Loading...
HomeMy WebLinkAbout _ 4.11(b)--Project Acceptance BS 5186 Ball Field Lighting at Alta Mesa S City Kiwanis Tiger Field GI �" Y � F � � � ° � � � " � � CITY OF REDDING REPORT TO THE CITY COUNCIL MEETING DATE: July 18, 2023 FROM: Chuck Aukland,Public ITEM NO. 4.11(b} Works Director ***APPROVED BY*** � ��n � .�.._ s.N,.�� � � � ��� ukl�n�l,H'ciblic Wc�aks L'��reGt ' 7�'3/2423 ry ip}�in,Ci ana � 7/7(2423 caulcland@ci.redding.ca.us btippin@cityofredding.org SUBJECT: 4.11(b)--Project Acceptance, Bid Schedule 5186 Ball Field Lighting Upgrades at Alta Mesa Park, Softball Park, South Cit Park Kiwanis #l, and Ti er Field Recommendation Accept Bid Sched�ule No. 5186 (Job No. 4908), Ball Field Lighting Upgrades at Alta Mesa Park, Softball Park, South City Park Kiwanis No. 1, and Tiger Field, awarded to Builder Solutions, Inc., as satisfactorily complete, with a final cost of$865,691.03. Fiscal Impact The Ball Field Lighting Upgrades Project (Project) was funded by the Green House Gas funding and the approved economic stimulus program. The total project cost, including surveying, design, bidding, construction, field engineering, inspection, and contract administration, is $865,691.03. Alternative Action The City Council (Council) may choose to not accept the project as satisfactorily complete, and advise staff on how to proceed. Background On Apri120, 2021, the City Manager awarded and Council rati�ied the project contract to Builder Solutions, Inc. (BSI) of Redding, California in the amount of$463,168 and approved a $50,000 construction contingency fund. Also authorized was $125,000 for contract administration and construction inspections fees. After construction began, it was discovered that significant changes were required at Tiger Field to construct a functional lighting system which included upgrading REU equipment (see Internal Communication dated January 3, 2023). This resulted in approval of $340,000 of additional project funding, for a total authorized amount of $978,168. During construction, there were eight change orders with a total value of$287,523.03. The final project cost was $865,691.03. This project included installation of City-furnished lighting equipment to replace, add, and enhanee sport field lighting systems at the City's Alta Mesa Park, Softball Park, South City Park Report to Redding City Council July 12, 2023 Re: 4.11(b)--ProjectAcceptance BS 5186 Balt Field Lighting atAlta Mesa S City Kiwanis Tiger Field Page 2 Kiwanis No. 1, and Tiger Field. The work included removal and disposal of existing lighting systems, and installation of City-furnished light poles, precast concrete foundations, grounding, and pole top luminaire assemblies, as well as furnishing and installing cast-in-place concrete backfill for pole foundations, and wiring and raceway to lighting fixtures and electrical equipment. At Tiger Field, the work included retrofitting the existing lighting systems, existing poles, wiring, and raceways. As of January 1'7, 2023, Builder Solutions, Inc., has completed the project scope of work at Alta Mesa Park, Softball Park, South City Park Kiwanis No. 1, and Tiger Field, which was outside the contract time frame and resulted in liquidated damages being assessed. The contract was awarded with 110 working days to complete all elements of construction. BSI completed construction activities at Alta Mesa Park, Softball Park, and South City Park Kiwanis No. 1, 10 calendar days beyond the contract completion date. Per the contract, liquated damages were defined as $1,000 per calendar day for a total assessment of liquidated damages in the amount of $10,000. Due to the significant design changes required at Tiger Field, this portion of work was performed on a time and materials basis and work days were not included in the liquidated damages assessment. The project warranty period expires one year from the completion date of January 17, 2023. Cost Summary Awarded Amounts Actual Cost Construction Contract+ Contingency $853,168 "��� Construction Contract+ Contract Change Orders �� , $750,691.03 Contract Administration&Inspection $125,000 $125,000 Liquidated Damages � � �� ������e� ��� -$10,000 � ' �� Total $978,168 $865,691.03 Environmental Review This action is not a project as de�ned by the California Environmental Quality Act (CEQA), and no further action is required. On December 29, 2020, staff found the project to be categorically exempt from review under the CEQA Guidelines,per section 15301 (a& d) —Existing Facilities. Council Pr�iority/City Manager Goals This agenda item is a routine operational item. Attachments ^Location Map ^Informal CM Award ^Council Ratify Award ^Contingency Fund Increase Request oF REoo CITY OF REDDING EXHIBIT A � _,:; �-� _.Z � � � PUBLIC WORKS �.p���w°,��� DEPARTMENT Foa� LOCATION MAP � � i � ��1 � �� �� � INTERI`�1AL � � _ , �G11�IMtJI'�IICATIC)I�I DATE: March 24, 2021 CODE: BS 5186 TQ: Barry Tippin, Gity Manager FROM: Chuck Aukland, City Engineer SUBJECT: Recammendakion of Contract Rward Bid Schedule No. 5186 Ball Field Lighting Upgrades at Alta Mesa Park, Softball Park, South City Park Kiwanis#1, and Tiger Field The City Manager has been delegated the authority to award energy savings contracts re[ated ta the Green House Gas fiunding approved by the Gity Cauncil on May 5, 2020, as part af the Lt�cal Ecanomic Stimulus. Att�ched is a tabulatian af bids received and opened on March 23, 2021; for this prc�ject. The low bid in the amount r�f$463,168 was rec�ived fram Buiider Solutions, Inc., of Redding. The engineer's estimate was$431,510, . R�commendation It is recommended that the City Manager: 1, Award this project to Builder So[utions, Inc., in the amount 4f$463;168, 2. Approve an additional$50,000 to cover the cost of contract change orders; 3: Approve an additional $1�5,000 for construction management, far a tatal of$638,168; and 4. Find the praject is-Categorically Exempt from the Califarnia Environmental Qu�lity Act per Section 15301(a &tl}—Existing facilities CosY Summaty Item Estimated Canstruction Contract+ Gontingency $513,168.00 Cantract Administration, Inspection,Testing $�25,Op0.p0 Tatai Projecf Co�ts $g3g,��g.p(� Backgrountl This� project includes installatian of City furnished lightin� equipment to replace; add, and enhance spart field lighti,ng systems at the City's Alta Mesa Park, Softball Fark; Sauth City Park Kiwanis #1, and Tiger field. The work includes removal and disposal of existing lightfng systems,and installation of�ity#urnished light pales; ;precast concrete foundations, grounding, and pc�letop luminaiee assemblies, as weil as ' furnishing and installing cast-in-place concrete backfill far pole fioundations, and wiring and racewa� to lighting fixtures and electrical equipment, as shown in the Plans. At Tiger field, the work will include retrafitting'the existing lighting systems and existing poles, wiring, and raceways will be utilized. Attachments Bid Tab � Notice of Exempti ;���.s-'�Z 1 City ' eer Qate APP t)VED: �.�.._,..._,,,,.,_,� t .� .'����' � �.��.�-....�.,.�.�_ �.� �� � . ��' � �-- ,� Gity Man� Qate fi� , O O C�.� O Q O O � C43 O CV N O � J O O O O CA C? O t0 M i7? �L9 LL7 CC1 CQ Q O O O O O Q O CO t0 t13 00 h+ frJ 00 1- u�a o 0 0 0 o u� cv_ r� r. c�s c� cc> p c� O c�i u7 0 0 o c�i ui c�a ua c�i c*i cci ci ctii � F- � � � r � � � � s�c�s u7 u7 aa � m ra r r � gf} tgy ffl �-} 64 6�} H' W d� EA if3 W 4f} L � � � s o a o 0 o a > � �- �' �- W ca o 0 o ei a "Q > � ZU � o ao 0 0 'Q � _ [C °a O. � .�� � � � � p r z- t- s� J � � � o ca o cti o 0 0 0 0 0 o r o 0 J = F�- N rn a�i '�� t��- rn rn �-�- v O :- ei- u7 rn en co c� O u i F- tfl � M m r � � F � 6�-+? 64 � t!-7 C (,� O O O Cs O O O t� O O G� O � � W u7 u� c+� d- �t o � W .c � � Nrn a�cao r`�, rn' � U � � � � � � � r � � � � �n '� � � 0 0 o r� o 0 o ca o a o 0 0 0 ca o o c� o a o 0 0 0 o a o' o -' r- � aa ci � cr ai -I o c�i c6i c�i c i cfi c�i cS �h i. � o i i � � � Fd- u�i rn o � c�v �' o�a c Q c�i ci r: r� ra r: ra � O cr�r` e�i r.� ra` ccYai r: F- � r- ra cv e- co � � F- � �r r� rd ua r- ce� c� r- � r- c� = EFk Ef3 ifl � � � �3 � � � Q � W � Q O O O Co.� O � 4 O O Q Q O 4L tt F' W 1`��- o � � t�p o L � W Ci N �'i t'V M Cfi t0 cS? h- N CO C) � � � v t� 1�- O c+') tn [\ Gi � � � C.� O CO N �f° w .� � � co ci r� r�" cri ra � � pG d= d= ' ra � c�i ers �e O. � T- M CV r CU � � '� EH r r- r' E9 Qp d. Ef3 ER � � � � H � H� kf} H3 � Cf3 69 (fl y3 d Q O O Q O O O O C3 C7 d O O O Q ' c� o 0 0 0 o a o 0 0 0 0 0 0 J o ci o ca o 0 o J o o ui u� � ei ,� r° d o �- a o a o t- � F.. o c�t cv_ co r e� s�i �.`Z.. �� � � � o � U'J Q G1 00 CA t�? IX? N c- � e- c� 1�- r h! I'` tV � r-� 69 a- r Q? O? M F b�} ft# Cf.1 I� �f> te f+• �,, � EJ� � � � lf-} � � 6�4 � � � � W � Y � Q O O O O O O O O O O Q � Q O O O O O BG W 1- t�j o � p o 0 0; c �' w c' `� `n "-a Q o a � � a cv cv co � �t a> � � c�'v c�u � � N o � �- � � � � � � r � rn w = d �� c�'`o' i u��a � t!- 2` r� �- r �r c�r �a �- e- r y� � W � � C.1 � � c� � � � � F� r- ��e- r-. �. � � r �� r� r.� r. a-� r. ,�. o � � � ~� f/� ��� (� f/� �: ... � � � � ��� � :�. f/� �.. � _ � � � J J J � � J J � � J � � � W �� ' � J Cp _ u� � .c� vy F �n � c � h„ Q t ° �a� c �� !- ° �'�-� � �c � pp , c m � � U "_' '_ a� � � 'c� _ � .� � � c tt� � � � U � Q � � � � t� m �,x o�� F t} � 00 � � � '� OtA a� o 0 0 � � p_ � J .ga 2 o ,� <C � � � �� Z V- � � � � � a p_ — p. -L7 --� p � � p ` — — � � -a -� fJ O � � °° v a" ° � v�i � �,i.� a -�-� U d Q Q � m ,�,.n� -�a � ta '� � p o I�' Q- � aa csa — tJ .� � ;;= .� d"_ �- ` a cn — t3 u" sv � � F- 0. � � N U � � � � � � � � Q � v � � � � � � � 11. Q Q = � � °� Nw � o � e�.a, � � °arn� a W � � � � � � °r� ��' � o ..�. o a �- ._ _ o ot- ._ � � m � m -s ra � 5 c:� a s, cn u� � i- .... N- r� 5 v ¢ J ua cn � f- � H d � � � � � r- ev c�3 �r u� to Wh �- tv c� � u� c� l�TtJTICE QF XE PTION To. � Shasta County Clerk FRom: City of Redding County of Shasta Public Works Department P.O. Box 9908$0, 1643 Market Street 777 Cypress Avenue Redding, CA 96099-0880 Redding; CA 96001 Praject T�tle: Ba11 Field Li�htin�Ub�rades at Alta Mesa and South Citv Parks J O #4908 23 (ED 21 20) Praject Location-Specific: Alta Mesa Park and South C�tv Park K-1 F-1 and Ti�;er Fi�ld Projeet Location-City: Reddin� Praject Lacation-County; Shasta Description of Project: As nart of the Citv of Reddin�'s Ener�v Effieiencv Economi� Recave Plan (EEERP� the proiect will enhance the sport field lighting systems Work in�ludes retrofittin existing li�ln�systems and the remr�val and replacement of existin�Ii�ht svstems which includes the installation of new li�ht�oles concrete foundahons,conduxt, wirin� h�ht assemblies fixtures panels and associated electrical equipment The removed rnaterlals w111 be dzsbased of in accordanee with state and local procedures All work wi11 occur on or within Citv propert�. ¢ Name af Public Ag�ncy Approving Projecte Citv of Reddin� Name af Person or Agency Carrying Out Project: Kurt Maire, Project En�ineer Exempt Status; (check one) ❑ Mznisterial-[Section 21080(b)(1); 15�68] ❑ Declared Emergency [Section 21080(b)(3); 152b9(a)] ❑ Ernergency Project [Section Z1080(b}(4); 15269(b)O� � Categorical Exemption. State type and secti�n number: S�c. 15341(a&d). Existing Facilities ❑ Statutory Exemptions. State code number: Reasons why project is exempt: Class 1 exemntions include the operation repair maintenance or minor ' alteration of existin�public facilities and infrastructure involvina ne�li�ible or no expansion of use The pr�o`ect has been reviewed for sensitive resources such as threatened or endangered sbecies or their habitats sensitive ve�etation communitles triballands or tribal cultural resources The proiect has no potential to have a s��nlficant effect on the enviranment Lead Agency Contact Person: Amber Kelley Telephane» 530.225.4046 If Filed by A�plicant: 1. Attac�certified document af exemption finding. 2. Has a notice of exemptian been filed by the public agency approving the project? ❑ Yes❑Na Signature.� d�w%���,�, �-'�r"•- Date'-,���'� -��.�7 � Titie: EnVirc�nrnental Com�liance Manager ❑ Signed by Lead Agency Date received far filing at C1PR: ❑ Signed by Applicant � � � ��" CITY OF REDDING � � `y REPORT TO THE CITY COUNCIL MEETING DATE: Apri120, 2021 FROM: Chuck Aukland,Public ITEM NO. 4.11(a) Works Director ***APPROVED BY*** � ��n � .�.._ s.N,.�� � � � ��� ukl�n�l,H'ciblic Wc�aks L'��reGt ' 4.�'817421 ry ip}�in,�C"i ana � 4r']2/2421 caulcland@ci.redding.ca.us btippin@cityofredding.org SUBJECT: 4.11(a)--COVID-19 Economic Stimul�us Package Projects Recommendation Authorize the following actions relative to the City of Redding's COVID-19 Economic Stimul�us Package projects: (1) Accept an update on project progress; and (2) Ratify approval of the City Manager award for the Ball Field Lighting Upgrades at Alta Mesa Park, Softball Park, South City Park Kiwanis No. 1, and Tiger Field (C19-LS-01) to Builders Solutions, Inc., in the amount of$463,16$. Fiscal Impact The City Council (Council) previously approved an allocation of$9 million in Greenhouse Gas (GI�G) Cap and Trade auction proceeds to be used for projects that reap an energy savings benefit to the City of Redding (City). To date, the City Manager has authorized purchases and projects totaling over $2.4 million and a consulting services agreement for engineering support for just over $1.2 million. AlteNnative Action The City Council (Council) may choose to not accept the project status report and provide further direction to staff. Background/Analysis On Tuesday, April 21, 2020, the Council unanimously approved the City of Redding Economic Response Plan. Included in the plan is the allocation of $9 million in Cap and Trade auction proceeds to be used for several projects (Program) associated with the Loca1 Economic Stimulus Package that equates to a savings in energy costs for the City. On May 5, 2020, the Council. authorized the City Manager to execute agreements, purehase orders and eontraets associated with the Program to ensure an expedited delivery schedule. The Council also directed staff to provide regular status updates on the Program and ratify all City Manager awards. Report to Redding City Council Apri112, 2021 Re: 4.11(a)--COVID Economic Stimulus Program of Projects Page 2 As directed by the City Manager, staff has endeavored to break up most of the work into smaller contracts, values lower than $500,000, with the idea that local contractors and vendors will compete better due to lack of mobilization costs and other local advantages. However, the City has liinited control because these are Public Works contracts and must be awarded to the lowest responsible and responsive bidder in accordance with State law. To date, staff has awarded 10 projects totaling over $2.4 million, including the recently awarded Ball Field Lighting Upgrades at Alta Mesa Park, Softball Park, South City Park Kiwanis No. 1, and Tiger Field which is presented to the Council for ratification, as we11 as lighting improvements at other sport fields, the Library, the Corporation Yard, and several purchase orders and on-call contract services for lighting, plumbing, mechanical work and equipment. SiY projects have been completed, and seven of the 10 projects have been awarded to contractors with local offices. The project presented for ratification includes installation of City furnished lighting equipment to replace, add, and enhance sport field lighting systems at the aforementioned spaces. The work includes removal and disposal of existing lighting systems, and installation of City furnished light poles, precast concrete foundations, grounding, and pole top luminaire assemblies, as well as furnishing and installing cast-in-place concrete backfill for pole foundations, and wiring and raceway to lighting fixtures and electrical equipment. The design consultant has completed the pre-final design for the LED Lighting Retrofit at City Hall and Police Station Project and staff expects to advertise the project for bids this month. The design consultant has also completed draft design packages for solar improvements at the Fire Stations and mechanical improvements at the Aquatic Center, performed preliminary evaluations and recommendations for the mechanical and plumbing projects, and is preparing design packages for several of the mechanical and plumbing projects. The attached Project Status Report provides more detailed information on project stat�us and costs. Staff will continue to return to the Council monthly to provide progress updates. Council Pr�iority/City Manager Goals � Budget and Financial Management — "Achieve balanced and stable 10-year Financial Plans for all funds." � Communication and Transparency — "Improve the quality of communication with the public and City employees to enhance knowledge and increase transparency to improve public trust." � Government of the 21st Century — `Be relevant and proactive to the opportunities and challenges of today's residents and workforce. Anticipate the future to make better decisions today." � Economic Development — "Facilitate and become a catalyst for economic development in Redding to create jobs, retain current businesses and attract new ones, and encourage investment in the community." Attachments Notice of Award Project Status Report OS-OS-20 Staff Report(available online) 04-21-20 Staff Report (available online) C I T Y {� F �� In�terna� +�on�r��nica�� n � � � �� _ � v �� c � L � � � � �; ���- DATE: January 3, 2023 TO: Barry Tippin, City Manager FROM: Chuck Aukland, Director of Public Works SUBJECT: Request for Increase of Project Contingency Funds Ball Field Lighting Upgrades at Alta Mesa Park, Saftball Park, South City Park Kiwanis #l, at Tiger Field Bid Schedule No. 5186, Job No. 4908 Recommendation: Approve an increase to the project contingency budget for the completion of subject Project- Bid Schedule No. 5186. Background/Analysis: In accordance with the Council Approved Authority to award energy saving contracts related to the Green House Gas projects, as part of the Local Economic Stimulus, an increase to Project Contingency Funds (4908-24) is requested. Additional contingency funds are necessary to cover the change order request to increase the contract scope of work necessary for the engineering re- design of the Tiger Field portion of this project as existing field conditions did not align with the original design intent. The consultant prepared design called for new lighting fixtures to be installed to existing poles and arrays and the addition of a control and monitoring panel tied into the existing switchgear. Upon field review of the existing equipment, it was discovered that existing electrical system as a whole lacked sufficient grounding and the necessary voltage requirements to operate the City furnished Musco Lighting equipment. It was also discovered that the existing wiring within the poles was unable to be removed to install the new lighting conductors and necessary ground wire at each locatian. Consequently, the work required for a functioning lighting system includes new switchgear, new electrical subpanel, removal and installation of all conductors for field lighting, installing new EMT conduit on all existing poles for conductor runs and the addition of several pull boxes was required to install the new Musco equipment. Additionally, REU facilities feeding the switchgear were also found to be out of compliance with ` current REU standards. The upgrades to REU equipment include installing a new vault with a pad mounted enclosure, new transformer and concrete pad, new primary feeders and conductor runs and security fencing around the new transformer and switchgear. A transfer of$340,000 from the available EEERP Project Funds is necessary to fully fund these change orders due to the extensive redesign. The foliowing table itemizes the praposed revised pro�ect funding allocations, Current Requested Newly Expencied Balan�e Authorfzed Increase Authorized Pro°ected Pra°ected Canstruction 463,168;00 O.OQ 463,168.OQ 463,168.OQ �.00 Cnntract Contingency SO;OOO.OQ 340,OQ0.00 39Q,OQO.QO 3$O,OdQ.04 10,000.00 Construction 12S,ODO.QO O.QO 125,OOO.QQ 12Q,000.00 5,000.00 Management City Manager 0.00 Q 00 0:00 0.00 O.QO Funds Total $638,168.00 $340,0OO,OD $978,16$,QQ $963,168.OQ �15,000.00 There is currently a balance of$2,365,846 af unencurnbered fiznds avarlable in EEERP Pro�ect Funds which is adequate to fully fund this cost lncrease: Please call me at 245-7155 or Josh Anthony at 225-4175 should you have any questions or need additianal infoxmation. ��� //{ �2..-� Citv En�ineer p�t� Approved: _ .� .:�"�,,.'" City Mana Date ca/mk Attaehments: Council Report May 5, 2020 Inf�rmal CM Pro�ect Award March 24,2021 c: Construction Manager Resident Engineer Finance � � , c � � It�T���t�:� . � _ . �C3 iV[tVi tJ I�I I CATI C?1[�I DATE: March 24, 2021 GODE; �S 5186 TQ: Barry Tippin, City Manager FR�M: Chuck Aukland, City Engin�er SUBJEGT: Recommendatian of Cc�ntract Award Bid Schedule Nt�: 518� Ball Fieid Lighting Upgrades at Alta Mesa Park, Softbal! Park, South City Rark Kiwanis#1, and Tiger Field The Gity Manager h�s been deleg�ted the authori�y tca award energy�avir�gs contracts related ta the Gr�en Hous�G�s fundin9 approved by the City Council an May 5, 2U�G, as part af th� Local Econ�mic Stimulus. Attached is a tabulatian raf bids received and opened on March 23, 2��1, for this pr�ject. The iaw bid`in the amount of$463,168 was received from Builder Sc�lutie�ns, Inc., c�f Redding. Th� engineer's estimate was$4�1,51{3. Recc�mmendation It i� rec�ammended that fhe Gity Manager. 1. Award this project to Builder Solutions, Inc., in th�amount af$463,'1�8, 2. Rpprov�an additi�naf$50,�00 tQ'cover th�cast of cantract ch�nge orders; 3: Approve an additic�nal$125,�00 for construction manag�rn�nt, for a total of'�638,168; and 4. Find the projecfi is Categorically Exempt from the California Environmental Quality Act per Section 153Q1{a &d)—Existing Fa�ilities Gost Sumtnary It�m Estimated C�nstruction Contra�t+ Contingency ; $5'13,16�.00 Contract Administratian, Inspection, Testing $125,000.00 Totat Prc�Ject ca.sts $638,168.00 �ackgrround This project in�ludes installation caf Gity furnished lighting equipment to re�lace, add, and'enhance sport field lighting systems at the �ity's Alta Mesa Park, Saftball Pa�k, Sou#h City Park Kiwanis#'I, �nd Tiger �eld. Th�work includes remoual and dispc�sal caf�xisting lighting systems, and install�tion af Gity furnish�d light �ales, preca�t concrete f�undations, graunding, and poletop luminair� assembii�s, as well as furnishing and installing cast-in-place cancrete backkfiiill ft�r p�l� foundatitrns, and wiring and raceway to lighting fixtures anc! electrical equipment; as shown in the Pl�ns. At Tiger field, fihe w�rk will include retrofitting ti�e existing lighting systems and existing poles,wiring, and'raceways will be utiPized: Atta�chm�nts Bid Tab � Natice of Exempti ;�,��.�"��1 City t e�r C?ate APP,�2QVE�: . � � �� �r � � � '€� �:I��/ ��ft� ` . _ C���� r.; � 0 o a a o o � v� � o c�v N o � 0 'C a a o a a o � � � � a�.y h M co � �1- ua o 0 o a a � cv_r. r- c� rn <,c> 0° � � u�'i � �.�n v� o W � � c�r� u�i c� a�o Q`p rv v � � � � � Q Z V � �s � � � � � o a o 0 0 0 } _ ��., wF= f.�� oo 00 0 0 '� � NZ u� o oa a o ,� � = a � � u�'au�i � e��- J � � � � 0 0 o a o o `� a o -� ui eci ri rr �r ci .= r = Fq-� Nrn atOoo � rn rn fQ- � Q t- v ui ai �ci cfl ri O � F- �s t� M c� �- � �y � N e- e- �- �. C 69� #H 69 �j O � o 0 0 o a o � � W �:ci ui ri v rr o W .cZ � c°'v_ rn ot°oo °r.' �'rn ~ U � = a � z �4 � M M r � = Q�„ ��'' lf� EF? ff� � O 4 O O O p � O J � O O O O Q O p Q ti O o�0 M C�n. O � ", Q N t� N cYi 4D � E^ t� O�'? O t�il' N � d�j Li F' t�- h- C7 t+? tt7 1`� r C � tLt O h 1`- M t�. � h- f- � t�Y r sCV- � � � C � � � h�� � li� e��- = 69 6FT 6� � � � ff# f�3 t� � ��q o � � � o o a a o a y� o0 0 0 0 0 �- t/} F,= � P~� t] a�,� t�i t�0 O 3G LEJ � N ai N M CO i � � � Z U r. r• a c� �n r. o Z U � cr.�, o c�a c�`v_ � � cof o r: r: ri r� (W,ry � = a. fA �^ M N r t4y � � Ll. �� !`�� � tJ e�m- � m � 6S 69 69 � .'�'"� ({� Gt} 64 f�# � � Z O O C'] G7 Q O O Q O O O O O O Q O O O O O Q p � J o ci ci o o ci e� J � �; ,,� � r. � e� o .- a o 0 0 .- c� o a co a �n u�'-, � � r� cv cv_ c� �- � � � � p o aci rn r� ao cv �,,, h- cv_ cv r- er cv_ a QF- F' � � :� � � .��. ,�"�� a �s � m n � ti r�. � � � � � � � � � � � � � o c� o o a a � 0 0 0 0 0 0 0 0 0 0 0 0 0 a' w E= CWj o 'nT-' o 0 o a � E' � o o c'�o o u� �.�`n n' � � �= o allo a�i" c� o c��' � z aV—, cv_cv_ r. �r cv o W � .-' t�"� f� � I� Z � � � a�- � � � �- EF1 4fl C�'} f�- uN'7 1- V tta F» c,a Cj tft � � � _ �, �. � � r r c- r- r e- � e- r �- �- �- r _ � � � = J J J J J � � = J J J J � J CL d'' � Cn W � � J � o � � � v+ H � � � � F 4 �t' ; Ct3 jy � � � o �.v � •� 0 � f�J t° m .x Y .� •� � C) � m �c Y � � tL' !!i a> � Z p <C � � � c t- Z � � x � � � � F � � � O � � a o- Q ,v J' O � a c � p- � 'i °' � � m . �- C�.. p '� N m ,�..a� zs U �'- � o d' � o" a�i ts U av O O �.' d ` N t� � C� � tJ.. � J d,' n- � N � m C� Lt' � ,^,, � ,Q � Z e� cv ,ro N � :� .t] w � �- ° Q v a� vj � ;� � .� c`o W a ¢ t� ;t� '° �y uu cv o c,�,u � � � m � � F- ua � c ca -� � � m a� w t- � m -°s ci G ? c.� <t � �n° cn° � F= � O w o = cn o or- .� °' p F— o � ca ¢ �, cncn � �- � E... � W r' N M �Y l(� tfl (J�,J r Cy M c!' ln tp � Q TICE UF XE PTION Toa � Shasta County Clerk F�tot�t. C�ty of Reddin� C+ounty of Shasta Public Works Dep ent P.4. Bc�x 990880, 1643 Market Street 7"77 GYpress Avea�ue ��(�t�111�, �t� ���}��-{}��� ��t�{�TTI�,��. ��?��1 Praject Title: Ball Field Li htin U rades at Alta Mesa and�outh Ci Pa�:ks J,t�. #4948-23 ED-21-2Q Froject Lacatian_Specific: A1ta Mesa Park and South Cifiv F`ark K-1 F-1 and Ti��r Fieid Pro,�ect Locatio;n—Gity. R.eddxn� Prc�ject Locatir►n—Caunty; Shasta Description of 1'ro;�ect: As t�art of the Citv of Reddin�'s Ener�;v EfficiencY Econornic Recovery Plan fEEERP) the ro'ec�will en.hance the s nrt field li ht�n s sterns. Wc�rk includes retrc�fitti�n existin li htin s stems:and the removal and re lacement of existin li ht s stems �vh�ch includes the�nstallation ofnew li ht oles cc�ncrefie faundations conduit wirin I1 ht asseml�lies fixtures anels and associated electrical e ui meant.The removed materzals w�ll be dis ased of xn acc�rdance with state a�d local rc�cedure�. t�ll worlc will occur on or within�zt ro�erty. Name of Public Agen+�y A�praving Proje+ct: Citv of Reddin� Name uf Ferson or Agency Carry�ng Cl�t Pro,�ect: Kurt Maire. Proie�t En in��r Exempt Status: (`check vne) CI Ministerial-[Section 21��0(b)(l); 15268] Cl Declared Emergency [Section�1080{b)(3); 152�9(aj] ❑ �mergency Project [Sect�on 21080(b)(�}; 15269{b)O] � Categorical Exer.n�tion. State type and section numberd Sec. 15301(a&d} Existin�Facilities [7 Statutory Exempt�ons. State code number: Reasons why projec�is exempt: Class 1 exemptions include the c�neratron repair m�int�nance or minc�r alteration ofexistin ubli� facilitles and infrastructure invalvin ne li ible �ar no ex ansion of use. The ro'ect has b�en revi�v�ed for sensltive z°esources such as threatened ar endan ered s ecies or their;hab�tats sensitive ve etation co unitres trib�l lands ar tribal cultural resaurces. The ro"��t has no' otenti�l to h�ue a si�nificant effect on the envirc�nment Lea+d Agency C'ontactPerson:Amber Kelle� Telephone: 53�.225.4046 If�'iled by Apglicant: 1. Attach certified do�ument t�f exemption finding. 2. Has a notice af exemption been filed by the public agency appr+�ving the project? ❑ Y�s ❑N� Signature: �"' G� ` L1ate: ,�2�-� - �,� � Title: Enviranmental Cornpliance Mana�er ❑ S�gned by Lead Agency Date received for filing at f�PR; CI Signed by Applicant qP 4 . m � �I Y I REPORT T0 THE CITY C�,IUNCIL ETING DATE: May 5,2020 FROM: �arry Tippin, City Manager ITEM NO. 9.1(b) ***APPROVED BY*** btipp►n a"�,,}cityofredding.org �u.�. .��5�.�,�-'� ry ip�ir�.Ci ` �ana�e �f?7J?0'?(} btippin@c'rtyofredding.org SUSJECT: 9.1(b)--Consider authorizing the City Manager to award energy savings contracts, purchase orders, and agreements related to the Green House Gas (GHGr) funding approved by the City Council as�art of the Local Econornic Stimulus. Recvmmendatiorz Authorize the City Manager ta award any public works cantract, purchase order, or agreements, of any value, associated with the $9.5 million GHG funding approved as part of the Lacal Economic Stimulus Package. �'iscal Impaet The City Council has previously approved the allocation of $9.5 million in Cap and Trade auctlon proceeds to be used far projects that reap an energy savings benefit to the City of Redding. There is no further fiscal impact to granting authoxity ta the City Manager ta execute the agreement�, purchase orders, and contracts associated with these project5. There may, hawev�r; be an added benefit af seeing the rnoney infiised more rapzdly intc�the local economy. ACternative Actron The City Council could choose to not authorize the City Manager to execute the agreements, � purchase orders, or contracts associated with the Gap and Trade distributian funds ta expedite delivery ofthe work. This would lengthen the process to use the authorized funding. BackgroundlAnalysis On Tuesday, April 21, 2020, the City Council unanimously approved the Econarnic Response Plan, Included in the pian is the allocatian of$9.5 mrllion in Cap and Trade auction proceeds to be used for projects associated with the Local Economic Stimulus Package that equate to a savings in energy costs for the City of Redding. Bp authorizing the City Manager to negatiate, execute, and direct the agreements,purchase orders and contracts, staff can proceed with rapidly assigning the wark and awarding bids. The benefit to this�s being able to see the Cap and Trade action proceeds go to wark as soon as possible in the community, and thereby providing the local Report to Redding Ciry Council April 28,2020 Re: 9.1(b)--Authorize City Manager to award energy savings contracts Page Z economy a direct opportunity to see a quick positive impact to jobs and business activity. The projects within the package may include, , LED light replacement in City facilities, reraofing and some solar installatian at Fire Stations, replacing largely older and heavy energy using equipment with newer more efficient equipment, and additional energy saving projects to be determined Council Priority/City Manager Goals • Budget and Financial Management — "Achieve balanced and stable 10-year Financial Plans for all funds." � Public Safety— "Work to improve all aspects of public safety to help people feel secure and safe where they live, work, and play in the City of Redding." � Communication and Transparency — "Improve the quality of communication with the public and City employees to enhance knowledge and increase transparency to improve public trust." • Government of the 21St Century — "Be relevant and proactive to the opportunities and challenges of today's residents and workforce. Anticipate the future to make better decisions today." • Economic Development — "Facilitate and become a catalyst for economic development in Redding to create jobs, retain current businesses and attract new ones, and encourage investment in the community."