Loading...
HomeMy WebLinkAbout _ 4.11(a)--Approve Increase to Project Budget for Redding Aquatic Center 50 Meter Improvement Project CITY OF REDDING REPORT TO THE CITY COUNCIL Recommendation Approve increases to the project budget in the amount of $150,000 for the completion of Bid Schedule No. 5222, Redding Aquatic Center 50 Meter Pool Improvement Project as outlined below for additional improvements: (1) Increase of $20,000 to the construction management budget, bringing the construction management total to $138,000; and (2) Increase of $130,000 to the construction contingency budget, bringing the construction contingency total to $240,000. Fiscal Impact The Redding Aquatic Center 50-meter Pool Improvement Project is being funded by the General Fund. The proposed $150,000 increase in funding is available in the existing allocation for the project in the Parks Division Budget. The total project cost, including the proposed increase, is expected to be $1,950,000. Alternative Action The City Council (Council) may choose to reject the request and provide alternative direction to staff. Background/Analysis On November 2, 2021, the Council awarded the construction contract for the project to Western Water Features, Inc. The project includes the removal of the existing 50-meter pool plaster and tile, as well as the removal of the activity pool water slide. MEETING DATE: February 21, 2023 ITEM NO. 4.11(a) FROM: ***APPROVED BY*** caukland@ci.redding.ca.us btippin@cityofredding.org SUBJECT: 4.11(a)--Approve Increase to Project Budget for the Redding Aquatic Center 50 Meter Pool Improvement Project Chuck Aukland, Public Works Director Report to Redding City Council February 15, 2023 Re: 4.11(a)--Approve Increase to Project Budget for Redding Aquatic Center 50 Meter Improvement Project Page 2 During the course of construction, conditions in the field warranted design revisions to meet the original project intent. After the resurfacing of the 50-meter pool was completed, the water-stop in the expansion joint failed. The pool is leaking a significant amount of water and will continue to do so until it is repaired. The consultant design team recommends replacing the expansion joint with a poured-in place repair. The scope of work for this repair includes the following: providing daily moisture conditioning to the new plaster finish, saw-cutting the old expansion joint (approximately 40” wide by 95 feet), removing and disposing of concrete, placement of dowel in new rebar, using shotcrete in new concrete section, tiling of new sections to match existing sections, repairing any damaged plaster areas (if needed), and finally filling and balancing the pool. The noted changes will result in the contract bid item exceeding the bid quantity and the additional time needed will increase the construction management services required. The additional work will cause the project budget to exceed the awarded amounts. An additional $150,000 is requested to cover increases to the construction contingency ($130,000) and construction management ($20,000) project components. COST SUMMARY Item Awarded Amount Projected Amount Increase Contract Administration, Inspection, Testing $118,000 $138,000 $20,000 Construction Contingency $110,000 $240,000 $130,000 Revised Totals $228,000 $378,000 $150,000 Environmental Review This action is not a project as defined by the California Environmental Quality Act (CEQA) Guidelines, and no further action is required. On November 2, 2021, the Council determined that the Redding Aquatic Center 50-Meter Pool Improvement Project is categorically exempt from review under the CEQA Guidelines, per Section 15301(d) – Existing Facilities. Council Priority/City Manager Goals • This agenda item is a routine operational item. Attachments Previous Staff Report 11-2-21 CITY OF REDDING REPORT TO THE CITY COUNCIL Recommendation Authorize the following actions relative to Bid Schedule No. 5222 (Job No. 7336) Redding Aquatic Center 50 Meter Pool Improvements Project: (1) Award to Western Water Features, Inc. in the amount of $908,765; (2) Approve an additional $118,000 to cover the cost of administration and inspection fees; and $50,000 for project development costs; (3) Approve $110,000 to provide construction contingency funding; (4) Authorize the City Manager to approve additional increases in either the construction management or construction contingency amounts up to a total of $15,000; and (5) Find that the Project is categorically exempt from the California Environmental Quality Act per Section 15301(d) - Existing Facilities. Fiscal Impact The Redding Aquatic Center 50 Meter Pool Improvement Project (Project) is being funded by the General Fund. Cost Summary Item Estimated Project Development Costs $50,000 Construction Contract + Contingency $1,018,765 Contract Administration, Inspection, Testing $118,000 Additional City Manager Authority $15,000 Total Project Costs $1,201,765 Project Budget $1,800,000 Project cost components are estimates and some shifting of the project development, construction management, and construction contingency funds may be necessary to balance the MEETING DATE: November 2, 2021 ITEM NO. 4.11(g) FROM: ***APPROVED BY*** caukland@ci.redding.ca.us btippin@cityofredding.org SUBJECT: 4.11(g)--Award Bid Schedule No. 5222 (Job No. 7336) Redding Aquatic Center 50 Meter Pool Improvements Chuck Aukland, Public Works Director Report to Redding City Council October 25, 2021 Re: 4.11(g)--Award BS No. 5222, Redding Aquatic Center 50 Meter Pool Page 2 project within the approved budget. Alternative Action The City Council (Council) could choose not to award the bid for the Redding Aquatic Center 50 Meter Pool Improvement Project and provide staff with alternate direction. If the project is not awarded, the 50-meter pool at the Aquatic Center, as well as the waterslide at the activity pool, will have ongoing maintenance and be in jeopardy of failing. Background/Analysis Attached is a tabulation of bids received and opened on October 14, 2021, for the Redding Aquatic Center 50 Meter Pool Improvement Project. The low bid in the amount of $908,765 was received from Western Water Features, Inc., of El Dorado Hills, California. The engineer's estimate was $1,100,000. Total project development costs for this project are estimated to be $50,000. Project development costs include engineering, surveying, right-of-way, environmental, consultant services, and permit fees. There is $1,800,000 budgeted for the total project. This project includes the removal of the existing 50-meter pool plaster and tile, in addition to the removal of the activity pool water slide. The project will install new plaster, tile, activity pool water slide, and complete water slide refurbishment. Staff has determined that the project qualifies as Categorically Exempt from environmental review under California Environmental Quality Act Guidelines Section 15301. The project area does not have significant values for wildlife habitat or other environmental resources, and the project has no potential to have a significant effect on the environment. Council Priority/City Manager Goals • This agenda item is a routine operational item. Attachments Bid Tabulation Location Map Notice of Exemption