HomeMy WebLinkAboutReso 96-041 - Approving Amendment 3 to the Standard Agreement for Professional Serv between the COR & Martin & Kane, Inc for Engineering Serv related to Diestelhorst Bridge Replacement Project t
,. . , • •
RESOLUTION NO. 96-�
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
REDDING APPROVING AMENDMENT 3 TO THE STANDARD
AGREEMENT FOR PROFESSIONAL SERVICES BETWEEN THE
CITY AND MARTIN & KANE, INC. FOR ENGINEERING SERVICES
RELATED TO THE DIESTELHORST BRIDGE REPLACEMENT
PROJECT.
WHEREAS, the City entered into a Standard Agreement for Professional Services
(No. C-3242) and Amendments 1 and 2 thereto with Martin & Kane, Inc. for engineering
services related to the Diestelhorst Bridge replacement project ("Project"); and
WHEREAS, attached hereto and made a part hereof is Amendment 3 for office
engineering services during construction of the Project, in an additional amount not to exceed
$65,000; and
WHEREAS, this Project is funded 80% under the Federal Bridge Rehabilitation and
Replacement Program for all eligible participating costs, and the remainder from available
traffic impact fees; and
WHEREAS, funds for the construction engineering services are included in the
1995-96 Public Works budget for the Project, and staff is requesting City Council approval
to Amendment 3;
NOW, THEREFORE, IT IS RESOLVED that the City Council approves entering
into the attached Amendment 3 between the City of Redding and Martin & Kane, Inc., not to
exceed an additional amount of $65,000.
BE IT FLTRTHER RESOLVED that the Mayor is authorized to execute
Amendment 3, and the Clerk is directed to attest the Mayor's signature and affix the official (�
seal of the City. y�
�
1
�.
1
. '
� •
Resolution Approving Amendment 3 to
City/Martin & Kane, Inc. Agreement C-3342
I HEREBY CERTIFY that the foregoing resolution was introduced, read and
adopted at a regular meeting of the City Council of the City of Redding on the 2oth day of
February , 1996, by the following vote:
E�YES• COUNCIL MEMBERS' P• Anderson, R. Anderson, McGeorge, Murray and Kehoe
NOES: COUNCIL MEMBERS: None
ABSENT: COUNCIL MEMBERS: None
ABSTAIN: COUNCII. MEMBERS: None
/ - .
DAVID A. HOE, M or
ATTEST:
CONNIE STROHMAYE , C' y Clerk
FORM APPROVED:
�/I/�'�'������:�s. '.��`
W. LEONARD WIN , City Attorney
2 ............ . ........ ... .. .
� •
AMENDMENT 3
TO THE AGREEMENT FOR ENGINEERING SERVICES WITH
MARTIN & KANE, INC., FOR ENGtNEERING SERVICES FOR THE
DIESTELHORST BRIDGE REPLACEMENT PROJECT
Article I - Engineering Services
Engineer will provide the following additional engineering services on a "will call" basis
at the direction of the engineer:
1. Project Management
2. Preconstruction Meeting
3. Falsework Review
4. P/S Shop Plan Review
5. 150 Ton Bored Shop Plan Review
6. Contract Change Order Review
7. Miscellaneous Shop Plan Review
- 8. Miscellaneous Design Questions
Article II - Basis of Compensation
Full compensation for providing the engineering services listed under Article I-
Engineering Services, Amendment No. 3, shall be as follows:
These services shall be provided on a "time and material" basis and
compensation shall be in accordance with Paragraph B, Cost
Reimbursable - Per Diem (Time and Materials), Article 2-Compensation,
Attachment B, to the Standard Agreement for Professional Services,
between the Engineer, the Owner for the Diestelhorst Bridge
Replacement Project.
Services shall be provided on a "will call" basis at the direction of the Owner.
Compensation for the additional services shall not exceed $65,000.
_....... ..
, . � , � •
IN WITNESS WHEREOF, the parties execute below:
For the CITY OF REDDING,
dated this day of , 1996
by:
City Manager
ATTESTED:
by:
City Clerk
APPROVED AS TO FORM:
by:
- City Attorney
For the Consultant, MARTIN & KANE, INC.
� dated this /2 �� day of �e6rua ru , 1996
by: , -�a � �.�,,�E--�
Project Manager
APPROVED:
CALIFORNIA DEPARTMENT OF TRANSPORTATION
dated this day of , 1996
by:
, Local Streets and Roads Engineer, District 2
67.fm