.67 $18,501.00 18 Sanitary Sewer Cleanouts EA 7 $1,003, $7,021.77 $700.00 $4,900.00 $381.41 $2,669.87 K Domestic Water System 19 Backflow Preventer (1.5") EA 1 .62 gal J, 0.00 65.11 1 . . . ..... A_ $5,23 0.00 $3, 259.74 $3,259.74 20 Water Line (2") LF 2 5 "$89.03 . . . . . . . . . 45.77 $61.85 $16,390.25 Site Electrical System .......... 21 Electric Service Pedestal & Distribution LS 1 $20,269.09 $2 "ARE, 06.00 $27,768.23 $27,768.23 22 Electrical Conduit/Trenching & Future Stubouts LS 1 $50,973.06 23,601.00 $23,601.00 $27,778.89 $27,778.89 Site Paving and Hardscape 23 Concrete Paving SF 10419 $12.44 $129,612.36 $10.43 $13.00 $135,447.00 24 Concrete Play Area Containment Curb LF 359 $44.43 $15,950.37 $37.03 $89.08 $31,979.72 25 PI y Area Turndown LF 67 $46.80 $3,135.60 $38.00 $2,546.00 $94.29 $6,317.43 26 Concrete Planter Curb LF 138 $27.25 $3,760.50 $23.72 $70.18 $9,684.84 27 Concrete Mowband (9") LF 215 $27.25 $5,858.75 $22.60 $4,859.00 $43.32 $9,313.80 28 Redwood Header LF 386 $8.89 $3,431.54 $12.79 ',$,*11i9 $13.58 $5,241.88 BID TABULATION FOR: SALT CREEK HIEGHTS NEIGHBORHOOD PARK Bid Schedule No.: 5162 ITEM Job No.: 9618 9/22/2020 IDESCRIPTION UNIT QTY Randy Hill Construction UNIT PRICE TOTAL Gifford Construction Inc. UNIT PRICE TOTAL Trent Consntruction UNIT PRICE TOTAL 29 Play Area Access Ramp EA 1 $1,007.00 $1,007.00 $850.00 $850.00 $1,263.86 $1,263.86 30 Raised Concrete Seatwall LF 19 $254.71 $4,839.49 $215.00 $4,085.00 $797.23 $15,147.37 31 CMU Play Area Wall LF 71 $404.05 $28,687.55 $381.96 2W,,45.1,6: $435.76 $30,938.96 32 Concrete Play Area Wall LF 66 $390.95 $25,802.70 $317.06 2i}z $511.85 $33,782.10 33 34 Segmented Terrace Retaining Wall Concrete Stairs and Cheek Wall . , , ,., 408 N", ,r.'"` " X6,219.69 $13,505.44 $6,219.69 $475.58 $2,250.00 Sr,4494� $2,250.00 $4,619.55 $6,704.13 $4,619.55 35 Fiber Plary Area Surfacing„ w.� 5492„,� $2.22 $12,192.24 $3.221 17,6 $3.40 $18,672.80 36 Resilient Play Area Surfacing` SF 2098 $34.90 $73,220.20 $28.91 f} If ; $31.15 $65,352.70 37 Decomposed Granite Paving „�' CY 2 X10.82 $1,421.64 $975.00 $1,950.00 $387.04 $774.08 Site Furnishing 38 Group Picnic Structure LS 1 $118,0,34.39 $118,034.39 $96,980.00 $96,980.00 $111,613.07 $111,613.07 39 Restroom Building Pad Preparation „��� $20,963.33 $10,000.00 $10,000.00 $4,382.65 $4,382.65 40 BBQ at Group Pinic Area i��'. ' 1,;157 95,;, $1,157,99 $1,216.00 $1,216.00 $1,042.36 $1,042.36 41 Serving Table EA 1 v,,,,.' $1,039.52 $1,039.52 $1,231,00 $1,231,00 $1,066.05 $1,066,05 42 43 Pinic Tables Round Plaza Tables EA EA 8 2 $968.86 $578.9 `'r , `r $7,750,88 ,vt .� $1,15,7.98 $1,071.00 $1,701.00 $8,568.00 $3,402.00 $1,012.75 $1,748.32 $8,102.00 $3,496.64 44 Round Plaza Tables (ADA) EA 1 ,; $1,993 f.r�' $1,?W0 $1,726.00 $1,726.00 $1,788.60 $1,788.60 45 Trash Receptacles EA 2 $680.50 $1,361.00 $627.79 $1,255.58 46 Chain Link Fence (4") LF 830 6fi0.i $42.00 $34,860.00 $49.75 $41,292.50 47 Soccer Goals LS 2 $3,885 61 ,, 7,771.22 $5,779.50 $11,559.00 $5,831.29 $11,662.58 48 Ornamental Fencing and Concrete at CMU Wall LF 137 $11��, $99.60 iLCI. $113.26 $15,516.62 49 50 Park Sign Bike Racks EA EA 1$ 3 1'„ .43 "In,$9,554 �.- $&,��.00 s ,9.5 `'� X0.00 $8,251.00 $1,200.00 $5,330.25 $604.10 $5,330.25 $1,812.30 51 Play Equipment & Swings (2-5 yr. & 5-12 yr.) LS 1 $282,536.76 $282,536.76 827.00 ;289,827.00 $341,491.35 $341,491.35 Irrigation System 52 Irrigation System (Complete) SF 152140 $1.32 $20Q 24.80 .k„A �.,,���`$1.10 $167,354.00 $1.31 $199,303.40 53 Meter & Backflow Preventer with Enclosure (3") EA 1 $15,993.50 $15;55 $12,350.00 $12,350.00 $15,990.75 $15,990.75 54 Irrigation Controller LS 1 $3,554.11 $3,554.11 $4,500.00 $4,500.00 $3,553.50 $3,553.50 55 Booster Pump LS 1 $58,050.48 $58,050.48 $50,500.00 $50,500.00 $58,040.50 $58,040.50 Landscaping 56 Finish Grade & Soil Amendments SF 152140 $0.34 $51,727.60 $0.43 $65,420.20 $1.08 $164,311.20 57 Shrubs/Groundcovers SF 1966 $1.95 $3,833.70 $23.00 $45,218.00 $1.95 $3,833.70 58 Box Trees (24") EA 7 $458.11 i6 $585.00 $4,095.00 $456.88 $3,198.16 BID TABULATION FOR: SALT CREEK HIEGHTS NEIGHBORHOOD PARK Bid Schedule No.: 5162 ITEM Job No.: 9618 9/22/2020 IDESCRIPTION UNIT QTY Randy Hill Construction UNIT PRICE TOTAL Gifford Construction Inc. UNIT PRICE TOTAL Trent Consntruction UNIT PRICE TOTAL 59 Trees (15 Gallon) EA 104 $165.86 $17,249.44 $180.00 $18,720.00 $165.83 $17,246.32 60 Tree Root Barrier Panels LF 170 $8.29 $1,409.30 $40.00 $6,800.00 $13.94 $2,369.80 61 Bark Mulch CY 43 $132.69 $5,705.67 $105.00 $4,515.00 $132.66 $5,704.38 62 Hydroseed Turf SF 1,50172 $0.1168 $0.15 ;SS $0.11 $16,518,92 TOTAL BASE BID ;,� „ at, .. 1,x,968,1 ° $2,102,433.07 $2,071,693.84 Additive Alternate 63 Landscape Maintenance �`� Alff. LS 1 O' 00.00 $134,200.00 $85,200.00 $72,000.00 $72,00000 TOTAL BASE BID PLUS ADDITIVE ALTERA The lowest bid shall be the lowest total of the bid prices on the base additive alternate that were specifically identified in the bid solicitatic Shaded areas indicate corrections made in accordance with the S 168.91 $2,187,633.07 $2,143,693.84 BID TABULATION FOR: SALT CREEK HIEGHTS NEIGHBORHOOD PARK Bid Schedule No.: 5162 ITEM Job No.: 9618 9/22/2020 IDESCRIPTION UNIT Site Work Solutions UNIT QTY PRICE TOTAL SEL Group UNIT PRICE UNIT TOTAL PRICE TOTAL Site Preparation & Earthwork 1 Mobilization LS 1 $27,474.67 $27,474.67 $12,779.00 $12,779.00 2 Clearing & Demolition LS 1 $12,989.25 $12,989.25 $45,462.00 $45,462.00 3 Temporary Construciton Fencing LS 1 $15,124.47 $15,124.47 $16,266.00 $16,266.00 4 Site Layout and Staking $18,419.43 $18,419.43 $31,050.00 $31,050.00 5 jEarthwork & Rough Grading �,"`112,560.13 $112,560.13 $212,668.00 $212,668.00 6 Project Funding Sign �A 1 X1,244.56 $1,244.56 $4,513.00 $4,513.00 7 SWPPP (Prepare)' LS 1,111.39 $3,111.39 $1,725.00 $1,725.00 8 SWPPP (Implement) Am ' LS 1 ,327.75 $69,327.75 $22,420.00 $22,420.00 9 Rain Event Action Action Plans (REAPS) «' EA 50 ,,$119.39 $5,969.50 $70.00 $3,500.00 Storm Drain Systems 10 11 Perforated Pipe (6") PVC Drain Line (6") bF x,10 $64.31 $32,798.10 $9,940.80 $48.50 $41.00 $24,735.00 $11,685.00 12 PVC Drain Line (8") 80 ,., „ ,,,.'> $3 �,' 3=,, $9,805.60 $41.00 $11,480.00 13 PVC Drain Line (10") LF 12Q $82 81 $9,937.20 $60.00 $7,200.00 14 PVC Drain Line (12") LF 11's',> $83 89 $9,647.35 $49.00 $5,635.00 15 Catch Basin (Area Drainings) EA 1 $4,536.0 ,, $72,576.96 $2,650.00 $42,400.00 16 Play Area Catch Basin EA 3 $1,816«, a I, $3,051.00 $9,153.00 Sanitary Sewer System 17 18 Sanitary Sewer Drain Line (4") Sanitary Sewer Cleanouts LF EA 300 7 $45.7q,,, 13,734.00 $9791„��$6,853,77 $45.00 �, $1,179.00 $13,500.00 $8,253,00 Domestic Water Systems , 19 Backflow Preventer (1.5") EA 1 4.95 t,�`"7.00 $9,327.00 20 Water Line (2") LF 265 '$37.96 � �� `.40 4`x$21.50 $5,697.50 Site Electrical System � , 21 Electric Service Pedestal & Distribution LS 1 $28,583.20 $28,583.20 .;,4,5', ` $34,087.00 22 Electrical Conduit/Trenching & Future Stubouts LS 1 $38,764.19 $�'23,Zia 1.00 $23,961.00 t .rriv Site Paving and Hardscape 23 Concrete Paving SF 10419 $12.20 $127,111.80 $16.00 $166,704.00 24 Concrete Play Area Containment Curb LF 359 $53.26 $19,120.34 $120.50 $43,259.50 25 Play Area Turndown LF 67 $53.81 $3,605.27 $3,576.50 $239,625.50 26 Concrete Planter Curb LF 138 $55.29 $7,630.02 $202.00 $27,876.00 27 Concrete Mowband (9") LF 215 $41.04 $8,823.60 $197.00 $42,355.00 28 Redwood Header LF 386 $9.36 77:5� $24.00 $9,264.00 BID TABULATION FOR: SALT CREEK HIEGHTS NEIGHBORHOOD PARK Bid Schedule No.: 5162 ITEM Job No.: 9618 9/22/2020 IDESCRIPTION UNIT QTY Site Work Solutions SEL Group UNIT UNIT PRICE TOTAL PRICE UNIT TOTAL PRICE TOTAL 29 Play Area Access Ramp EA 1 $2,898.89 $2,898.89 $5,319.00 $5,319.00 30 Raised Concrete Seatwall LF 19 $982.30 $18,663.70 $1,118.00 $21,242.00 31 CMU Play Area Wall LF 71 $718.07 $50,982.97 $497.00 $35,287.00 32 Concrete Play Area Wall LF ___66 $765.72 $50,537.52 $953.00 $62,898.00 33 Segmented Terrace Retaining Wall Lt � $713.25 $30,669.75 $493.00 $21,199.00 34 Concrete Stairs and Cheek Wall t„12,777.33 $12,777.33 $14,585.00 $14,585.00 35 Fiber Plary Area Surfacing 414 `!= 5492 $4.61 $25,318.12 $5.40 $29,656.80 36 Resilient Play Area Surfacing SF 2098 $27.62 $57,946.76 $21.00 $44,058.00 37 Decomposed Granite Paving CY 2 X746.74 $1,493.48 $1,540.00 $3,080.00 4 Site Furnishing 38 Group Picnic Structure LS j $182,489.73 $182,489.73 $21,519.00 $21,519.00 39 Restroom Building Pad Preparation „ ,x t $7,479.87 $18,600.00 $18,600.00 40 BBQ at Group Pinic Area i ' 1 M,`362 ft $1,362.52 $1,630.00 $1,630.00 41 IServing Table EA 1 $1,293.5(Dq $1,293.50 $1,606.00 $1,606,00 42 43 Pinic Tables Round Plaza Tables EA. EA 2 , 98,, $2,066.0 f ,.nj 84 ? $9,887,84 $4,132.04 $1,155.00 $1,590.00 $9,240,00 $3,180.00 44 Round Plaza Tables (ADA) EA 1 ,; $2,107,h, � $ 9.11 $1,645.00 $1,645.00 45 Trash Receptacles EA 2 am j $2,048.00 $4,096.00 46 Chain Link Fence (4") LF 83040:040,0. ..,.;;. $49.00 $40,670.00 47 Soccer Goals LS 2 $6,857.4 0 " 714 84 $6,035.00 $12,070.00 48 Ornamental Fencing and Concrete at CMU Wall LF 137 $21�, ;j $29,718.04,,,,,,,',''$x,11.00 $15,207.00 49 Park Sign EA 1 $1 t 08„ i, $11,06Q V $t,,r0.00 $8,110.00 50 Bike Racks EA 3, , ���07.24 ;a s Q`` x$3.00 $5,349.00 51 Play Equipment & Swings (2-5 yr. & 5-12 yr.) LS 1 $347,933.65 $347,933.65,000.00 „x$253,000.00 Irrigation System 52 Irrigation System (Complete) SF 152140 $1.49 $22,6 �.��$1.30 $197,782.00 53 Meter & Backflow Preventer with Enclosure (3") EA 1 $16,801.51 $1,0.1 $11,440.00 $11,440.00 54 Irrigation Controller LS 1 $3,733.67 $3,733.67 $5,227.00 $5,227.00 55 Booster Pump LS 1 $60,983.25 $60,983.25 $52,262.00 $52,262.00 Landscaping 56 Finish Grade & Soil Amendments SF 152140 $0.57 . i 6 19.9 $5.00 $7 f7,700�00 57 Shrubs/Groundcovers SF 1966 $2.49 $4,895.34 $33.00 $64,878.00 58 1 Box Trees (24") EA 7 $479.15 1 $3,354.05 $680.00 $4,760.00 BID TABULATION FOR: SALT CREEK HIEGHTS NEIGHBORHOOD PARK Bid Schedule No.: 5162 Job No.: 9618 9/22/2020 ITEM IDESCRIPTION UNIT QTY Site Work Solutions UNIT PRICE TOTAL SEL Group UNIT PRICE UNIT TOTAL PRICE TOTAL 59 Trees (15 Gallon) EA 104 $174.24 $18,120.96 $210.00 $21,840.00 60 Tree Root Barrier Panels LF 170 $18.67 $3,173.90 $47.00 $7,990.00 61 Bark Mulch CY 43 $139.39 $5,993.77 $122.00 $5,246.00 62 Hydroseed Turf SF 1„50172 $0.14 $21,024.08 $0.20 $30,034.40 TOTAL BASE BID 2t10,1,8,r22,8#3Ia93i.70' Additive Alternate 63 Landscape Maintenance; .`� LS 1 $x,835.85 $151,835.85 $83,600.00 $83,600,00 TOTAL BASE BID PLUS ADDITIVE ALTERt� The lowest bid shall be the lowest total of the bid prices on the base additive alternate that were specifically identified in the bid solicitatic Shaded areas indicate corrections made in accordance with the SDE BID TABULATION FOR: SALT CREEK HIEGHTS NEIGHBORHOOD PARK Bid Schedule No.: 5162 Job No.: 9618 9/22/2020 ITEM IDESCRIPTION UNIT QTY Site Preparation & Earthwork 1 Mobilization LS 1 2 Clearing & Demolition LS 1 3 Temporary Construciton Fencing LS 1 4 Site Layout and Staking r t ,, 5 Earthwork & Rough Grading., �`' 1� 6 Project Funding Sign 1 7 SWPPP (Prepare)'' LS 1 8 SWPPP (Implement) LS 1 9 Rain Event Action Action Plans (REAPS)E',° EA 1 50 Storm Drain Systems 10 Perforated Pipe (6")LF , x,10 11 PVC Drain Line (6") 12 PVC Drain Line (8") 80 13 PVC Drain Line (10") LF 12Q 14 PVC Drain Line (12") LF 11,w,, 15 Catch Basin (Area Drainings) EA 16 Play Area Catch Basin EA 3 Sanitary Sewer System 17 Sanitary Sewer Drain Line (4") LF 300 18 Sanitary Sewer Cleanouts EA 7 Domestic Water System 19 Backflow Preventer (1.5") EA 1 20 Water Line (2") LF 265 Site Electrical System 21 Electric Service Pedestal & Distribution LS 1 22 Electrical Conduit/Trenching & Future Stubouts LS 1 Site Paving and Hardscape 23 Concrete Paving SF 10419 24 Concrete Play Area Containment Curb LF 359 25 Play Area Turndown LF 67 26 Concrete Planter Curb LF 138 27 Concrete Mowband (9") LF 215 28 Redwood Header LF 386 UNIT PRICE I TOTAL BID TABULATION FOR: SALT CREEK HIEGHTS NEIGHBORHOOD PARK Bid Schedule No.: 5162 Job No.: 9618 9/22/2020 ITEM IDESCRIPTION UNIT UNIT QTY PRICE 29 Play Area Access Ramp EA 1 30 Raised Concrete Seatwall LF 19 31 CMU Play Area Wall LF 71 32 Concrete Play Area Wall LF ,..66 33 Segmented Terrace Retaining Wall'. EA 34 Concrete Stairs and Cheek Wall Round Plaza Tables EA 35 Fiber Plary Area Surfacing Round Plaza Tables (ADA) 5492 36 Resilient Play Area Surfacing SF 2098 37 Decomposed Granite Pavinq� Cy 2 TOTAL Site Furnishing 38 Group Picnic Structure ,LS ,1 39 Restroom Building Pad Preparation L �, 40 BBQ at Group Pinic Area , �WWI 41 Serving Table EA 1 ,. 42 Pinic Tables EA 8,1 43 Round Plaza Tables EA 2 44 Round Plaza Tables (ADA) EA 1 45 46 Trash Receptacles Chain Link Fence (4") EA LF 2 830 47 Soccer Goals LS 2 48 Ornamental Fencing and Concrete at CMU Wall LF 137 49 Park Sign EA 1 50 Bike Racks EA 3 51 Plav Equipment & Swinas (2-5 vr. & 5-12 vr.) LS 1 TOTAL irrigation System 52 Irrigation System (Complete) SF 152140 53 Meter & Backflow Preventer with Enclosure (3") EA 1 54 Irrigation Controller LS 1 55 Booster Pump LS 1 Landscaping 56 Finish Grade & Soil Amendments SF 152140 57 Shrubs/Groundcovers SF 1966 58 Box Trees (24") EA 7 BID TABULATION FOR: SALT CREEK HIEGHTS NEIGHBORHOOD PARK ITEM Bid Schedule No.: 5162 Job No.: 9618 9/22/2020 IDESCRIPTION UNIT UNIT QTY PRICE TOTAL 59 Trees (15 Gallon) EA 104 60 Tree Root Barrier Panels LF 170 61 Bark Mulch CY 43 62 Hydroseed Turf SF 1„50172 TOTAL BASE BID Additive Alternate � � I My 63 ILandscape MaintenanceLS 1 1 T �1 d TOTAL BASE BID PLUS ADDITIVE ALTS The lowest bid shall be the lowest total of the bid prices on the base additive alternate that were specifically identified in the bid solicitatic Shaded areas indicate corrections made in accordance with the S r /L A h � ft VEN3URPECVO Q t BUENA W uj Z � Z MO COVE OR s W Y O t � l J UJ M WLLJ Q U 0RE00N 1R�Y V J z to p�0 .'N838V i s s uj . M31A Vl5VH5 z f^, t fy y� y W m m 8010IA 08 N3360 NBnH3 " / 7 a ' W r a aJ " o N83 N8nHo y�.oE ^ a e J 6_ 4 1 I113H038 / pa �-� Q ON Y G d�� 58273 ✓p c w _ {/YJ L N Y ® W do m JFe= U W � t Ff = tll t} H Z ,t V O CUYAHOGA PKWY ♦ F— pQ % u (L 0y P �, 6nx CITY G.REDDING DEVELOPMENT SERVICES DEPARTMENT PLANNING DIVISION 777 Cypress Avenue, Redding, CA 96001-271 P.O. Box 496071, Redding, CA 96049-6071 530.225.4020 FAX 530.225.4495 SHASTA COUKrY CLERK NOTICE OF DETERMINATION To: 0 Office of Planning and Research FROM: City of Reddin P.O. Box 3044, 1400 Tenth Street, Room 212 Development Ttervices Department Sacramento, CA 95814 777 Cypress Avenue Redding, CA 96001 IR County Clet, Filing of i of Determination in U= (If submitted to Clearinghouse) ect Subject: with Section 21108 or 21152 of the Public Resources Code 530-225-4020 Person Area Code/Telephone/Extension VAI g A Project Description: 440 residential nedwith ix of housing types, including single- family, multiple -family, cluster homes with garden C1 ts, andGusto( sites; 127 acres of natural open 'j" space; and a 13,9 -acre neighborhood park with a Firs. The project'o includes construction of an internal circulation network, on- and off-site utility exdrape rmplrements necessary to serve the lots; an extension of Buenaventura Bottle oposed Project; and two new street connections to SR 299 at buildout. This is to advise that the City of Redding has approved the above-described ne 15, 2 and has made the following determinations regarding the above -describe - ........... 1. The project 0 will N will not have a significant effect on the 2. ®An Environmental Impact Report was prepared for"'b" kht to provisions of CEQA. ..... . . .. .......... 0 A Negative Declaration was prepared for this project pursuant to the provisions of CEQA. 3. Mitigation measures N were 0 were not made a condition of the approval of the project. 4. A Mitigation Report or Monitoring Plan IR was 0 was not made a condition of the approval of the project. 5. A statement of Overriding Considerations 0 was X was not adopted for this project. 6. Findings IR were 0 were not made pursuant to the provisions of CEQA. This is to certify that the final EIR with comments and responses and record of project approval, or the Negative Declaration, is available to the general public at Redding City Hall, 777 Cypress Avenue, Redding, California. Date Mailed: tic Date Received 0as Dea for filing: Development Se es Department Envirdoc I O\NOD-S 1507-SaItCreek,wpd RESOLUTION NO. 2020-071 A RESOLUTION OF THE CITY OF REDDING APPROVING AND ADOPTING THE 41ST AMENDMENT TO CITY BUDGET RESOLUTION NO. 2019-050 APPROPRIATING 51,777,600 FOR THE SALT CREEK HEIGHTS PARK DEVELOPMENT PHASE ONE FOR FISCAL YEAR 2019-20 BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OFREDDING THAT Budget Resolution No. 2019-050 be and is hereby amended as follows: FUND DIVISION DESCRIPTION INCREASE DECREASE 128 619 Salt Creek Heights $1,627,600 128 618 Creek Heights $150,000 THAT acconumbers re ing adjustments by this Resolution are as follows: USE SOURCE OF FUNDS OF FUNDS Decrease (Ince 128-618-1-0001 Increase Revenues 128-619-9-5400-01 Increase Expenditures 128-619-4747-03 128-618-4747-03 nning Balance THAT the purpose is to app for fiscal year 2019-20. I HEREBY CERTIFY that Council of the City of Reddii by the following vote: AYES: NOES: ABSENT: ABSTAIN: COUNCIL M COUNCIL MEMBERS: None COUNCIL MEMBERS: None COUNCIL MEMBERS: None AT 'ST: r PAMELA MIZE, Ci (Cl rk ADAM McELVAIN, Mayor FORM APPROVED: BARRY E. DeWALT, City Attorney 150,000 1,627,600 1,777,600 nt phase one of the City ?id meeting ,.Elvain