HomeMy WebLinkAboutMinutes - City Council - unsigned - 1994-08-12 - Special Special Meeting, Redding City Council
City Hall Conference Room A
760 Parkview Avenue
Redding, California
August 12, 1994 11:00 a.m.
The meeting was called to order by Mayor Anderson with the following Council
Members present: P. Anderson, Kehoe, McGeorge, Murray, and R. Anderson.
Also present were Interim City Manager McMurry, City Attorney Hays, Electric
Utility Director Lindley, Planning and Community Development Director Perry,
Electric Utility Operations Manager Ryan, Director of General Services
Masingale, Risk Manager Mlinarcik, Electric Utility Power Plant Manager
Heckenberg and Assistant City Clerk Moscatello.
REDDING POWER COMBUSTION TURBINE PROJECT
- Builders Risk Insurance
(R-100-375-550 & E-120-150)
Risk Manager Mlinarcik reviewed the Report to City Council dated August 12,
1994. Mr. Mlinarcik recommended that Council authorize the purchase of a
builders risk insurance policy from Zurich-American in the amount of $66,725
with the stipulation that the $10 million sublimit for earthquake perils
will apply to the entire Power Plant site, not just the Combustion Turbine
Project, and that we agree to purchase property insurance from them for at
least one year after completion of the project. Mr. Mlinarcik stated that
Zurich-American has very competitive prices. He explained that the premium
is based on a $37.5 million project. However, if the project has a greater
value, which he believes it does, the premium will cost more, but it will be
based on the same rate.
Mr. Mlinarcik stated that he asked Zurich-American to look for additional
earthquake insurance and the indications are it will cost $25,000 to $30,000
for an additional $10 million coverage.
In response to Council Member Kehoe's questions about other alternatives,
Mr. Mlinarcik stated that there are very few. He noted that Zurich-American
is buying into this late in the game and during the most hazardous time,
testing.
Mayor Anderson noted that $75,000 was budgeted for insurance costs, and
without the additional earthquake coverage, we are on track.
Council Member Murray asked if staff analyzed the impact on rates by
changing the deductible. Mr. Mlinarcik said there would probably be a
reduction, but it would not be great. He explained that this proposal
maintains the same coverage in existence between MLP Energy and Insurance
Company of North America. Council Member Murray asked if those deductibles
make sense and if they are in line with other projects. Mr. Mlinarcik
answered yes.
Council Member Murray asked if staff has done an analysis of the facility to
determine if earthquake damage would cause over $10 million in damage. Mr.
Mlinarcik pointed out that this is a low earthquake zone area and that is
why we are even able to buy earthquake insurance. He explained that some
work was done to insure against the adverse impacts of an earthquake, but an
analysis has not been done.
Council Member Murray said it would make sense to prepare an analysis of the
high dollar items and estimate the potential for negative impact and
determine if we are overinsured or underinsured. Mayor Anderson agreed that
an analysis should be prepared.
Mr. Mlinarcik explained that $10 million in insurance covers $80-$90 million
of value at the site, and it may not be hard to exhaust $10 million,
including the $4-$5 million deductible. He conveyed that the old policy
included $30 million in earthquake coverage; therefore, if Council believes
it is advisable, staff will insure to a higher level.
Mayor Anderson asked Mr. Mlinarcik to make a recommendation to Council
assessing the need for additional earthquake coverage.
Mr. Mlinarcik clarified that he is requesting approval for the insurance
rate and if the value of the property goes up, the price will go up based on
that rate.
MOTION: Made by Council Member P. Anderson, seconded by Council Member
Murray, to approve the purchase of a builders risk insurance policy from
Zurich-American in the amount of $66,725.00. The Vote: Unanimous Ayes
RESOLUTION
- Contract with Zurn/NEPCO for Completion of Redding Power
Combustion Turbine Project
(E-120-150)
Council Member Kehoe stated that consistent with his position taken at the
City Council meeting of July 5, 1994, and at meetings thereafter, he will
abstain from consideration from this matter.
Electric Utility Operations Manager Ryan reviewed the Report to City Council
dated August 10, 1994.
Mr. Ryan stated that after considerable negotiations, staff and the firm of
Zurn/NEPCO (Zurn) have arrived at what staff believes is a fair and
equitable agreement for the remainder of the construction work for the
Redding Power Combustion Turbine Project. The contract price is
$3,916,866.00 including the cost of Performance, Payment and Maintenance
Bonds.
Council questioned why the contract with Zurn references the contract
between MLP Energy (MLP) and Zurn but does not incorporate a copy of it into
the contract.
Mr. Ryan said it was staff's understanding that Council directed staff to
negotiate a contract with Zurn for the completion of work as it was defined
in their agreement with MLP. The agreement is referenced because it is
Zurn's position that these exceptions and exclusions must be incorporated
into the agreement with the City. Mr. Ryan said he does not see any problem
with the exceptions and exclusions; however, he cannot tell Council there is
not. If Council desires that staff go back and negotiate a different
agreement that incorporates something outside of Zurn's prior arrangement
with MLP, that can be done.
Council Member Murray noted that MLP, in their contract with Zurn, did
certain things the City was not a party to, and the City is now legitimizing
whatever those agreements were. He said his concept of the direction
Council gave staff was to complete the project, not complete the work Zurn
had with MLP.
Mr. Ryan conveyed that Zurn put exceptions in the contract acknowledging
that the City had a different agreement with MLP than Zurn had with MLP.
Therefore, Zurn will not be liable when the City does not see what it
contracted for with MLP.
Council Member P. Anderson asked if Zurn has any problem with the directions
they received from MLP and if the City has any concerns with the direction
MLP gave Zurn. In addition, is Zurn concerned about any of the exceptions
and exclusions, and would staff make changes to the exclusions because we
are not in agreement with MLP's direction to Zurn.
Mr. Ryan stated that staff has not contemplated any changes to the
exceptions. Zurn has included a statement that they believe that with
completion of the scope of work defined in this contract and with work that
remains to be done by others, the City will have a complete and operable
facility consisting of three gas turbine generators sets and necessary
ancillary equipment.
City Attorney Hays noted that the plant is 95% complete, and to the extent
this list is not in the contract, parts of the plant would have to be torn
out and replaced.
Council Member Murray stated that the City bought a turn key project without
being specific about its makeup. The City is now entering into a series of
contracts to complete the project and he is concerned about its makeup. He
wants to clarify that the City is making a conscious choice to move forward
and accept these changes.
Council Member Murray asked if any of the changes that were made between MLP
and Zurn that Council is contemplating ratifying will result in peak power
of less than 70 megawatts or reduce system reliability or longevity over
that originally contemplated by the City of Redding and the MLP contract.
Mr. Ryan said he does not believe that any of the changes will result in
less than a peak power of 70 megawatts. He stated that some of the
conditions are different than the City's agreement with MLP; but, they are
fairly minor in nature in terms of cost or scope. The only immediate
concern is the busbar connections and that will be resolved in consultation
with internal engineering and Black and Veatch.
Council Member Murray clarified that it is the Electric Department's belief
that these changes will not reduce system reliability or longevity over what
was initially contemplated. Mr. Lindley replied that with the exceptions
noted, that is the case.
Council Member Murray asked why there are no holdbacks in the contract. Mr.
Ryan explained that Zurn was extremely reluctant to accept holdbacks;
however, a process is in place that approves payment over the term of the
project in phases. If the City disputes any portion of the work as being
completed, we have the ability to withhold that portion of the invoice.
Once the work is completed and accepted, payment must be made within 20
days.
Council Member Murray asked if it is a good contract. City Attorney Hays
replied yes, it meets the needs of the City and it will result in the
project being completed in a manner that puts it on line as expected. Mayor
Anderson asked if the City is adequately protected. Mr. Hays replied yes.
Council Member Murray asked if the insurance and bonding requirements in
this contract are sufficient to warrant the completion of the project. Mr.
Hays conveyed that the form of bond is the standard City of Redding Public
Works contract bond form. Risk Manager Mlinarcik stated that the
certificates of insurance submitted by Zurn are fine.
Mr. Ryan suggested that Council consider setting up a contingency fund in
the amount of $30,000 to $40,000, subject to the City Manager's approval,
for minor change orders.
Council Member P. Anderson asked if there will be any major cost increases
over the nominal change orders. Mr. Ryan said it is his belief that there
will not be any. Mr. Smith, representative from Zurn/NEPCO, said that is
his belief also. Council Member Murray asked if that statement is limited
to the relationship between the City and Zurn/NEPCO or the relationship
between the City and completion of this project. Mr. Ryan said it relates
to the relationship between the City and Zurn/NEPCO.
Council Member Murray said he sees no provision for change orders relative
to the entire project. He suggested that staff prepare a staff report
requesting authority for a contingency fund for the entire project. Mr.
Ryan said staff will bring a report to Council for consideration.
Council Member McGeorge noted that because of this project's background, the
City Attorney and Electric Department have thoroughly reviewed this contract
and it is probably as close as possible to meeting the City's needs at this
particular point in time.
Council Member Murray pointed out that the contract contemplates Zurn using
certain subcontractors, but it is Zurn's responsibility to finish the job
whether or not those subcontractors participate in its completion. He said
there is concern about the subcontractors in the community who contracted
under the original City/MLP contract who may not have been paid what they
were entitled to. City Attorney Hays clarified that this contract does not
address that issue.
Mayor Anderson noted that Black & Veatch are listed in the contract as the
City engineer and given considerable authority to halt the job and change
things. He asked what their responsibility and liability is in regard to
completion of the contract. City Attorney Hays stated that if, based upon
their review, something should be shut down, Black & Veatch will consult
with staff to determine what to do. Mayor Anderson questioned why someone
on staff did not have that authority. Mr. Hays explained that there are
parts of the project that staff may not be sufficiently educated about, so
Black & Veatch were brought in.
Mayor Anderson asked if Black & Veatch has reviewed the entire contract and
feel that this will give us a complete project. Mr. Hays replied yes. Mr.
Ryan stated that Black & Veatch will provide the City with a letter stating
that they know of no reason why the project will not work.
MOTION: Made by Council Member Murray, seconded by Council Member McGeorge,
that Resolution No. 94-223 be adopted, a resolution of the City Council of
the City of Redding approving the contract between the City of Redding and
Zurn/NEPCO, for the completion of the Redding Power Combustion Turbine
Project, and authorizing the Mayor to sign same. Voting was as follows:
Voting was as follows:
Ayes: Council Members - P. Anderson, McGeorge, Murray & R. Anderson
Noes: Council Members - None
Absent: Council Members - None
Abstain: Council Members - Kehoe
Resolution No. 94-223 is on file in the office of the City Clerk.
DISPOSITION OF COMBUSTION TURBINE PROJECT EQUIPMENT
- Stored at Pittsfield,
Massachusetts
(B-050-100-700 & E-120-150)
Electric Utility Power Plant Manager Heckenberg reviewed the Report to City
Council dated August 11, 1994. Mr. Heckenberg stated that surplus equipment
not utilized in the City's combustion turbine project was stored by MLP
Energy (MLP) in Pittsfield, MA, until such time as its final disposition
could be determined. The warehouse owner, Robert F. Naples Associates,
Inc. (RFN), has notified the City that it is abandoning the warehouse and
advised the City to remove its equipment or enter into a lease agreement
with the new owner. RFN has offered to purchase the surplus equipment for
$10,000 and waive any storage costs incurred to date.
It is the recommendation of staff to accept the offer of $10,000 from RFN
for the sale of surplus equipment.
Council Member Kehoe questioned what the value of the equipment is. Mr.
Heckenberg stated that the value was determined by the quote offered by RFN
and the Belyea Company, $10,000 plus waiver, and $8,500, respectively. He
explained that there is not a great deal of interest in the equipment, and
the shipping charge to Redding is $35,000.
Council Member Kehoe asked what the cost of the equipment was to the City.
Mr. Heckenberg explained that the cost was included in the total purchase
price of the combustion turbines. He added that the equipment is leftover
and essentially junk.
Council Member Kehoe asked why the City was paying rent to store it. Mr.
Heckenberg conveyed that MLP was storing the equipment.
He explained that the City and MLP entered into a development agreement and
we were not calling their shots. Staff is trying to clean up the situation.
Council Member Kehoe asked if any of these items would be repurchased. Mr.
Ryan said no, the City was lucky to find a buyer.
MOTION: Made by Council Member P. Anderson, seconded by Council Member
McGeorge, that Resolution No. 94-224 be adopted, a resolution of the City
Council of the City of Redding declaring certain combustion turbine project
equipment stored at Pittsfield, Massachusetts, as surplus; authorizing the
sale of said equipment to Robert F. Naples Associates, Inc., for the amount
of $10,000.00; and further authorizing the City Manager to execute the
appropriate documentation.
Voting was as follows:
Ayes: Council Members - P. Anderson, Kehoe, McGeorge, Murray & R.
Anderson
Noes: Council Members - None
Absent: Council Members - None
Resolution No. 94-224 is on file in the office of the City Clerk.
Council Member Murray asked for a report on equipment stored in Texas and
asked if an appraisal had been prepared and if staff has a plan for the
equipment. Electric Utility Director Lindley stated that it is the
department's plan to move forward and sell the equipment as soon as
possible.
Electric Utility Operations Manager Ryan conveyed that staff received a
letter yesterday from Natole Associates offering to act as a non-exclusive
agent for the City to sell the equipment for 5% of the sale price. Staff
will bring that item to Council for consideration and discuss the status of
the equipment.
Stewart Oliver asked if a process could be implemented whereby a
disinterested third party, such as the City Clerk, could review all
contracts.
Mayor Anderson conveyed that Council is reviewing the entire contract
process. Interim City Manager McMurry stated that the City Clerk is not an
expert on terms and conditions of a contract, the City Clerk is the
repository of contracts.
Mr. Oliver stated that he would like to visit the power plant. Electric
Utility Director Lindley stated that a visitor tour program has not been set
up; however, if Mr. Oliver would give sufficient advance notice so staff
would be available to meet with him, the request can be accommodated.
Interim City Manager McMurry stated that the City is very proud of the power
plant, and there is an impressive amount of work to be seen.
John Hoeflich, 1984 Laurel Avenue, stated that he attended an Electric
Utility Commission meeting wherein several Electric Utility Commissioners
expressed concern about the age of the gas turbine generators and the
availability of parts. Mr. Hoeflich questioned the reliability of the
plant.
City Attorney Hays explained that at the meeting Mr. Hoeflich attended,
several proposals were discussed including one that proposed to use old
generators. The City did not buy that proposal. Electric Utility Director
Lindley stated that the gas turbines are current technology and parts are
still manufactured. Two of the units are brand new and one is
remanufactured.
ADJOURNMENT
There being no further business, at the hour of 12:30 p.m., Mayor Anderson
declared the meeting adjourned.
APPROVED:
_______________________________
Mayor
ATTEST:
_____________________________________
Assistant City Clerk