HomeMy WebLinkAboutReso 94-344 - Approve entering into Public Works Contract Mod CO#1 dated 11/30/94, between COR & Sharrah Dunlap Sawyer, Inc (Contract C-3106) Buckeye Water Treatment Plant Project ® •
RESOLUTION NO. 94-24
IZ
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF REDDING
APPROVING ENTERING INTO PUBLIC WORKS CONTRACT
MODIFICATION (CHANGE ORDER) NO. 1 DATED NOVEMBER 30,
1994, BETWEEN THE CITY OF REDDING AND SHARRAH DUNLAP
SAWYER, INC. (CONTRACT NO. C-3106) IN THE AMOUNT OF
$15,211, IN CONNECTION WITH PERFORMING ADDITIONAL TASKS
FOR THE BUCKEYE WATER TREATMENT PLANT PROJECT.
IT IS HEREBY RESOLVED that the City Council of the City of
Redding hereby approves entering into the above-mentioned
Contract Modification (Change Order) No. 1 in the amount of
$15 , 211.00 , a true copy of which is attached hereto and made a
part hereof.
IT IS FURTHER RESOLVED that the City Manager is hereby
authorized and directed to sign said Change Order on behalf of
the City Council; and the City Clerk is directed to attest the
signature of the City Manager and to impress the official seal of
the City of Redding thereto.
I HEREBY CERTIFY that the foregoing Resolution was
introduced, read, and adopted at a regular meeting of the City
Council on the 6th day of December , 1994, by the following vote:
AYES: COUNCIL MEMBERS: P. Anderson, McGeorge, Murray and R. Anderson
NOES: COUNCIL MEMBERS: None
ABSENT: COUNCIL MEMBERS: Kehoe
ABSTAIN: COUNCIL MEMBERS: None
01
OBERT C. ANDERSON, Mayor
City of Redding
ATTEST: FORM APPROVED:
e, &4e4_'f
G�
CONNIE STROHMAYER, ity Clerk RANDALL A. HAYS, City Attorney
0 PUBLIC WORKS •
CONTRACT MODIFICATION (CHANGE ORDER)
CHANGE ORDER NO.: 1 DATE: November 30, 1994
PROJECT NAME: Surveying Contract, Buckeye Water Treatment Plant JOB NO.: 2733
CONTRACTOR: Sharrah Dunlap Sawyer CONTRACT. NO.: 3106
The Following Modifications to the Contract are Hereby Ordered
The following tasks are amended:
Original Revised Increase
Amount Amount Amount
Task 1 South line Treatment site
to north end Bandana Trail $10,500 $11,380 $ 880
Task 2 Bandana Trail $ 2,700 $ 2,820 $ 120
Task 3 Rock Creek Road $ 3,600 $ 3,900 $ 300
Task 4 Between Rock Creek & Iron
Mountain Roads $ 3,975 $ 4,395 $ 420
Task 5 Iron Mountain/Keswick Dam Rd.
to Dam Structure $ 4,575 $ 7,440 $ 2,865
Task 6 Dam Structure to End Pipe $ 4,650 $ 6,495 $ 1,845
Tasks 7,8 Site Control, Misc. Surveys $ 5,000 $ 5,000 No Change
New Tasks Added:
Task 9 George & Jose Easements $ 3,823 $ 3,823
Task 10 Constr. Survey Across Keswick Dam $ 4,958 $ 4,958
TOTAL ADDITION $15,211
CONTRACT AMOUNT CONTRACT TIME/CALENDAR DAYS
ORIGINAL CONTRACT AMOUNT $38,500 ORIGINAL CONTRACT TIME N/A
PREVIOUS CHANGE ORDERS(ADD/DEDUCT) None PREVIOUS CHANGE ORDER(ADD/DEDUCT) N/A
THIS CHANGE ORDER(ADD/DEDUCT) $15,211 THIS CHANGE ORDER(ADD/DEDUCT) N/A
REVISED CONTRACT AMOUNT $53,711 AREVISED CONTRACT TIME N/A
THE REVISED CONTRACT COMPLETION DATE IS: N/A
OWNER CONTRACTOR DIRECTOR OF PUBLIC WORKS
CITY OF REDDING Sharrah Dunlap Sawyer ENGINEER
BY BY BY
DATE DATE DATE
61.dc