HomeMy WebLinkAboutMinutes - City Council - 1981-05-26 195
City Council Special Meeting
Police Dept. & Council Chambers
Redding, California
May 26 , 1981 12 : 00 Noon
1111 The meeting was called to order by Mayor Pugh with the follow-
ing Council Members present: Demsher, Fulton, Gard, and
Kirkpatrick.
Also present were City Manager Brickwood, Assistant City
Manager Courtney, City Attorney Hays, Public Works Director
Arness , Planning and Community Development Director Perry,
Electric Director Simpson, Superintendent-Electric Mix, and
City Clerk Richter.
AWARD OF BID - Bid Schedule No. 1287 , Hydroelectric Generation
System, Whiskeytown Dam
Electric Director Simpson reviewed his memorandum to Council
dated May 22 , 1981. He stated that the Electric Department
recommends the award of Bid Schedule No. 1287 , hydroelectric
generation system at Whiskeytown Dam, be made to the Brown-
Boveri Corporation in the amount of $2 , 939 ,525 , not including
sales tax or escalation. Escalation for the project is quoted
at $22 , 920 per month after October of 1982 .
Mr. Simpson advised that the recommendation is based on a
technical evaluation made by the City of Redding Electric
Department and an independent technical evaluation made by the
International Engineering Company of San Francisco. Both
evaluations conclude that Brown-Boveri Corporation has provided
the only technically complete bid. He noted that the double
turbine proposed by Brown-Boveri is much more flexible than the I/
turbine proposed by the Jaxon Enterprises and General Electric
Company. Mr. Simpson explained that the water flow from
Whiskeytown varies from 50 to 200 cubic feet per second, and
•
the double turbine is sized to work with this variation and
take full advantage of the water flow. He advised that the bid
is in two parts : 1) $47 ,600 to prepare the necessary documents
to apply for the necessary licenses from the Federal Energy
Regulatory Commission; and 2) Final design, construction,
installation, start-up, and testing for the project. The
contractor will proceed with the second phase of the project
only after the second notice is authorized by the City.
Mr. Simpson stated that the award amount as stated above
includes an estimate for site construction of $600 , 000 based on
First Quarter, 1981 prices. The estimate is a valid estimate
in the opinion of the Electric Department. The sales tax
applicable to the bid will not exceed $105 , 220 .
It is the recommendation of the Electric Department that
Council award this project to the Brown-Boveri Corporation and
authorize staff to notify them to proceed.
Howard Kirkpatrick asked for clarification of the escalation
clause in the Brown-Boveri bid and of the fact that Brown-
Boveri apparently does have the appropriate State license to
construct the project.
Mr. Simpson explained that staff has asked that escalation
costs be shown. Because of the length of time to complete the
project, it would not be feasible to ask for a firm price. He
added that until October of 1982 , there is no escalation.
5/26/81
196
After that time, the Brown-Boveri bid will escalate $22 , 920 per
month. Mr. Simpson noted that that escalation does not include
the $600 , 000 of civil construction work that would escalate
beginning at the time we let the bid. He noted that all
bidders provide for escalation after October, 1982 .
Mr. Simpson asked that the City Attorney address Mr. Kirkpatrick ' s
question regarding the requirement for certain State licenses.
City Attorney Hays stated that the specifications asked that
the contractor on the project be properly licensed. However,
the contractor' s licensing laws in the State of California
state that said requirements do not apply to any construction
carried on within any site , the title of which rests with the
Federal Government. Mr. Hays advised that the subject property
is totally within property that is Federally owned.
Mr. Simpson advised that in the Brown-Boveri bid, the $600 , 000
amount was listed as an estimate and staff has determined that
it is reasonable to firm that bid at $600 , 000 .
Mrs. Gard questioned the notation in the report from Interna-
tional Engineering that there were minor errors in the Brown-
Boveri bid which needed to be clarified, and asked if this had
been done.
Mr. Simpson stated that bidders are required to provide a
workable project. He expects no problems in clarification.
In response to an inquiry from Dr. Fulton, Mr. Simpson advised
that a firm price was not requested in the initial call for
bids. Dr. Fulton also asked if this is a recommendation for
open-ended bids.
Mr. Simpson stated that staff can reasonably project what the
escalation will be, based on when construction should begin and
labor statistics, so that an unreasonable escalation figure
would be apparent.
In response to an inquiry from Mrs. Gard regarding the E. I .R.
procedure for the project, Mr. Simpson advised that the environ-
mental concerns on the project are minor and may be satisfied
with a negative declaration or environmental assessment. This
will be determined in the first phase of the project with the
preliminary engineering and preparation of FERC licensing
documents. Mr. Simpson explained that the Federal Energy
Regulatory Commission makes the environmental determination as
it relates to the City of Redding receiving the license.
Councilman Fulton inquired about the local firms who bid on the
project and Mr. Simpson advised that these bids were not
technically complete , escalation was higher per month, and the
over-all bids were higher.
Mayor Pugh thanked the Electric Department for its review of
the bids. He stated that Brown-Boveri has an excellent record
and is a highly reputable firm. He also thanked the staff of
International Engineering for their helpful report.
Ron Munk, Jaxon Enterprises, disputed the recommendation of the
Electric Department and International Engineering Company. He
stated that this was an "end-result bid" and the successful
contractor is required to guarantee performance of his design.
5/26/81
;
197
It is a turn-key project. He stated that everything incor-
porated in the design must be submitted to the City and Water
Resources for approval. Mr. Munk felt that because of this
provision, the technical aspects of the bids are almost irrele-
vant. Mr. Munk further noted that the bid specifications
clearly state that the appropriate contractors licenses are
required.
In regard to price, Mr. Munk stated that the specifications ask
for a lump sum amount for construction work and they were the
only bidders to comply with this requirement. He stated that,
had they known they should bid according to 1981 prices, their
bid could have been lower also.
In response to an inquiry from Councilman Kirkpatrick, Mr. Munk
advised that the bid specifications required a lump sum figure
firm until October of 1982 ; that the provision for escalation
was there in the event that approval of all agencies was not
obtained by that date. He stated that inflation of labor
costs, equipment costs, and interest rates are risks assumed by
his firm.
Mr. Simpson advised that Brown-Boveri did not submit a total
firm bid on the civil construction portion of the project, but
submitted an estimate which, based on current figures , could be
firmed at $600 , 000 until October of 1982 , and even with the
escalation estimates, would be lower than any other bids .
Mr. Kirkpatrick asked if the amount could exceed $600 , 000 and
the City Attorney advised that it could; however, given the
standard for escalation, the amount can be firmed and will not
exceed the bid from Jaxon Enterprises. He noted that there is
about a $1 million difference in the bids. Mr. Hays advised,
in staff' s judgment, there would still be a very large gap
between the bids of Jaxon Enterprises and Brown-Boveri .
Mr. Kirkpatrick asked if any bids should have been accepted
without the appropriate licenses. Mr. Hays stated that the •
specifications read two ways and that an addendum was added so
that CH2M Hill could submit a bid. He also noted that standard
language dealing with street jobs was inadvertently left in the
bid specifications. Mr. Hays assured that the contractor for
the job will have the proper licenses.
Mrs. Gard asked the City Attorney if he is satisfied that all
legal requirements have been met for the award of bid on the
project.
Mr. Hays advised that Council is within its authority to award
the bid and that Brown-Boveri meets all the necessary require-
ments and could be awarded the bid for the project.
Mrs. Gard asked if the escalation clause following October
1982 , would remain in accordance with the Labor statistics , and
Mr. Simpson advised that they would revert to the standard
escalation provision and would amount to $27 ,000 per month for
the Brown-Boveri bid, while Jaxon Enterprises escalates $37 , 000
per month.
Mr. Munk stated that the bid specifications should be issued so
that everyone is bidding on exactly the same basis.
Jack Kenealy, attorney representing Jaxon Enterprises, stated
he feels Mr. Simpson is reading something into the bids .
5/26/81
198
Mr. Kenealy stated that the escalation clause does not come
into effect unless construction is delayed beyond October of
1982 . He noted that Brown-Boveri ' s escalation does not end in
1982 but continues until the project is completed. He objected
to the fact that Brown-Boveri did not give a lump sum amount.
Mr. Kenealy stated that with the type of escalation clause in
the Brown-Boveri bid, the City assumes the risks rather than
the contractor.
Mr. Kenealy also felt it is fundamentally unfair to ask for a
lump sum bid and subsequently award the bid to someone who did
not comply with the terms of the bid specifications.
Mr. Kenealy stated that since plans are reviewed by a number of
Government agencies and changes are required throughout the
project, he did not agree that Jaxon Enterprise' s bid could be
considered technically incomplete.
Mayor Pugh asked if, assuming the International Engineering
report is correct that a double Francis turbine would be
necessary, would Jaxon Enterprises be willing provide it
without asking for additional money.
Mr. Kenealy stated it is not certain that the single turbine
cannot meet the production schedule called for in the bid.
Mr. Munk responded that his staff has not had adequate time to
respond to each technical point discussed in the report. He
did state that the specifications require that a certain number
of killowatt hours of power be produced and if that can be
produced with a single turbine and this can be proven, the City
• cannot require a double turbine.
In response to an inquiry from Mrs. Gard, Mr. Hays advised that
the time line for awarding the bid is Monday, June 1.
Mayor Pugh noted that Council is going to award a bid to the
company who is willing to provide the best turbine, with the
longest life and quality of the project as well as for the
lowest bid. The evaluation of all bids includes the long range
• quality of the project.
Mr. Munk stated that the firm they have selected to provide the
turbine has been in business for over 80 years and is world
renowned. They are willing to guarantee that it will produce
the required killowatts of power. He further noted that
Collins Electric, their electric subcontractor, has done most
of the hydroelectric power projects in the state.
City Attorney Hays advised that there is disagreement regarding
the Jaxon bid. He does not see the Jaxon bid as a firm bid.
Caveats, are made on certain items . They make the statement
• that testing of water flows will be done with equipment already
installed at the dam. The equipment they refer to is not in
existence and would therefore be an additional expense.
Mr. Munk stated that this equipment is shown on drawings
obtained from the U. S. Department of Reclamation.
Mr. Hays advised that our people say that they were never
built.
Councilman Kirkpatrick commented that bidding requirements
should be standardized and in the future, bid specifications
5/26/81
199
for projects such as this should be reviewed by staff before
being sent out.
In response to an inquiry from Mrs. Gard, City Attorney Hays
advised that the bidding procedure was changed at the request
of CH2M Hill and the time for submitting bids was extended.
Councilman Demsher stated he is not certain he is ready to make
any decision at this time but proposed that the meeting be
continued until Wednesday or Thursday to give Council Members
time to meet with staff to discuss some of their areas of
concern.
Mrs. Gard stated she would like to have some background infor-
mation on International Engineering.
MOTION: Made by Councilman Demsher, seconded by Councilman
Kirkpatrick that consideration of the award of bid for Bid
Schedule No. 1287 , Hydroelectric Generating Plant at Whiskey-
town Dam, be continued to 6 : 00 P.M. , Thursday, May 28 , 1981 , in
the City Council Chambers. The Vote: Unanimous Ayes
AWARD OF CONTRACT - Preliminary Engineering, Lake Redding Power
Project
Electric Director Simpson reviewed his memorandum to Council
dated May 22 , 1981. He stated that the City has a Preliminary
Permit for the Lake Redding Power Project and is pursuing the
necessary steps to file an application for licensing with the
Federal Energy Regulatory Commission. The Bechtel Corporation
has submitted to the City of Redding a proposed contract for
providing this design. He noted this did not include environ-
mental work and some geotechnical work.
12
Mr. Simpson advised that the maximum on this contract is lute
$100 , 000 , and funds were budgeted for this project in the
1980-81 budget.
It is the recommendation of the Electric Director that this
contract be approved and that the Mayor be authorized to sign.
MOTION: Made by Councilwoman Gard, seconded by Councilman
Demsher approving the recommendation of the Electric Director
as hereinabove stated. The Vote : Unanimous Ayes
ADJOURNMENT
There being no further business, at the hour of 1: 00 P.M. ,
Mayor Pugh declared the meeting adjourned to 6 : 00 P.M. , May 28 ,
1981.
APPROVED:
ayo
ATTEST:
City Clerk
5/26/81